Federal contract award
N6339420C0008
VLS PROGRAMMABLE POWER SUPPLY (PPS)
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | COMMANDING OFFICER |
| NAICS | 334519 — Other Measuring and Controlling Device Manufacturing |
| PSC | 5999 — Miscellaneous Electrical and Electronic Components |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $70.3M |
| Current contract value | $70.3M |
| Potential contract value / ceiling | $75.4M |
| Start date | Aug 26, 2020 |
| Current end date | Dec 3, 2025 |
| Potential end date | Dec 3, 2025 |
| Latest award activity | Jun 11, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 24 of 24 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 11, 2026 | P00023 | $0 | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VLS PROGRAMMABLE POWER SUPPLY, MAINTENANCE ASSISTANCE MODULE KIT, ONBOARD REPAIR PART KIT, INSTALLATION AND CHECKOUT SPARES KIT DEPOT SPARES KIT & LOWEST REPLACEABLE UNIT KIT EQUITABLE |
| Jun 9, 2025 | P00022 | $0 | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VLS PROGRAMMABLE POWER SUPPLY, MAINTENANCE ASSISTANCE MODULE KIT, ONBOARD REPAIR PART KIT, INSTALLATION AND CHECKOUT SPARES KIT DEPOT SPARES KIT & LOWEST REPLACEABLE UNIT KIT-EQUITABLE |
| Nov 18, 2024 | P00021 | $760.3K | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VLS PROGRAMMABLE POWER SUPPLY, MAINTENANCE ASSISTANCE MODULE KIT, ONBOARD REPAIR PART KIT, INSTALLATION AND CHECKOUT SPARES KIT DEPOT SPARES KIT & LOWEST REPLACEABLE UNIT KIT-EQUITABLE. |
| Oct 28, 2024 | P00020 | $0 | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VLS PROGRAMMABLE POWER SUPPLY, MAINTENANCE ASSISTANCE MODULE KIT, ONBOARD REPAIR PART KIT, INSTALLATION AND CHECKOUT SPARES KIT DEPOT SPARES KIT & LOWEST REPLACEABLE UNIT KIT-EQUITABLE. CHANGE IN SCHEDULE. |
| Sep 30, 2024 | P00019 | $1.2M | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VLS PROGRAMMABLE POWER SUPPLY,MAINTENANCE ASSISTANCE MODULE KIT,ONBOARD REPAIR PART KIT,INSTALLATION AND CHECKOUT SPARES KIT DEPOT SPARES KIT & LOWEST REPLACEABLE UNIT KIT-EQUITABLE. SETTLE REA IMS 17058. |
| Aug 5, 2024 | P00018 | $304.9K | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VLS PROGRAMMABLE POWER SUPPLY,MAINTENANCE ASSISTANCE MODULE KIT,ONBOARD REPAIR PART KIT,INSTALLATION AND CHECKOUT SPARES KIT, DEPOT SPARES KIT & LOWEST REPLACEABLE UNIT KIT-EQUITABLE ADJUSTMENT. |
| Jun 5, 2024 | P00017 | $0 | PPS PRODUCTION OY1,CHANGE DELIVERY SCHEDULE FOR CLINS/SLINS 0015 AND 0021AA, UPDATE CLAUSE 252.232-7006. |
| Mar 19, 2024 | P00016 | $5.1M | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VERTICAL LAUNCHING SYSTEM (VLS) PROGRAMMABLE POWER SUPPLY (PPS)AND ASSOCIATED KITTED MATERIAL. |
| Feb 7, 2024 | P00015 | $0 | MANUFACTURE, ASSEMBLY, TEST AND DELIVERY OF VERTICAL LAUNCHING SYSTEM (VLS) PROGRAMMABLE POWER SUPPLY (PPS)AND ASSOCIATED KITTED MATERIAL. |
| Nov 6, 2023 | P00014 | $0 | PPS PRODUCTION OY1 |
| Sep 18, 2023 | P00013 | $0 | PPS PRODUCTION OY1 |
| Jun 26, 2023 | P00012 | $10.4M | VLS PROGRAMMABLE POWER SUPPLY (PPS) AND COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, AND DEPOT SPARES KIT |
| Apr 6, 2023 | P00011 | $0 | PPS PRODUCTION OY1 |
| Feb 7, 2023 | P00010 | $1.1M | VLS PROGRAMMABLE POWER SUPPLY (PPS) AND COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, AND DEPOT SPARES KIT |
| Nov 2, 2022 | P00009 | $0 | VLS PROGRAMMABLE POWER SUPPLY (PPS) AND COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, AND DEPOT SPARES KIT. |
| Jun 30, 2022 | P00008 | $15.4M | VLS PROGRAMMABLE POWER SUPPLY (PPS) AND COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, AND DEPOT SPARES KIT. |
| May 2, 2022 | P00007 | $0 | VLS PROGRAMMABLE POWER SUPPLY (PPS) AND COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, AND DEPOT SPARES KIT. |
| Dec 15, 2021 | P00006 | $0 | VLS PROGRAMMABLE POWER SUPPLY (PPS) AND COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, DEPOT SPARES KIT. |
| Sep 10, 2021 | P00005 | $960.8K | VLS PROGRAMMABLE POWER SUPPLY (PPS) OY1 COMPONENTS: MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, DEPOT SPARES KIT. |
| Aug 18, 2021 | P00004 | $0 | VLS PROGRAMMABLE POWER SUPPLY (PPS) MK 179 MOD 0, MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, DEPOT SPARES KIT, AND LOWEST REPLACEABLE UNIT (LRU) KIT. |
| Jul 16, 2021 | P00003 | $0 | VLS PROGRAMMABLE POWER SUPPLY (PPS) MK 179 MOD 179 MOD 0, MAINTENANCE ASSISTANCE MODULE (MAM) KIT, ONBOARD REPAIR PART (OBRP) KIT, INSTALLATION AND CHECKOUT (INCO) SPARES KIT, DEPOT SPARES KIT, AND LOWEST REPLACEABLE UNIT (LRU) KIT. |
| Jan 26, 2021 | P00002 | $11.0M | PPS PRODUCTION OY1 |
| Oct 22, 2020 | P00001 | $0 | PPS (NON-FMS) |
| Aug 26, 2020 | 0 | $24.0M | VLS PROGRAMMABLE POWER SUPPLY (PPS) |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.