N4008023F4969
X001 P-3002 RELOCATE HAZARDOUS CARGO PAD AND EOD PROFICIENCY RANG
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVFACSYSCOM WASHINGTON |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | N4008023D0030 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $50.8M |
| Current contract value | $50.8M |
| Potential contract value / ceiling | $50.8M |
| Start date | Sep 19, 2023 |
| Current end date | Dec 18, 2025 |
| Potential end date | Dec 18, 2025 |
| Latest award activity | May 5, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 5, 2026 | P00007 | $384.0K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PC 13, PC 14, AND PC 24 INTO THE CONTRACT. |
| Feb 26, 2026 | P00006 | $4.9M | PC11 FOR THE ADDITIONAL WORK INCURRED FOR THE SURCHARGE PAD REMEDIATION (PADS 1, 2, AND 3) AND PC15 FOR THE TIME EXTENSION AND COSTS ASSOCIATED WITH DELAYS AS PROPOSED IN TIME IMPACT ANALYSIS 01. |
| Sep 23, 2025 | P00005 | $422.0K | PC 10, 16, AND 21 |
| Aug 4, 2025 | P00004 | $458.2K | P00004 |
| Jun 13, 2025 | P00003 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE MDE PERMIT. |
| Mar 20, 2025 | P00002 | $843.6K | X001 P-3002 RELOCATE HAZARDOUS CARGO PAD AND EOD PROFICIENCY RANG |
| May 16, 2024 | P00001 | $0 | X001 P-3002 RELOCATE HAZARDOUS CARGO PAD AND EOD PROFICIENCY RANG |
| Sep 19, 2023 | 0 | $43.8M | X001 P-3002 RELOCATE HAZARDOUS CARGO PAD AND EOD PROFICIENCY RANG |