Federal contract award

N6274223F4034

RHS PHASE 2 CONNECTION

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeNAVFACSYSCOM PACIFIC
NAICS561210 — Facilities Support Services
PSCW046 — Lease or Rental of Equipment: Water Purification and Sewage Treatment Equipment
Parent award / vehicleN6274216D3552
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$76.3M
Current contract value$76.3M
Potential contract value / ceiling$93.6M
Start dateSep 29, 2023
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activityFeb 27, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 27, 2026P00007$6.3MN62742-16-D-3552 GCSMAC II FOR NAVAL FACILITIES ENGINEERING COMMAND PACIFIC, JOINT BASE PEARL HARBOR HICKAM, TO N6274223F4034 RED HILL SHAFT CONNECTION - PHASE 2, MODIFICATION P00007 - GAC TANK LEASE EXTENSION
Dec 9, 2025P00006$0N62742-16-D-3552 GCSMAC II FOR NAVAL FACILITIES ENGINEERING COMMAND PACIFIC, JOINT BASE PEARL HARBOR HICKAM, TO N6274223F4034 RED HILL SHAFT CONNECTION - PHASE 2, MODIFICATION P00006 - ADMINISTRATIVE MODIFICATION
Nov 18, 2025P00005$0N62742-16-D-3552 GCSMAC II FOR NAVAL FACILITIES ENGINEERING COMMAND PACIFIC, JOINT BASE PEARL HARBOR HICKAM, TO N6274223F4034 RED HILL SHAFT CONNECTION - PHASE 2, MODIFICATION P00005 - PERIOD OF PERFORMANCE (POP) EXTENSION
Sep 19, 2025P00004$306.3KN62742-16-D-3552 GCSMAC II FOR NAVAL FACILITIES ENGINEERING COMMAND PACIFIC, JOINT BASE PEARL HARBOR HICKAM, TO N6274223F4034 RED HILL SHAFT CONNECTION - PHASE 2, MODIFICATION P00004 - CONCRETE SLAB DISPOSAL
Jul 10, 2025P00003$3.2MRED HILL SHAFT PHASE 2 CONNECTION
Mar 12, 2025P00002$0N62742-16-D-3552, N6274223F4034: PHASE 2 - TEMPORARY WATER TREATMENT FACILITY AT RED HILL