Federal contract award
N4008518F7202
IGF::OT::IGF X041 REPLACE CHILLERS NH100 NAVAL HOSPITAL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVFACSYSCOM MID-ATLANTIC |
| NAICS | 238220 — Plumbing, Heating, and Air-Conditioning Contractors |
| PSC | Z2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | N4008514D7744 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $5.6M |
| Current contract value | $5.6M |
| Potential contract value / ceiling | $5.6M |
| Start date | Sep 28, 2018 |
| Current end date | Apr 8, 2021 |
| Potential end date | Apr 8, 2021 |
| Latest award activity | Jul 28, 2021 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jul 28, 2021 | P00007 | $0 | TIME EXTENSION DUE TO ITEM DELAYS - REPLACE CHILLERS NH100 NAVAL HOSPITAL |
| Jan 25, 2021 | P00006 | $38.1K | REPLACE CHILLERS NH100 NAVAL HOSPITAL |
| Jun 8, 2020 | P00005 | $334.3K | MODIFICATION TO X041 REPLACE CHILLERS NH100 NAVAL HOSPITAL |
| Dec 3, 2019 | P00004 | $16.9K | PROVIDE ADDITIONAL PIPE SUPPORTS. |
| Oct 17, 2019 | P00003 | $8.1K | REDIRECT CONDENSATE LINE. |
| Sep 18, 2019 | P00002 | $19.0K | 1. REMOVE ASPHALT AS NEEDED TO EXPOSE ALL LOOSE AREAS OF SUBGRADE ESTIMATED 1100 SF. 2. EXCAVATE ALL LOOSE SUBGRADE MATERIAL FROM THE SITE ESTIMATED 1100 SF 8' DEEP. 3. VERIFY NO EXISTING DAMAGE TO THE STORMWATER PIPING, MANHOLE (MANHOLE HAS 5 PIPE PENETRATIONS) AND 8" WATER LINES. IF DAMAGES NOTED INFORM NMCCL ENGINEERING STAFF OF THE DAMAGES AND HOW TO PROCEED. 4. BACKFILL AREA AND REPAIR THE ASPHALT AS CALLED FOR IN THE DRAWINGS/SPECIFICATIONS FROM THIS CONTRACT. |
| Sep 11, 2019 | P00001 | $104.9K | PC 02 - AT LOCATION SPECIFIED ON ATTACHED DRAWING, INSTALL 1200 AMP MANUAL TRANSFER SWITCH TO POWER THE TEMPORARY CHILLER WITH SHORE POWER OR POWER FROM THE TEMPORARY GENERATOR. - 1200 AMP MANUAL TRANSFER SWITCH WILL INCLUDE CAMLOK CONNECTIONS -CAMLOK FITTINGS TO BE FILLED WITH STRAIN RELIEF OR MOUNTED INTO THE PANEL. $99,257.00 AND 21 DAYS PC 03 1. CORRECT THE OFFSET/DEFLECTION OF THE SPRINKLER PIPING IN HALLWAY E163A. 2. MOVE CONDUIT AS REQUIRED TO STRAIGHTEN SPRINKLER PIPING. $3,808.00 AND 0 DAYS PC 04 1. EXTEND EXISTING 1" REFRIGERATION CONDENSER DISCHARGE WATER UPSTREAM OF EXISTING SHUTOFF VALVE TO TIE-IN TO NEW CONDENSER WATER RETURN. SEE ATTACHED DRAWING. $1,855.00 AND 1 DAY PC 06 TIME EXTENSION FOR EXCUSABLE DELAY. 129 DAYS |
| Sep 28, 2018 | 0 | $5.1M | IGF::OT::IGF X041 REPLACE CHILLERS NH100 NAVAL HOSPITAL |