Federal contract award

SAQMMA17C0314

DESIGN-BID-BUILD CONSTRUCTION SERVICES FOR THE ATHENS COMPOUND MAJOR REHAB IN GREECE.IGF::OT::IGF

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of State
OfficeACQUISITIONS - AQM MOMENTUM
NAICS236220 — Commercial and Institutional Building Construction
PSCY1AA — CONSTRUCTION OF OFFICE BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$239.5M
Current contract value$239.5M
Potential contract value / ceiling$239.5M
Start dateSep 29, 2017
Current end dateDec 31, 2026
Potential end dateDec 31, 2026
Latest award activitySep 10, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 41 of 41 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 10, 2026P00040$241.4KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFP 150 FOR WEST TUNNEL UPGRADE.
Aug 24, 2026P00039$7.0MTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFP 131 FOR EXISTING GAS PIPE REPLACEMENT AND 148 FOR FIRE LIVE SAFETY SYSTEMS CHANGES.
Jun 2, 2026P00038$151.8KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFP 131 FOR EXISTING GAS PIPE REPLACEMENT AND 148 FOR FIRE LIVE SAFETY SYSTEMS CHANGES.
Apr 8, 2026P00037$0THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTRATIVELY CHANGE THE INVOICING PROCEDURES TO ALLOW FOR THE CONTRACTOR TO SUBMIT INVOICES VIA THE IPP SYSTEM. THIS MODIFICATION DOES NOT CHANGE THE CONTRACT COMPLETION DATE.
Feb 24, 2026P00036$320.2KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN RFPS FOR RELOCATING LIGHT FIXTURES, ADDITIONAL DUCT RISERS, TECHNICAL EQUIPMENT, AND WATER LINES.
Jan 15, 2026P00035$30.6KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN RFP 137 FOR FIBER OPTIC CABLE INSTALLATION.
Dec 19, 2025P00034$5.5MTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN RFP 129 AND EXTEND THE PERIOD OF PERFORMANCE TO MARCH 21, 2026.
Nov 14, 2025P00033$0THE PURPOSE OF THIS MODIFICATION IS TO ADMINISTRATIVELY CHANGE THE INVOICING PROCEDURES TO ALLOW FOR THE CONTRACTOR TO SUBMIT INVOICES VIA THE IPP SYSTEM. THIS MODIFICATION DOES NOT CHANGE THE CONTRACT COMPLETION DATE.
Jul 21, 2025P00032$0THIS MODIFICATION IS WRITTEN TO CHANGE THE DELEGATED COR TO JORGE VAZQUEZ AND EXTEND THE PERIOD OF PERFORMANCE TO OCTOBER 4, 2025.
Jun 13, 2025P00031$491.8KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS FOR INSPECTION AND CLEANING OF TWO TANKS FOR EMBASSY BACKUP GENERATOR, INSTALLATION OF 53MM CONDUITS ON ROOF, AND TELECOM ROOM
May 12, 2025P00030$147.8KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS FOR INSPECTION AND CLEANING OF TWO TANKS FOR EMBASSY BACKUP GENERATOR, INSTALLATION OF 53MM CONDUITS ON ROOF, AND TELECOM ROOM
Mar 24, 2025P00029$0THIS MODIFICATION IS WRITTEN TO EXTEND THE PERIOD OF PERFORMANCE BY 120 DAYS FROM MARCH 16, 2025 TO JULY 14, 2025. ALL TERMS AND CONDITIONS REMAIN UNCHANGED.
Dec 3, 2024P00028$243.8KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS FOR STEEL COVER FOR ELECTRICAL DUCT BANK, UNDER SLAB SANITARY LINE REPLACEMENT, AND FRENCH DRAIN UNDER BASEMENT SLAB.
May 14, 2024P00027$299.7KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS FOR WATERPROOFING WORKS, RELOCATION OF WALL MOUNTED PHONE, WEST TUNNEL STRUCTURE DEMO, AND CHANGES TO FEBR DOOR.
Jan 17, 2024P00026$295.3KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 110, 111, AND 114 - 117.
Sep 20, 2023P00025$1.6MTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 85, 89, 90 THROUGH 102, AND 104 THROUGH 109.
Mar 31, 2023P00024$0ATHENS MAJOR REHAB. THIS MODIFICATION IS WRITTEN TO INCORPORATE THE GUIDE TO INTERNET COLLABORATION SYSTEMS AS J.1.15 AND REVISE SECTIONS E AND H TO UTILIZE OTHER GOVERNMENT-PROVIDED/APPROVED SBU SYSTEMS IN ADDITION TO PROJNET.
