Federal contract award

SP060011C8275

PRIVATIZATION OF THE ELECTRICAL DISTRIBUTION SYSTEM AT ABERDEEN PROVING GROUND, MARYLAND

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeDLA ENERGY
NAICS221122 — Electric Power Distribution
PSCS112 — Electric Services
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIXED PRICE REDETERMINATION
Obligations$237.3M
Current contract value$817.7M
Potential contract value / ceiling$817.7M
Start dateSep 30, 2011
Current end dateAug 31, 2062
Potential end dateAug 31, 2062
Latest award activityJun 2, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 200 of 257 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 2, 2026P00256$24.3KELECTRIC UTILITY SERVICES
May 19, 2026P00255$0ELECTRIC UTILITY SERVICES
May 5, 2026P00254$9.1MELECTRIC UTILITY SERVICES
Mar 30, 2026P00253$4.6MELECTRIC UTILITY SERVICES
Feb 24, 2026P00252$2.3MELECTRIC UTILITY SERVICES
Feb 17, 2026P00251$5.4KELECTRIC UTILITY SERVICES
Nov 25, 2025P00250$9.1MELECTRIC UTILITY SERVICES
Sep 25, 2025P00249$130.9KELECTRIC UTILITY SERVICES
Sep 9, 2025P00247$2.3MELECTRIC UTILITY SERVICES
Sep 9, 2025P00248$0ELECTRIC UTILITY SERVICES
Aug 12, 2025P00246$103.3KELECTRIC UTILITY SERVICES
Jul 28, 2025P00245$4.6MELECTRIC UTILITY SERVICES
Jul 2, 2025P00244$0ELECTRIC UTILITY SERVICES
Jun 30, 2025P00243$323.1KELECTRIC UTILITY SERVICES
Jun 10, 2025P00242$2.3MELECTRIC UTILITY SERVICES
May 12, 2025P00241$2.3MELECTRIC UTILITY SERVICES
Mar 31, 2025P00240$0ELECTRIC UTILITY SERVICES
Mar 26, 2025P00239$2.3MELECTRIC UTILITY SERVICES
Mar 7, 2025P00238$78.3KELECTRIC UTILITY SERVICES
Jan 28, 2025P00237$6.8MELECTRIC UTILITY SERVICES
Oct 29, 2024P00236$6.8MELECTRIC UTILITY SERVICES
Oct 16, 2024P00235$0ELECTRIC UTILITY SERVICES
Sep 18, 2024P00234$248.8KELECTRIC UTILITY SERVICES
Sep 10, 2024P00233$0ELECTRIC UTILITY SERVICES
Aug 27, 2024P00232$43.0KELECTRIC UTILITY SERVICES
Jul 25, 2024P00231$376.7KELECTRIC UTILITY SERVICES
Jul 19, 2024P00230$45.9KELECTRIC UTILITY SERVICES
Jul 11, 2024P00229$0ELECTRIC UTILITY SERVICES
Jun 20, 2024P00228$424.6KELECTRIC UTILITY SERVICES
May 21, 2024P00227$0ELECTRIC UTILITY SERVICES
May 1, 2024P00226$13.4MELECTRIC UTILITY SERVICES
Mar 22, 2024P00225$2.3MELECTRIC UTILITY SERVICES
Feb 27, 2024P00224$296.2KELECTRIC UTILITY SERVICES
Feb 20, 2024P00223$2.3MELECTRIC UTILITY SERVICES
Jan 22, 2024P00222$2.3MELECTRIC UTILITY SERVICES
Jan 10, 2024P00221$0ELECTRIC UTILITY SERVICES
Dec 15, 2023P00220$2.3MELECTRIC UTILITY SERVICES
Nov 22, 2023P00219$2.3MELECTRIC UTILITY SERVICES
Oct 31, 2023P00218$2.3MELECTRIC UTILITY SERVICES
Sep 28, 2023P00216$0ELECTRIC UTILITY SERVICES
Sep 28, 2023P00217$157.1KELECTRIC UTILITY SERVICES
Sep 26, 2023P00214$1.8MELECTRIC UTILITY SERVICES
Sep 26, 2023P00215$304.9KELECTRIC UTILITY SERVICES
