Federal contract award
N0016725F1100
THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION REQUIRED TO REBUILD ONE (1) COUPLED VERTICAL TURBINE PUMP, AND (2) 10 INCH WEIGHT AND LEVER CHECK VALVES LOCATED IN BUILDING 4, J-BASIN
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NSWC CARDEROCK |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1HB — CONSTRUCTION OF GOVERNMENT-OWNED GOVERNMENT-OPERATED (GOGO) R&D FACILITIES |
| Parent award / vehicle | N0016724D0013 |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $209.0K |
| Current contract value | $209.0K |
| Potential contract value / ceiling | $209.0K |
| Start date | Jul 16, 2025 |
| Current end date | Apr 17, 2026 |
| Potential end date | Apr 17, 2026 |
| Latest award activity | Apr 1, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 5 of 5 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 1, 2026 | P00004 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM NOVEMBER 21, 2025, TO DECEMBER 12, 2025, DUE TO THE SUBCONTRACTOR REPORTED LEAD TIME OF 10 WEEKS FOR PUMP MATERIAL PARTS. |
| Jan 7, 2026 | P00003 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM NOVEMBER 21, 2025, TO DECEMBER 12, 2025, DUE TO THE SUBCONTRACTOR REPORTED LEAD TIME OF 10 WEEKS FOR PUMP MATERIAL PARTS. |
| Oct 24, 2025 | P00002 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM NOVEMBER 21, 2025, TO DECEMBER 12, 2025, DUE TO THE SUBCONTRACTOR REPORTED LEAD TIME OF 10 WEEKS FOR PUMP MATERIAL PARTS. |
| Aug 21, 2025 | P00001 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE COMPLETION DATE FROM NOVEMBER 21, 2025, TO DECEMBER 12, 2025, DUE TO THE SUBCONTRACTOR REPORTED LEAD TIME OF 10 WEEKS FOR PUMP MATERIAL PARTS. |
| Jul 16, 2025 | 0 | $209.0K | THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION REQUIRED TO REBUILD ONE (1) COUPLED VERTICAL TURBINE PUMP, AND (2) 10 INCH WEIGHT AND LEVER CHECK VALVES LOCATED IN BUILDING 4, J-BASIN |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.