Dec 20, 2022P00023$50.9KATHENS MAJOR REHAB. THIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS RFPS 82 THROUGH 84 AND 86 THROUGH 88.
Apr 28, 2022P00022$2.8MATHENS MAJOR REHAB. THIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 76 THROUGH 81. THIS MOD INCLUDES A 150 DAY EXTENSION TO THE CONTRACT PERIOD OF PERFORMANCE TO AUGUST 18 2024
Jan 25, 2022P00021$2.1MATHENS MAJOR REHAB. THIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 56, 59, 60, 68 75, AND REA 01. THIS MOD INCLUDES A 385 DAY EXTENSION TO THE CONTRACT PERIOD OF PERFORMANCE TO MARCH 18, 2024.
Sep 20, 2021P00020$0ATHENS MAJOR REHAB. ADMINISTRATIVE MODIFICATION TO CORRECT AND UPDATE THE IPP APPROVAL CODE.
Jun 18, 2021P00019$192.5KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 50, 61, AND 63 - 67.
Apr 8, 2021P00018$566.4KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 49, 58, AND 62 AND EXTEND THE CONTRACT PERIOD OF PERFORMANCE BY 72 DAYS TO FEBRUARY 27, 2023.
Mar 3, 2021P00017$2.0MTHIS MODIFICATION IS WRITTEN TO PROVIDE ADDITIONAL FUNDING FOR CLIN 0010: ALLOWANCE FOR REIMBURSEMENT COVID-19.
Feb 16, 2021P00016$0ATHENS COMPOUND MAJOR REHAB
Feb 11, 2021P00015$103.4KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 47, 48, 51 THROUGH 55, AND 57.
Jan 5, 2021P00014$698.5KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFP 46A - IMPLEMENTATION OF DESIGN BULLETIN 10 AND EXTEND THE CONTRACT PERIOD OF PERFORMANCE TO DECEMBER 17, 2022.
Sep 29, 2020P00013$145.0KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFP 46 - IMPLEMENTATION OF DESIGN BULLETIN 10.
Sep 10, 2020P00012$1.1MMOD TO INCORPORATE AND FUND MULTIPLE RFPS AND EXTEND THE PERIOD OF PERFORMANCE TO OCTOBER 28, 2022.
Jul 15, 2020P00011$185.9KMOD TO INCORPORATE AND FUND MULTIPLE RFPS.
May 28, 2020P00010$3.4MADD A CLIN FOR ALLOWANCE FOR REIMBURSEMENT COVID-19 COST ASSOCIATED WITH AGREED MEASURES TO REDUCE/MITIGATE COLLATERAL DELAY TO PROJECT DELIVERY.
May 11, 2020P00009$319.9KINCORPORATE AND PROVIDE FUNDING FOR RFP-14 DESIGN CLARIFICATIONS FOR DESIGN BULLETIN 6.
May 4, 2020P00008$437.8KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 18, 20, 25, 31, 34, 35, 37, 38, 39 AND 31.
Mar 11, 2020P00007$44.4KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 15, 21, 23, 24, 26, 28, AND 30.
Dec 10, 2019P00006$676.7KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 3, 8, 11, 12, 17 AND EXTEND THE CONTRACT PERIOD OF PERFORMANCE TO 10/11/2022.
Jun 18, 2019P00005$48.3KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 009A, 010, 013, AND 016.
Feb 4, 2019P00004$187.3KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN RFP 007.
Nov 30, 2018P00003$150.8KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN RFP 005.
Sep 28, 2018P00002$250.4KTHIS MODIFICATION IS WRITTEN TO INCORPORATE THE REVISED/CHANGED PERFORMANCE REQUIREMENT AS DESCRIBED IN THE FOLLOWING: RFPS 001, 002, 004, AND 006.
Jul 19, 2018P00001$0CHANGE ORDER FOR ELECTRICAL SYSTEM CHANGES IGF::OT::IGF
Sep 29, 20170$207.6MDESIGN-BID-BUILD CONSTRUCTION SERVICES FOR THE ATHENS COMPOUND MAJOR REHAB IN GREECE.IGF::OT::IGF

Estimated positioning window

Oct 25, 2026 – Jan 23, 2027

Recompete signal:
80/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 80/100. Available recorded signals: 75 points.

Contract end 2026-12-31 (67 days from calculation)
+35 points
276 historical awards in this buyer and category group
+15 points
41 recorded award transactions
+10 points
Latest award action: 2026-09-10
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.