Federal contract award
NAMA17F0004
NEW ELECTRICITY TASK ORDER AT LENEXA. IGF::OT::IGF FOR OTHER FUNCTIONS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | National Archives and Records Administration |
| Office | NARA CONTRACTING OFFICE |
| NAICS | 221112 — Fossil Fuel Electric Power Generation |
| PSC | S112 — Electric Services |
| Parent award / vehicle | GS00P07BSD0526 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $6.2M |
| Current contract value | $6.2M |
| Potential contract value / ceiling | $6.2M |
| Start date | Sep 22, 2016 |
| Current end date | Sep 30, 2026 |
| Potential end date | Sep 30, 2026 |
| Latest award activity | Aug 19, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 49 of 49 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 19, 2026 | P00006 | $127.0K | ADD FUNDS FOR FY26 FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jun 4, 2026 | P00005 | $0 | CORRECT THE ORG CODE TO NAR6524320000 ON LINE 10, SHIPMENT 100006, DISTRIBUTION 601 FOR ELECTRICITY AT THE LENEXA FACILITY. |
| May 7, 2026 | P00004 | $246.0K | ADD FY26 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Mar 23, 2026 | P00003 | $44.0K | ADD FY26 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY FOR 3/1/2026 TO 3/31/2026. |
| Feb 18, 2026 | P00002 | $44.0K | ADD FY26 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY FOR 2/1/2026 TO 2/28/2026. |
| Jan 8, 2026 | P00001 | $70.0K | ADD FY26 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY FOR 10/01/2025 TO 1/31/2026. |
| Dec 30, 2025 | 42 | $0 | CHANGE THE PREVIOUS MOD FOR FY26 FUNDING FOR IPP MANDATE FROM "Y" TO "N" |
| Dec 9, 2025 | 41 | $100.0K | ADD FY26 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jul 24, 2025 | 40 | $148.0K | ADD FY25 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jun 26, 2025 | 39 | $0 | CHANGE INVOICE APPROVER FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jun 6, 2025 | 37 | $2.1K | ADD FY24 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jun 6, 2025 | 38 | $10.9K | ADD FY23 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jan 15, 2025 | 36 | $375.0K | ADD FY25 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Oct 28, 2024 | 35 | $125.0K | ADD FY25 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Sep 12, 2024 | 34 | $61.0K | ADD FY24 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Apr 9, 2024 | 33 | $250.0K | ADD FY24 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Nov 30, 2023 | 32 | $100.0K | ADD FY24 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Oct 23, 2023 | 31 | $160.5K | ADD FY23 AND FY24 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Aug 9, 2023 | 30 | $0 | CHANGE INVOICE APPROVER AND BACKUP FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Feb 7, 2023 | 29 | $350.0K | OBLIGATE FULLY FY23 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Feb 2, 2023 | 28 | $-9.1K | DE-OBLIGATE FY22 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Nov 7, 2022 | 27 | $150.0K | OBLIGATE FY23 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jun 27, 2022 | 26 | $175.0K | OBLIGATE FY22 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jan 26, 2022 | 25 | $128.3K | DE-OBLIGATE FY21 FUNDS AND OBLIGATE FY22 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Nov 4, 2021 | 24 | $175.0K | OBLIGATE FY22 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Aug 18, 2021 | 23 | $142.0K | OBLIGATE FY21 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| May 17, 2021 | 22 | $200.0K | OBLIGATE FY21 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Mar 22, 2021 | 21 | $100.0K | OBLIGATE FY21 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Jan 14, 2021 | 20 | $56.0K | OBLIGATE FY21 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Dec 16, 2020 | 19 | $90.0K | OBLIGATE FY21 FUNDS FOR ELECTRICITY AT THE LENEXA FACILITY. |
| Nov 24, 2020 | 18 | $3.6K | INCREASE FY20 FUNDS ON CLIN 0004, PERIOD 4. |
| Nov 18, 2020 | 17 | $54.0K | OBLIGATE FY21 FUNDS FOR ELECTRICITY AT LENEXA. |
| Oct 15, 2020 | 16 | $19.2K | INCREASE FY20 FUNDS FOR ELECTRICITY AT LENEXA. |
| Jan 13, 2020 | 15 | $487.5K | INCREASE FY20 FUNDS FOR ELECTRICITY AT LENEXA. |
| Dec 31, 2019 | 14 | $152 | INCREASE FY19 FUNDS FOR ELECTRICITY AT LENEXA. |
| Nov 6, 2019 | 13 | $162.5K | INCREMENTALLY FUND FY20 FOR ELECTRICITY AT LENEXA. |
| Oct 31, 2019 | 12 | $2.2K | INCREASE FY19 FUNDS FOR ELECTRICITY AT LENEXA. |
| Jul 25, 2019 | 11 | $-3.0K | DE-OBLIGATE EXCESS FY18 FUNDS FOR ELECTRICITY AT LENEXA. |
| Dec 6, 2018 | 10 | $487.5K | FULLY FUND FY19 FOR ELECTRICITY AT LENEXA. |
| Oct 24, 2018 | 9 | $162.5K | INCREMENTALLY FUND FY19 FOR ELECTRICITY AT LENEXA. |
| Sep 26, 2018 | 8 | $76.0K | ADD ADDITIONAL FY18 FUNDS FOR ELECTRICITY AT LENEXA. |
| Sep 7, 2018 | 7 | $0 | FY19 STAF FUNDING FOR ELECTRICITY AT LENEXA. |
| Feb 26, 2018 | 6 | $487.5K | FULLY FUND FY18 FOR ELECTRICITY AT LENEXA. |
| Feb 12, 2018 | 5 | $-6.2K | DEOBLIGATE FY17 FUNDS FOR ELECTRICITY AT LENEXA. |
| Oct 30, 2017 | 4 | $162.5K | INCREMENTALLY FUND FY18 FOR ELECTRICITY AT LENEXA. |
| Sep 18, 2017 | 3 | $0 | STAF FY18 FOR ELECTRICITY AT LENEXA. IGF::OT::IGF FOR OTHER FUNCTIONS |
| Aug 18, 2017 | 2 | $150.0K | ADD ADDITIONAL FUNDS FOR FY17 FOR ELECTRICITY AT LENEXA. IGF::OT::IGF FOR OTHER FUNCTIONS |
| Oct 25, 2016 | 1 | $500.0K | FULLY FUND FY17 FOR ELECTRICITY AT LENEXA. IGF::OT::IGF FOR OTHER FUNCTIONS |
| Oct 1, 2016 | 0 | $0 | NEW ELECTRICITY TASK ORDER AT LENEXA. IGF::OT::IGF FOR OTHER FUNCTIONS |