THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT AN UPGRADE OF ALTERNATING CURRENT AC AND DIRECT CURRENT DC ESSENTIAL POWER SYSTEMS ALONG WITH UNINTERRUPTED POWER SYSTEMS UPS REPLACEMENT AT THE CENTRAL HEAT AND POWER PLANT ON EIELSON AFB.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeFA5004 354 CONS PK
NAICS237130 — Power and Communication Line and Related Structures Construction
PSCZ2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-aside8(A) SOLE SOURCE
Pricing typeFIRM FIXED PRICE
Obligations$3.4M
Current contract value$3.4M
Potential contract value / ceiling$3.4M
Start dateJul 21, 2024
Current end dateNov 18, 2025
Potential end dateNov 18, 2025
Latest award activitySep 18, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 18, 2025P00004$24.1KTHE PURPOSE OF THIS PROJECT IS TO CONSTRUCT AN UPGRADE OF ALTERNATING CURRENT AC AND DIRECT CURRENT DC ESSENTIAL POWER SYSTEMS ALONG WITH UNINTERRUPTED POWER SYSTEMS UPS REPLACEMENT AT THE CENTRAL HEAT AND POWER PLANT ON EIELSON AFB.
Aug 13, 2025P00003$0THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT AN UPGRADE OF ALTERNATING CURRENT AC AND DIRECT CURRENT DC ESSENTIAL POWER SYSTEMS ALONG WITH UNINTERRUPTED POWER SYSTEMS UPS REPLACEMENT AT THE CENTRAL HEAT AND POWER PLANT ON EIELSON AFB.
Mar 27, 2025P00002$0THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT AN UPGRADE OF ALTERNATING CURRENT AC AND DIRECT CURRENT DC ESSENTIAL POWER SYSTEMS ALONG WITH UNINTERRUPTED POWER SYSTEMS UPS REPLACEMENT AT THE CENTRAL HEAT AND POWER PLANT ON EIELSON AFB.
Oct 7, 2024P00001$0THE PURPOSE OF THIS PROJECT IS TO CONSTRUCT AN UPGRADE OF ALTERNATING CURRENT AC AND DIRECT CURRENT DC ESSENTIAL POWER SYSTEMS ALONG WITH UNINTERRUPTED POWER SYSTEMS UPS REPLACEMENT AT THE CENTRAL HEAT AND POWER PLANT ON EIELSON AFB.