N3220526P5007

TWENTY-THREE (23) HOTEL ROOMS FROM 1 NOV 2025-10 MAR 2026, WITH CHECKOUT 11 MAR 2026 (130 NIGHTS/2,990 ROOM-NIGHTS) THREE (3) HOTEL ROOMS, 1 NOV 2025 -6 NOV 2025, WITH CHECKOUT 7 NOV 2025 (6 NIGHTS/18 ROOM-NIGHTS)TOTAL NUMBER OF ROOM-NIGHTS 3,008

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeMSCHQ NORFOLK
NAICS721110 — Hotels (except Casino Hotels) and Motels
PSCV231 — Lodging - Hotel/Motel
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$339.8K
Current contract value$339.8K
Potential contract value / ceiling$508.8K
Start dateOct 31, 2025
Current end dateMar 20, 2026
Potential end dateMay 29, 2026
Latest award activityMar 18, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 18, 2026P00002$24.1K1.) THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION ONE ON TASK ORDER N3220526P5007. 2.) USNS FRANK CABLE CIVMAR LODGING IN GUAM. OPTION 1: 11 MARCH 2026 - 20 MARCH 2026, WITH CHECKOUT 21 MARCH 2026.
Dec 18, 2025P00001$315.7KTHE PURPOSE OF THIS MODIFICATION IS TO AMEND THE PERIOD OF PERFORMANCE AND REVISE THE PERFORMANCE WORK STATEMENT (PWS) AND ADD FUNDING TO BASE CLIN 0001 - FY26 FUNDING
Nov 4, 20250$0TWENTY-THREE (23) HOTEL ROOMS FROM 1 NOV 2025-10 MAR 2026, WITH CHECKOUT 11 MAR 2026 (130 NIGHTS/2,990 ROOM-NIGHTS) THREE (3) HOTEL ROOMS, 1 NOV 2025 -6 NOV 2025, WITH CHECKOUT 7 NOV 2025 (6 NIGHTS/18 ROOM-NIGHTS)TOTAL NUMBER OF ROOM-NIGHTS 3,008

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.