Federal contract award
N3319123F4001
X004 1603800 -- ERCIP UPGRADE DEL DIN CENTRAL ENERGY PLANT W/ BAT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVFACSYSCOM EUROPE AFRICA CENTRAL |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AZ — REPAIR OR ALTERATION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | N3319118D0624 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $14.9M |
| Current contract value | $14.9M |
| Potential contract value / ceiling | $14.9M |
| Start date | Dec 6, 2022 |
| Current end date | Jun 30, 2026 |
| Potential end date | Jun 30, 2026 |
| Latest award activity | Apr 13, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 13, 2026 | P00008 | $251.9K | DEL DIN ERCIP - P00008, PC05, 06, 07 AND 08 |
| Jul 30, 2024 | P00007 | $16.2K | ERCIP UPGRADE DEL DIN CENTRAL ENERGY PLANT W/ BAT-MODIFICATION FOR SWITCHGEAR SUPPORT AND ADJUST GREEN PIPING & CAMERA HEIGHTS. |
| May 3, 2024 | P00006 | $18.1K | ERCIP UPGRADE DEL DIN CENTRAL ENERGY PLANT W/ BAT - MODIFICATION TO INCREASE BESS PAD SIZE |
| Mar 15, 2024 | P00005 | $11.3K | ERCIP UPGRADE DEL DIN CENTRAL ENERGY PLANT W/ BAT - MODIFICATION TO RELOCATE STORM DRAIN THAT INTERFERES WITH FOUNDATION |
| Jan 18, 2024 | P00004 | $501.5K | ERCIP UPGRADE DEL DIN CENTRAL ENERGY PLANT W/ BAT - MODIFICATION TO FOUNDATION TO COMPLY WITH PERMIT AND UPDATE TO BESS BREAKER LOCATION |
| Mar 1, 2023 | P00003 | $0 | ADMIN UPDATE TO REMOVE REFERENCES TO BASIS OF DESIGN AND CALCULATIONS |
| Feb 21, 2023 | P00002 | $0 | ADMINISTRATIVE UPDATES (ADMIN BY, WAWF) |
| Dec 8, 2022 | P00001 | $2.1M | WON 1603800 ERCIP UPGRADE DEL DIN, MODIFICATION TO EXERCISE OPTION ITEM NO. 1, CONSTRUCTION OF THERMAL STORAGE SYSTEMS AT CASSERMA DEL DIN. |
| Dec 6, 2022 | 0 | $12.1M | X004 1603800 -- ERCIP UPGRADE DEL DIN CENTRAL ENERGY PLANT W/ BAT |