Federal contract award
NNG12FD66C
ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | National Aeronautics and Space Administration |
| Office | NASA GODDARD SPACE FLIGHT CENTER |
| NAICS | 336414 — Guided Missile and Space Vehicle Manufacturing |
| PSC | 1820 — Space Vehicle Components |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | COST PLUS AWARD FEE |
| Obligations | $443.3M |
| Current contract value | $457.0M |
| Potential contract value / ceiling | $457.0M |
| Start date | Jan 19, 2012 |
| Current end date | Mar 31, 2027 |
| Potential end date | Mar 31, 2027 |
| Latest award activity | Jun 25, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 149 of 149 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 25, 2026 | 148 | $2.0M | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jun 16, 2026 | 147 | $0 | ADD 52.222-90 IAW EO 14398. THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| May 18, 2026 | 146 | $0 | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Apr 29, 2026 | 145 | $4.0M | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Apr 22, 2026 | 144 | $0 | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Feb 12, 2026 | 143 | $1.5M | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Sep 30, 2025 | 142 | $500.0K | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Sep 25, 2025 | 141 | $579.0K | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Aug 7, 2025 | 140 | $2.0M | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jul 14, 2025 | 139 | $1.0M | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jul 3, 2025 | 138 | $0 | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS. |
| May 14, 2025 | 137 | $0 | REMOVAL OF CLAUSES/DRDS IAW EO 14148. THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH AND -APOPHIS EXPLORER (OSIRIS-REX,-APEX) PROJECT FOR THE SAMPLE RETURN OF ASTEROIDS |
| Mar 19, 2025 | 135 | $0 | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH AND APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Mar 19, 2025 | 136 | $300.0K | REMOVAL OF CLAUSES/DRDS IAW PCD 25-01, -02, EO 14148. CONTRACTOR SHALL PROVIDE RESOURCES TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH & APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS |
| Mar 5, 2025 | 134 | $1.5M | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH AND APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jan 27, 2025 | 133 | $0 | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH AND APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jan 24, 2025 | 132 | $0 | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH AND APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jan 23, 2025 | 131 | $0 | REMOVAL OF CLAUSES/DRDS IAW EO 14148. THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH AND APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Jan 2, 2025 | 130 | $480.3K | THE CONTRACTOR SHALL PROVIDE RESOURCES NECESSARY TO SUPPORT ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY REGOLITH AND APOPHIS EXPLORER (OSIRIS-REX,-APEX) MISSION FOR THE SAMPLE RETURN OF ASTEROIDS. |
| Dec 30, 2024 | 129 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 10, 2024 | 128 | $700.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 1, 2024 | 127 | $-120.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 30, 2024 | 126 | $1.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 19, 2024 | 125 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 28, 2024 | 124 | $-800.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 5, 2024 | 123 | $3.5M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Apr 18, 2024 | 122 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Apr 4, 2024 | 121 | $777.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 21, 2024 | 120 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 7, 2024 | 118 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 7, 2024 | 119 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 11, 2024 | 117 | $2.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 29, 2023 | 116 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 2, 2023 | 115 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 22, 2023 | 114 | $500.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 20, 2023 | 112 | $1.6M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 20, 2023 | 113 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 8, 2023 | 111 | $10.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 14, 2023 | 110 | $400.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 5, 2023 | 109 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 9, 2022 | 108 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 19, 2022 | 107 | $1.5M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 25, 2022 | 106 | $2.2M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Apr 5, 2022 | 105 | $700.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 26, 2022 | 104 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 6, 2022 | 103 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 16, 2021 | 102 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 14, 2021 | 101 | $0 | EO14042 ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 29, 2021 | 100 | $250.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 24, 2021 | 99 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 23, 2021 | 98 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Apr 14, 2021 | 97 | $3.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 15, 2021 | 96 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 23, 2020 | 95 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 26, 2020 | 94 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 15, 2020 | 93 | $10.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 5, 2019 | 91 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 5, 2019 | 92 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 30, 2019 | 90 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 23, 2019 | 89 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 4, 2019 | 88 | $8.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 9, 2019 | 87 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 21, 2019 | 86 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Apr 1, 2019 | 85 | $8.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 12, 2019 | 84 | $2.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 19, 2018 | 83 | $1.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 6, 2018 | 82 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 15, 2018 | 81 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 19, 2018 | 80 | $2.5M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 5, 2018 | 79 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 24, 2018 | 78 | $5.