Federal contract award

N0001914C0037

CVN 79 EMALS LONG LEAD TIME MATERIAL

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeNAVAL AIR SYSTEMS COMMAND
NAICS336413 — Other Aircraft Parts and Auxiliary Equipment Manufacturing
PSC1720 — Aircraft Launching Equipment
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$1.8B
Current contract value$1.8B
Potential contract value / ceiling$1.8B
Start dateMay 8, 2014
Current end dateJan 30, 2030
Potential end dateJan 30, 2030
Latest award activityMay 21, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 123 of 123 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 21, 2026P00116$15.9MPROCUREMENT OF ECPS 0107 AND 0109 FOR EMALS AND DIRECTED CHANGE FOR ECP 0137 FOR AAG
May 13, 2026P00115$654.7KFY26 INCREMENTAL FUNDING FOR CLIN 9015
Mar 26, 2026P00114$-800.0KDE-OBLIGATION MODIFICATION
Mar 4, 2026P00113$817.0KINCREMENTALLY FUND CLINS 9011 AND 9012
Dec 23, 2025P00112$36.4KADDING FUNDING TO CLIN 6001 FOR PARTS TRANSFER FROM CVN 80-79 EA
Nov 12, 2025P00111$12.4MCVN 80 PILE 2 IMPLEMENTATION INTO PRODUCTION AND INCO HARDWARE
Oct 29, 2025P00110$0ISSUE A DIRECTED CHANGE TO SUPPORT THE REDESIGN AND IMPLEMENTATION INTO CVN 80 FOR ECP-I-EMALS-0022 AND THE IMPLEMENTATION INTO CVN 80 FOR ECP-I-EMALS-0042R4 AND UPDATED ATTACHMENT 23 PBPS
Sep 25, 2025P00109$6.5MTHE PURPOSE OF THIS MODIFICATION IS TO PROCURE ECP-0039 HPU AND INCO FOR CVN 80 AND INCORPORATE COST IMPACT OF FAR CLAUSE 52.246-26.
Sep 9, 2025P00108$3.1MESTABLISH NEW CLINS FOR ECP 0120 NRE, DRAWINGS AND LOGISTICS
Sep 4, 2025P00107$1.9MTHE PURPOSE OF THIS MODIFICATION IS TO INCREASE CLIN 7020 BY $45,267 FOR ECP-I-AAG-0115 AND ESTABLISH CLIN 8003 FOR WT MOD-II SPARES AND FULLY FUND $1,826,164, AS WELL AS UPDATE ASSOCIATED DOCUMENTS.
Jul 25, 2025P00106$3.1MEXERCISE OPTIONS, FUNDING, AND CORRECT LOE ERRORS (REMOVE MATERIAL FROM LOE)
Jun 27, 2025P00105$3.4MINCREMENTAL FUND 3007 AND EXERCISE OPTION CLINS 6010 & 6011.
Mar 6, 2025P00104$797.5KINCREMENTALLY FUND CLINS 9011 AND 9012
Jan 27, 2025P00103$264.2KINCREASE FUNDING TO CLIN 7011 FOR ECP 0042 INSTALL DELAYS.
Dec 16, 2024P00102$5.9MCLINS 1102, 1104, 3007, AND 3008 - INCREMENTALLY FUND
Dec 9, 2024P00101$282.1KOBLIGATE FUNDING TO CLINS 3001 AND 3003. INCREASE FUNDING TO CLIN 6003 FOR ECP 0063 CSA OOB PSB
Sep 26, 2024P00100$1.3MADJUST WT DELIVERY DATES BASED ON ACCELERATION OF CVN 79 SCHEDULE.
Sep 16, 2024P00099$837.1KTHE PURPOSE OF THIS MODIFICATION IS TO INCREASE CLIN 2201 BY $837,061 FOR THE ASSESSMENT AND REWORK OF HPUS ON CVN 79.
Sep 4, 2024P00098$3.6MTHE PURPOSE OF THIS MODIFICATION IS TO ACCOUNT FOR COSTS ASSOCIATED WITH THE MRB DELAY EFFORT, INCREMENTALLY FUND CLIN 1102, 1104 AND UPDATE SECTION J ATTACHMENTS.
May 29, 2024P00097$1.8MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND PAYOUT INCENTIVES.
Apr 19, 2024P00096$3.7MTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE ADMINISTRATIVE CHANGES AND ADD ADDITIONAL SCOPE FOR CVN 80 HARDWARE STORAGE MANAGEMENT.
