Federal contract award

N0001923F0287

SEALING FTSU CENTER TANK

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeNAVAL AIR SYSTEMS COMMAND
NAICS336413 — Other Aircraft Parts and Auxiliary Equipment Manufacturing
PSC1560 — Airframe Structural Components
Parent award / vehicleN0001918D0118
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$7.9M
Current contract value$7.9M
Potential contract value / ceiling$7.9M
Start dateApr 18, 2023
Current end dateJan 14, 2026
Potential end dateJan 14, 2026
Latest award activityMar 11, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 11, 2026P00015$55.3KTHE PURPOSE OF THIS MODIFICATION IS TO FUND ECAS ON SLINS 0006AS AND 0006AT AND RECTIFY A LINE OF ACCOUNTING ISSUE ON SLIN 0007AD.
Dec 4, 2025P00014$569.1KTO ADD SUBCONTRACT LINE ITEM NUMBER (SLIN) 0006AR IN THE AMOUNT OF $569,122 TO INCORPORATE THE EQUITABLE COST ADJUSTMENT PROPOSAL 2025.0821 REV 1 FOR THE LABOR STANDBY COST INCURRED DURING THE COMPLETION OF TASKING UNDER SLIN 0006AB-0006AE.
Sep 30, 2025P00013$42.4KTHE PURPOSE OF THIS MODIFICATION IS TO: INCREASE THE CEILING UNDER CONTRACT LINE ITEM NUMBER (CLIN) 0007 OVER & ABOVE FOR RESEAL OF MAIN TANK #2 VIA SUB CONTRACT LINE ITEM NUMBER (SLIN) 0007 AD IN THE TOTAL AMOUNT OF $42,436.00.
Aug 28, 2025P00012$90.4KTHE PURPOSE OF THIS MODIFICATION IS TO APPLY EQUITABLE COST ADJUSTMENT (ECA) FOR STANDBY ACCRUED IN MARCH AND APRIL 2025.
Aug 4, 2025P00011$796.6KTHE PURPOSE OF THIS MODIFICATION IS TO APPLY EQUITABLE COST ADJUSTMENT (ECA) FOR STANDBY ACCRUED IN MARCH AND APRIL 2025.
Jul 28, 2025P00010$1.1MTHE PURPOSE OF THIS MODIFICATION IS TO FUND ECAS FOR STANDBY AND FOR MATERIAL LOSS.
Apr 28, 2025P00009$1.1MTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE PRICE ADJUSTMENT FOR THE RESEAL OF MAIN TANKS #1-#4.
Mar 20, 2025P00008$19.4KTHE PURPOSE OF THIS MOD IS TO RECTIFY AN ECA FOR STANDBY FOR HOLIDAY CLOSURES.
Feb 24, 2025P00007$153.6KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE A PRICE ADJUSTMENT ON CLIN 0006AA/.
Jan 22, 2025P00006$2.8KTHE PURPOSE OF THIS MOD IS TO ADD FUNDING TO CLIN 0005 FOR VETERANS DAY HOLIDAY.
Dec 30, 2024P00005$94.6KINCORPORATE PRICE IMPACT ON FUEL SYSTEM MAINTENANCE ON E-6B MERCURY AIRCRAFT FOR REPLACEMENT OF SEALANT FOR RESERVE TANKS #1 AND #4.
Dec 16, 2024P00004$15.6KA/C 164407 COLUMBUS DAY SITE CLOSURE
Nov 13, 2024P00003$317.5KUPDATE DODAAC AND FUND OFF-SITE STANDBY COSTS FOR 7/31/2024 TO 8/22/2024, WORK STOPPAGE ON-SITE COSTS FOR 8/27/2024 AND OFF-SITE STANDBY COSTS FOR LABOR DAY.

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.