N62742-22-C-1329, FY18 MCON P-661 NAVY-COMMERCIAL TIE-IN HARDENING JOINT REGION MARIANAS, GUAM

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeNAVFACSYSCOM MARIANAS
NAICS237120 — Oil and Gas Pipeline and Related Structures Construction
PSCY1GC — CONSTRUCTION OF FUEL STORAGE BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$39.2M
Current contract value$39.2M
Potential contract value / ceiling$39.2M
Start dateMay 12, 2022
Current end dateFeb 21, 2025
Potential end dateFeb 21, 2025
Latest award activityApr 1, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 13 of 13 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 1, 2026P00011$143.5KTO INCORPORATE REA#5 FOR MEC RELATED WORK ON UNDERGROUND UTILITIES NOT INCLUDED IN THE CONTRACT SPECIFICATIONS, WITH NO ADDITIONAL TIME TO CONTRACT COMPLETION DATE.
Nov 17, 2025P00010$100.5KTO INCORPORATE CONTRACT ADJUSTMENT FOR UNIT PRICED ITEMS FOR FURNISHING 426 LF OF ADDITIONAL PILE LENGTH AND PILE DRIVING 10.9 LF PAST TIP ELEVATION FOR PROJECT TEST PILE PROGRAM, WITH NO ADDITIONAL TIME TO CONTRACT COMPLETION DATE.
Mar 24, 2025P00009$597.2KMODIFICATION TO INCORPORATE PC14, PC15, PC16, PC17, PC18, AND 75 CALENDAR DAYS.
Dec 19, 2024P00008$0BASE ITEM
Sep 23, 2024P00007$470.6KINCORPORATE REA #3 AND FOOH COSTS FOR PC06 AND TO ADD 36 CALENDAR DAYS TO CONTRACT.
Jun 20, 2024P00006$67.3KPC11: ADDITIVE WORK RELATIVE TO 12" ACP AND 12" CS BALLAST LINE PENETRATING SEISMIC VAULT PC12: ADDITIVE WORK TO PROVIDE CONCRETE ENCASEMENT AROUND WATERLINE IN CONFLICT WITH CHT LINE AT STA. 1+39.29
Apr 12, 2024P00005$127.6KPC10: REVISED LIGHT POLE AND FOUNDATION
Mar 19, 2024P00004$400.5KPC06 CONCRETE ENCASEMENT OF ACP & THRUST BLOCK REMOVAL PC07 REMOVE UPPER W14X193 GIRDER FROM EAST & WEST WALLS ADDITIONAL 23 CALENDAR DAYS
Mar 6, 2024P00003$94.1KPC09: PROVIDE ADDITIVE INJECTOR SYSTEM WITH TWO 1L PUMPS REFLECTING THE CORRECT PUMP ADDITIVE INJECTOR CONFIGURATION.
Nov 24, 2023P00002$702.9KPC03 ADD 12-INCH ACP & REMOVE REQUIREMENT TO INSTALL OPERATIONAL BYPASS LINES FOR 12" STEEL BALLAST WATERLINE AS WELL AS 16" & 24" CS BYPASS LINE. PC08 (REA) DUE TO DIFFERING SITE CONDITIONS FROM EXISTING PIPE ELEVATIONS.
Oct 27, 2023P00001$-187.9KPC04 DE-SCOPE ACTUATED DBB FOR 24' AND 16' VALVES
Nov 25, 2022A00001$700.0KADMINISTRATIVE MODIFICATION TO INCORPORATE UPDATES TO SPEC SECTION SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS AND SPEC SECTION BLAST RESISTANT DOORS GRANITES NO COST RESPONSE DATED 19 AUGUST 2022 PC02 MEC OPTION PER SF1442 DATED 21 APRIL 2022
Apr 21, 20220$36.0MN62742-22-C-1329, FY18 MCON P-661 NAVY-COMMERCIAL TIE-IN HARDENING JOINT REGION MARIANAS, GUAM