Jan 30, 2024P00095$17.1MWT OPTION EXERCISE, PUK CNAL, LMM INCOS
Dec 15, 2023P00094$29.5MOPTION EXERCISE, PSB IUID, PRIME POWER INTERFACE SUBSYSTEM (PPIS) TRANSFORMER RECTIFIER (T/R) DRAWINGS
Sep 28, 2023P00093$6.1MSOFTWARE CHANGES, T/R SHOCK CHANGES, DE-OBLIGATION, SHIPPING ADDRESS UPDATE, REVISE GFP
Sep 1, 2023P00092$6.1MTHE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION LINE ITEM NUMBER 7024.
Aug 8, 2023P00091$6.5MWATER TWISTER II, CENTER DECK DISPLAY, DEADLOAD AXLE, MAGNETIC LATCH
Jul 20, 2023P00090$829.7KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE THE DELTA FUNDING FOR THE PARTS ESTABLISHED IN P00081 AND P00083.
May 25, 2023P00089$342.1KADDING FUNDING IN SUPPORT OF CLIN 6003 FOR AAG SW DC UNDER 22-0150/ME-A
May 15, 2023P00088$5.0MTHE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND CLINS 1101, 1102, 1103, AND 1104 FOR CVN 79/80 INSTALLATION AND TEST SUPPORT.
May 8, 2023P00087$203.4KDIRECTED CHANGE EQUITABLE ADJUSTMENTS FOR MOTOR GENERATORS AND HARDWARE ACCELERATION
Mar 21, 2023P00086$338.8KEMALS AFT BOGEY DIRECTED CHANGE AND HAMPTON STORAGE IF.
Mar 9, 2023P00085$2.7MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE STORAGE SPACE FOR CVN 80 EMALS AND AAG SHIPSET ASSEMBLIES IN BUILDING 12 OF GA'S TUPEOLO FACILITY.
Jan 19, 2023P00084$3.4MTHE PURPOSE OF THIS MODIFICATION IS TO FUND INSTALLATION AND TEST SUPPORT FOR CVN 79 AND CVN 80.
Nov 17, 2022P00083$0TO UPDATE THE DATES IN EXHIBIT AM FOR COSAL AND REVISE THE INSPECT BY LOCATION IN DFARS CLAUSE 252.232-7006.
Oct 21, 2022P00082$0FACILITATE CLIN COMPLETION ON CLINS 0001, 1001, 2001, AND 2002
Sep 29, 2022P00081$829.0KPROCURE COSAL SPARES FOR CVN78
Sep 19, 2022P00080$11.5MFUNDING FOR LRU AND PSB STORAGE AND INSTALL AS WELL AS INCO SPARES PLUS UP.
Jul 20, 2022P00079$1.1MFUND SLIN 800102 FOR AAG ILSN SPARES AND ADD CLIN 8002 FOR WT MOD-II SPARES
Jul 7, 2022P00078$426.0KCVN80 HARDWARE ACCELERATION DIRECTED CHANGE AND PSB COSTS STEMMING FROM SWO & SWO CANCELLATION
Jun 8, 2022P00077$214.6KTHE PURPOSE OF THIS MODIFICATION IS TO FUND ADDITIONAL ACTUAL COSTS INCURRED DURING PRODUCTION OF THE DEADLOAD AXLES AND HOLDBACK CLEATS.
May 19, 2022P00076$349.4KPROVIDE FUNDING FOR ECP
Apr 25, 2022P00075$4.0MSCHEDULE INCENTIVE PAYMENT AND SOFTWARE UPGRADES.
Apr 13, 2022P00074$3.8MARMATURE TORSION BREAK, HAMPTON STORAGE, AND AAG DAQ WIRING
Mar 7, 2022P00073$189.2KTROUGH COVER TRANSFER AND STORAGE
Feb 1, 2022P00072$0NO-COST ADMINISTRATIVE MODIFICATION.
Dec 6, 2021P00071$6.4MPCD INCREMENTAL FUNDING, LMM & TROUGH CABLES STORAGE, EMALS CERTIFICATION
Oct 27, 2021P00070$33.7MEXERCISE OPTION CLINS 7016 AND 7017 AND FULLY FUND BOTH CLINS. INCREMENTALLY FUND CLIN 7020.
Oct 22, 2021P00069$418.5KPAYBACK CVN79 AND CVN80 FOR MATERIAL USED FOR CVN78
Sep 28, 2021P00068$9.6MTHE PURPOSE OF THIS MODIFICATION IS TO DELIVER A -06 CONFIGURATION OF THE PURCHASE CABLE DRUM (PCD) FOR CVN-80 AND TO UPDATE THE PCD-05 CONFIGURATION FOR CVN-79.