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 22, 2018 | 77 | $4.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 5, 2017 | 76 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 10, 2017 | 75 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 8, 2017 | 74 | $6.7M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 1, 2017 | 73 | $2.5M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 28, 2017 | 72 | $100.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 27, 2017 | 71 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 23, 2017 | 70 | $23.5K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 19, 2016 | 69 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 20, 2016 | 68 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 26, 2016 | 67 | $3.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 2, 2016 | 66 | $2.2M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 18, 2016 | 65 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 15, 2016 | 64 | $42.8K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 11, 2016 | 63 | $1.5M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 10, 2016 | 62 | $24.3M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 9, 2016 | 61 | $308.3K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 20, 2016 | 60 | $3.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 19, 2016 | 58 | $608.3K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 19, 2016 | 59 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 29, 2015 | 57 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 25, 2015 | 55 | $330.4K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 25, 2015 | 56 | $1.3M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 13, 2015 | 54 | $25.1M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 7, 2015 | 53 | $5.8M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 24, 2015 | 52 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 13, 2015 | 51 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 22, 2015 | 50 | $10.7M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 10, 2015 | 49 | $889.4K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 7, 2015 | 48 | $460.4K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 25, 2015 | 47 | $31.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 14, 2015 | 46 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 12, 2015 | 45 | $7.5M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 12, 2014 | 44 | $585.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 10, 2014 | 43 | $215.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Oct 30, 2014 | 42 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 30, 2014 | 41 | $496.3K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 19, 2014 | 40 | $200.2K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 29, 2014 | 39 | $16.7M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 7, 2014 | 38 | $200.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 25, 2014 | 37 | $127.6K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 15, 2014 | 36 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 11, 2014 | 35 | $413.3K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 29, 2014 | 34 | $176.7K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 9, 2014 | 33 | $114.2K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 31, 2014 | 32 | $2.2M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 5, 2014 | 31 | $64.4M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 25, 2014 | 30 | $62.1K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 13, 2014 | 29 | $634.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Feb 7, 2014 | 28 | $13.1M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 29, 2014 | 27 | $146.9K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 14, 2014 | 26 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 12, 2013 | 24 | $1.3M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 12, 2013 | 25 | $13.7M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 6, 2013 | 23 | $43.4K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 1, 2013 | 22 | $2.4M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 19, 2013 | 21 | $320.8K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 5, 2013 | 20 | $14.2M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 26, 2013 | 19 | $897.3K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 21, 2013 | 18 | $143.4K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 1, 2013 | 17 | $269.2K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 26, 2013 | 15 | $155.9K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 26, 2013 | 16 | $813.1K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 11, 2013 | 14 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jun 5, 2013 | 13 | $38.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 31, 2013 | 12 | $12.0M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 15, 2013 | 11 | $850.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 1, 2013 | 10 | $5.7M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Mar 12, 2013 | 9 | $416.5K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Dec 4, 2012 | 8 | $3.1M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 21, 2012 | 7 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Nov 20, 2012 | 6 | $6.6M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Sep 12, 2012 | 5 | $0 | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Aug 9, 2012 | 4 | $681.0K | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 5, 2012 | 3 | $11.1M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jul 2, 2012 | 2 | $1.1M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| May 9, 2012 | 1 | $6.2M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
| Jan 19, 2012 | 0 | $14.7M | ORIGINS SPECTRAL INTERPRETATION RESOURCE IDENTIFICATION SECURITY-REGOLITH EXPLORER (OSIRIS-REX) PHASE B EFFORT. UNDER THIS CONTRACT, THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO COMPLETE MISSION DESIGN AND REQUIREMENTS FLOW DOWN ACTIVITIES CULMINATING IN AN OSIRIS-REX PROJECT MISSION DESIGN REVIEW (MDR). THE CONTRACTOR SHALL PROVIDE THE RESOURCES NECESSARY TO SUPPORT THE OSIRIS-REX PROJECT TO DEFINE AND COMPLETE THE DEFINITION OF THE PRELIMINARY DESIGN, AND THE PLANS FOR DEVELOPMENT, MANUFACTURE, TEST, VERIFICATION AND OPERATION OF A FLIGHT SYSTEM. |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
65/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 65/100. Available recorded signals: 60 points.
- Contract end 2027-03-31 (157 days from calculation)
- +35 points
- 1 historical awards in this buyer and category group
- +0 points
- 149 recorded award transactions
- +10 points
- Latest award action: 2026-06-25
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.