IGF::OT::IGF P1701 FUELS FACILITY DESIGN
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVFACSYSCOM ATLANTIC |
| NAICS | 541310 — Architectural Services |
| PSC | C211 — Architect - Engineer Services (including landscaping, interior layout, and designing) |
| Parent award / vehicle | N6258310D0408 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.3M |
| Current contract value | $2.3M |
| Potential contract value / ceiling | $2.3M |
| Start date | Mar 26, 2014 |
| Current end date | Sep 30, 2026 |
| Potential end date | Sep 30, 2026 |
| Latest award activity | Mar 2, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Mar 2, 2026 | 12 | $0 | P1701 CONSTRUCT FUEL STORAGE FACILITIES, CAMP LEMONNIER, DJIBOUTI |
| Jul 17, 2023 | 11 | $-5.2K | POST CONSTRUCTION AWARD SERVICES CONSULTATION HOURS |
| Apr 20, 2023 | 10 | $0 | MODIFICATION FOR TIME EXTENSION |
| Mar 10, 2023 | 9 | $0 | MODIFICATION TO CHANGE CONTRACTING OFFICER'S REPRESENTATIVE |
| Aug 5, 2020 | 8 | $0 | NO COST TIME EXTENSION |
| Oct 28, 2019 | 7 | $0 | MOD FOR TIME EXTENSION. |
| Jan 10, 2018 | 6 | $394.6K | IGF::OT::IGF MOD FOR ADDTL PCAS CONSTRUCTION SITE VISIT SURVEY AND TO EXTEND THE CCD TO 31 OCT 2019. |
| Mar 20, 2017 | 5 | $316.1K | IGF::OT::IGF PCAS AND TIME EXTENSION FROM 31 MAY 2016 TO 30 OCT 2019 |
| Feb 29, 2016 | 4 | $23.5K | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO REDESIGN EXISTING PLANS FOR THE TRUCK TURN LOOP FOR TASK ORDER JN02 (FUEL STORAGE FACILITY CAMP LEMONNIER, DJIBOUTI) TO COMPLY WITH THE UPDATED BASE MASTER PLAN. |
| Sep 4, 2015 | 3 | $83.7K | IGF::OT::IGF ADDITIONAL MEETING TO FINALIZE DESIGN |
| Jul 23, 2015 | 2 | $0 | IGF::OT::IGF EXTEND TASK ORDER COMPLETION DATE TO AND INCLUDING 31 MAY 2016. |
| Apr 1, 2015 | 1 | $668.8K | IGF::OT::IGF EXERCISE OPTION FOR 35-100% DESIGN, P-1701 FUEL STORAGE FACILITY |
| Mar 27, 2014 | 0 | $801.8K | IGF::OT::IGF P1701 FUELS FACILITY DESIGN |