Sep 22, 2021P00067$961.7KIMPLEMENTATION OF INSTALLATION AND CHECKOUT SPARE (INCOS) WIRING HARNESS REPLACEMENT, AND HEALTHMAP (HMAP) DELIVERY IN SUPPORT OF EMALS FOR CVN 79 AND CVN 80
Sep 3, 2021P00066$124.7KACCELERATED PRODUCTION OF PRINTED CIRCUIT BOARD ASSEMBLY (PCBA), PRIME POWER INTERFACE SUBSYSTEM (PPIS) INVERTER CONTROLLER CARDS.
Jul 8, 2021P00065$464.8KTHE PURPOSE OF THIS MODIFICATION IS TO UPDATE NAVAIR AND DFARS CLAUSES FOR CLIN 2001 AND TO UPDATE DATES AND PAGES IN SECTION J. PID N00019-21-RFPREQ-TPM251-0487 PR 1300937038 PID N00019-RFPREQ-TPM251-0304 PR 1300925394 MICHAEL.J.LANG92.CIV@US.NAVY.MIL
Jun 8, 2021P00064$1.3MFY20 SCHEDULE INCENTIVE
May 26, 2021P00063$66.0MINCREMENTALLY FUND CLINS 3007, 3008, 6001, AND 6003.
Apr 30, 2021P00062$36.4MWT MOD II SHIPSET
Apr 27, 2021P00061$1.2MDELIVERY ACCELERATION OF EMALS PCS/PPIS INVERTER INTERNALS FOR CVN 79 PCS RECTIFIER LEAK DETECTOR CHANGE KIT INSTALLATION UNDER FOR CVN 79 AND PRODUCTION CUT-IN OF ECP-I-EMALS-0051 FOR CVN 80.
Mar 29, 2021P00060$149.1KEQUITABLE ADJUSTMENT FOR PROPOSAL PREPARATION
Feb 2, 2021P00059$3.6MESTABLISH CLIN 7013 FOR THE MANUFACTURE AND DELIVERY OF DEADLOAD AXLES, FALSE AXLES, AXLE SLEEVES, AND SPLASH SHIELDS.
Nov 18, 2020P00058$0CLIN 7008 POP EXTENSION
Oct 7, 2020P00057$290.4KADD FUNDING TO CLIN 2001 FOR CVN 79 NOSE GEAR LAUNCH
Sep 21, 2020P00056$713.9KREDESIGN NOSE GEAR LAUNCH
Aug 31, 2020P00055$63.3KPROVIDE AN EQUITABLE ADJUSTMENT FOR THE CVN 80 POSITION SENSOR BLOCK (PSB) STOP WORK ORDER IN ACCORDANCE WITH FEDERAL ACQUISITION REGULATION CLAUSE 52.243-1, CHANGES FIXED PRICE AND NAVAIR LETTERS 19-0201 DATED 23 JULY 2018 AND 19-0253 DATED 11 SEPTEMBER 2019. UPDATE SECTION J.
Aug 5, 2020P00054$846.5KECP 0047 FOR AAG PCD PIN
Jun 23, 2020ARZ998$0CVN 79 EMALS LONG LEAD TIME MATERIAL
Jun 16, 2020P00053$3.0MECR 06685 EMALS POWER CONDITIONING SUBSYSTEM AND PRIME POWER INTERFACE SUBSYSTEM INVERTER ASSEMBLY HIGH FREQUENCY TERMINAL BLOCK
Apr 28, 2020P00052$162.2MTHE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND CLINS 6001 AND 6003 AND UPDATE DFARS CLAUSE 252.232-7007.
Apr 10, 2020P00051$3.0MMOTOR SUPPORT STRUCTURE ECP INCORPORATION 78-REACHBACK INTEGRATED LOGISTICS SUPPORTABILITY OTHER ADMINISTRATIVE UPDATES
Mar 25, 2020P00050$1.8MFY19 INCENTIVE PAYMENT IN ACCORDANCE WITH H-8 SCHEDULE INCENTIVE UNDER CLIN 2003
Mar 5, 2020P00049$3.0MTO PROCURE SIX (6) CVN78 WATER TWISTER MOD-II ROTORS
Feb 19, 2020P00048$10.4MSCL AND SFD HARDWARE UPGRADES.
Feb 18, 2020P00047$0TO CORRECT THE COL# FOR CSA SHEAVE ASSY AS INTENDED IN P00046.
Feb 13, 2020P00046$0SECTION F DELIVERY QTY UPDATE
Dec 30, 2019P00045$10.1MPOST PRODUCTION AND PRODUCTION INCORPORATION OF ECPS FOR CVN 79 AND CVN 80, RESPECTIVELY.
Nov 1, 2019P00044$46.0KDELIVERY DATE FOR EXHIBIT G SPARES MOVED FROM 8/2018 TO 5/2024 RESULTING IN THE NEED OF STORAGE AND PRESERVATION FOR THESE SPARES UNTIL DELIVERY
Aug 13, 2019P00043$7.2MPROVIDE AN EQUITABLE ADJUSTMENT FOR A DIRECTED CHANGE AGAINST THE AAG WT AND CSA.
Jul 22, 2019P00042$0UPDATE EXHIBITS E&N TO THE CORRECT QUANTITY OF THE ECS HOSE ASSEMBLIES, AND PROVIDE ADMIN UPDATES TO EXHIBIT F, G, AND R.
Jul 10, 2019P00041$326.1KCABLE SHOCK ABSORBERS DIRECTED CHANGE.
May 31, 2019P00040$100.0KMOTOR GENERATOR STORAGE DIRECTED CHANGE REA
May 23, 2019P00039$3.4MFY18 SCHEDULE INCETIVES
Apr 17, 2019P00038$0UPDATE CLINS 3005, 3006, 3007, AND 3008.
Apr 16, 2019P00037$0UPDATE TO EXHIBITS AND ATTACHMENTS AND PROVIDE GFI
Feb 26, 2019P00036$3.8MINCREMENTALLY FUND CLIN 2004
Dec 26, 2018P00035$336.6MINCREMENTAL FUNDING FOR CVN80
Oct 30, 2018P00034$-11.4MUPDATE TO ATTACHMENTS AND EXHIBITS UNDER CVN 79/80 EMALS&AAG PRODUCTION CONTRACT
Oct 26, 2018P00033$41.8KWELD POSITIONER GOVERNMENT FURNISHED PROPERTY
Oct 22, 2018P00032$0SCHEDULE ACCELERATION DEFIN
Sep 7, 2018P00031$2.2MPROVIDE THE FY17 SCHEDULE INCENTIVE PAYMENTS FOR EMALS DELIVERIES AND AAG DELIVERIES UNDER CLIN 2003, CHANGE CLIN 6002 FROM CVN 80 EMALS SHIPSET W/O AAG TO RESERVED, CHANGE SECTION F, DELIVERIES OR PERFORMANCE, GFE WAREHOUSE POINT OF CONTACT, UPDATE EXHIBIT E, CVN 79 EMALS DELIVERY DATES AND EXHIBIT F, CVN 79 AAG DELIVERY DATES, AND UPDATE EXHIBIT H, AAG INCO DELIVERY DATES.
Aug 7, 2018A00004$0CVN 79 EMALS LONG LEAD TIME MATERIAL
Jul 18, 2018P00030$250.0KINCREMENTAL FUNDING OF NRE CLIN 3007 AND SOW/CDRL UPDATES
Jun 19, 2018P00029$0NO COST MODIFICATION TO CHANGE THE DELIVERY DATE AND RECEIVE CONSIDERATION, DEOBLIGATE FUNDS FROM CLIN 3001 AND 3003, CHANGE DELIVERY LOCATIONS, AND UPDATE EXHIBIT P AND ATTACHMENT 5 WITH ADMINISTRATIVE UPDATES.
May 2, 2018P00028$42.8MINCREMENTAL FUNDING OF CVN 80 CLINS. NO COST CHANGES INCLUDE APPROVAL OF RFVS AND ECNS, DELIVERY DATE CHANGE FOR PPIS-PCS WATER COOLING CONTROL PANEL AND AS CONSIDERATION GA WILL STORE UNTIL DELIVERY, UPDATE TO TECHNICAL DATA REQUIREMENTS, AND A CONTRACT ERROR CHANGE TO SECTION E.
Mar 29, 2018P00027$55.0KEQUITABLE ADJUSTMENT IN BOTH DELIVERY SCHEDULE AND CONTRACT PRICE FOR A STOP WORK CANCELLATION OF THE HEALTHMAP AND PC/104 COMPUTER.
Feb 14, 2018P00025$0UNPRICED DIRECTED CHANGE FOR THE INCORPORATION OF THE WT MOD-I UPGRADE
Feb 14, 2018P00026$35.3MCONTRACT LINE ITEMS (CLIN) 6001, CVN 80 EMALS AND 6003, CVN 80 AAG ARE INCREMENTALLY FUNDED FOR THE ITEM SUM OF $35,300,000
Feb 6, 2018P00024$48.1KEQUITABLE ADJUSTMENT FOR A WATER TWISTER STOP WORK ORDER.
Jan 3, 2018P00023$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE ATTACHMENT 19. THERE WILL BE NO CHANGE TO CONTRACT PRICE.
Dec 28, 2017P00022$198.6MINCREMENTAL FUNDING FOR CONTINUED CONTRACTING PERFORMANCE.
Dec 27, 2017P00021$82.9KEXERCISE CSA CHARGING PANEL OPTION
Dec 9, 2017P00020$61.4MINCREMENTAL FUNDING FOR CONTINUED CONTRACTING PERFORMANCE.
Dec 2, 2017P00019$9.1MPROVIDE INCREMENTAL FUNDING FOR CVN 80.
Nov 2, 2017P00018$7.3MTHIS PURPOSE OF THIS MODIFICATION IS TO PROCURE AAG RALS HARDWARE COMPONENTS TO REPLACE THE CVN 79 HARDWARE CURRENTLY INSTALLED AT THE RUNWAY ASSISTED LANDING SITE (RALS).
Aug 18, 2017P00017$0MODIFICATION TO EFFECT THE CONSIDERATION OWED FOR CVN 80 AAG OPTION EXERCISE EXTENSION.
Aug 17, 2017A00003$0CVN 79 EMALS LONG LEAD TIME MATERIAL
Jun 29, 2017A00002$0CVN 79 EMALS LONG LEAD TIME MATERIAL
Jun 20, 2017P00016$0UNPRICED CHANGE ORDER AS A RESULT OF STOP WORK ORDERS
Jun 15, 2017P00015$443.2KFIRST INSTALLMENT OF THE SCHEDULE INCENTIVE FOR EMALS AND AAG DELIVERIES
May 18, 2017P00014$4.0MEXERCISE OPTION FOR CVN 80 ADVANCED ARRESTING GEAR.
May 15, 2017P00013$0ADMINISTRATIVE MODIFICATION TO EXTEND THE CVN 80 AAG OPTION (CLIN 6003) OPTION EXERCISE DATE.
Apr 14, 2017A00001$0CVN 79 EMALS LONG LEAD TIME MATERIAL
Feb 23, 2017P00012$164.7MFUNDING ONLY MODIFICATION
Jan 27, 2017P00011$11.0MEXERCISE CVN 80 EMALS OPTION
Jan 12, 2017P00010$0FUNDING DE-OB RE-OB ONLY MODIFICATION.
Dec 22, 2016P00009$0DEFINITIZATION OF CVN 79 PRODUCTION CONTRACT
Sep 15, 2016P00008$0UPDATE OF EXISTING SECTION J EXHIBITS, ATTACHMENTS, AND OTHER DOCUMENTS. DELIVERY ADDRESS CHANGE FOR EMALS HARDWARE SHIPSET.
Jun 1, 2016P00007$0PERIOD OF PERFORMANCE EXTENSION ON CLINS 3001 AND 3003.
May 9, 2016P00006$100.0MCVN 79 INCREMENTAL FUNDING MODIFICATION
Mar 8, 2016P00005$0MODIFICATION TO UPDATE THE GA MAKE/BUY APPROACH FOR MOTOR GENERATORS.
Dec 2, 2015P00004$64.3MCVN 79 INCREMENTAL FUNDING MODIFICATION.
Nov 11, 2015ARZ999$0CVN 79 EMALS LONG LEAD TIME MATERIAL
Jun 12, 2015P00003$164.8MCVN 79 LLTM DEFINITIZATION&CVN 79 UCA EXECUTION.
Sep 9, 2014P00002$0ADMIN MOD TO DELETE TWO FAR CLAUSES AND REPLACE SUPPLEMENT 2 TO EXHIBITS A&B.
Aug 6, 2014P00001$0THE PURPOSE OF THIS MODIFICATION IS TO REVISE AND REPLACE EXHIBIT A CDRL A00G, AND ATTACHMENT 3 STATEMENT OF WORK. ADDITIONALLY FUNDS ARE DEOBLIGATED FROM ACRN AB AND OBLIGATED ON ACRN AA WITH NO OVERALL CHANGE IN CONTRACT PRICE.
May 8, 20140$15.4MCVN 79 EMALS LONG LEAD TIME MATERIAL

Estimated positioning window

Jan 30, 2029 – Jul 30, 2029

Recompete signal:
50/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 50/100. Available recorded signals: 45 points.

Contract end 2030-01-30 (1193 days from calculation)
+5 points
14 historical awards in this buyer and category group
+15 points
123 recorded award transactions
+10 points
Latest award action: 2026-05-21
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.