Sep 8, 2023P00213$0ELECTRIC UTILITY SERVICES
Aug 15, 2023P00212$52.7KELECTRIC UTILITY SERVICES
Jun 30, 2023P00211$0ELECTRIC UTILITY SERVICES
Jun 21, 2023P00210$15.0KELECTRIC UTILITY SERVICES
May 17, 2023P00209$141.7KELECTRIC UTILITY SERVICES
May 12, 2023P00206$0ELECTRIC UTILITY SERVICES
May 12, 2023P00207$408.3KELECTRIC UTILITY SERVICES
May 12, 2023P00208$42.6KELECTRIC UTILITY SERVICES
May 4, 2023P00205$10.6MELECTRIC UTILITY SERVICES
Mar 21, 2023P00204$128.3KELECTRIC UTILITY SERVICES
Mar 9, 2023P00203$4.3MELECTRIC UTILITY SERVICES
Jan 20, 2023P00202$4.3MELECTRIC UTILITY SERVICES
Dec 27, 2022P00201$2.1MELECTRIC UTILITY SERVICES
Nov 15, 2022P00200$0ELECTRIC UTILITY SERVICES
Oct 26, 2022P00199$4.3MELECTRIC UTILITY SERVICES
Oct 24, 2022P00198$0ELECTRIC UTILITY SERVICES
Sep 23, 2022P00197$1.3MELECTRIC UTILITY SERVICES
Aug 16, 2022P00196$51.3KELECTRIC UTILITY SERVICES
Jun 28, 2022P00195$8.1MELECTRIC UTILITY SERVICES
May 26, 2022P00194$2.0MELECTRIC UTILITY SERVICES
May 4, 2022P00193$0ELECTRIC UTILITY SERVICES
Apr 28, 2022P00192$2.0MELECTRIC UTILITY SERVICES
Mar 30, 2022P00191$2.0MELECTRIC UTILITY SERVICES
Mar 14, 2022P00190$0ELECTRIC UTILITY SERVICES
Jan 26, 2022P00189$0ELECTRIC UTILITY SERVICES
Dec 29, 2021P00188$6.1MELECTRIC UTILITY SERVICES
Nov 10, 2021P00187$0ELECTRIC UTILITY SERVICES
Oct 27, 2021P00186$4.1MELECTRIC UTILITY SERVICES
Sep 22, 2021P00185$207.1KELECTRIC UTILITY SERVICES
Aug 26, 2021P00184$2.0MELECTRIC UTILITY SERVICES
Jul 29, 2021P00183$987.9KELECTRIC UTILITY SERVICES
Jul 1, 2021P00182$987.9KELECTRIC UTILITY SERVICES
Jun 29, 2021P00181$4.2MELECTRIC UTILITY SERVICES
Jun 15, 2021P00180$45.8KELECTRIC UTILITY SERVICES
Jun 3, 2021P00179$0ELECTRIC UTILITY SERVICES
May 25, 2021P00178$110.1KELECTRIC UTILITY SERVICES
May 19, 2021P00177$1.0MELECTRIC UTILITY SERVICES
Apr 15, 2021P00176$1.0MELECTRIC UTILITY SERVICES
Apr 5, 2021P00175$0ELECTRIC UTILITY SERVICES
Mar 10, 2021P00174$191.2KELECTRIC UTILITY SERVICES
Feb 17, 2021P00173$2.1MELECTRIC UTILITY SERVICES
Jan 13, 2021P00172$1.0MELECTRIC UTILITY SERVICES
Nov 25, 2020P00171$2.1MELECTRIC UTILITY SERVICES
Oct 30, 2020P00170$1.0MELECTRIC UTILITY SERVICES
Sep 30, 2020P00169$769.6KELECTRIC UTILITY SERVICES
Sep 29, 2020P00168$-4.2KELECTRIC UTILITY SERVICES
Sep 22, 2020P00167$101.3KELECTRIC UTILITY SERVICES
Sep 10, 2020P00166$154.0KELECTRIC UTILITY SERVICES
Sep 9, 2020P00165$0ELECTRIC UTILITY SERVICES
Aug 31, 2020P00164$80.7KELECTRIC UTILITY SERVICES
Aug 26, 2020P00162$1.1MELECTRIC UTILITY SERVICES
Aug 26, 2020P00163$1.0MELECTRIC UTILITY SERVICES
Jul 20, 2020P00161$0ELECTRIC UTILITY SERVICES
Jul 15, 2020P00160$203.4KELECTRIC UTILITY SERVICES
Jul 10, 2020P00159$193.5KELECTRIC UTILITY SERVICES
Jun 25, 2020P00158$220.4KELECTRIC UTILITY SERVICES
Jun 12, 2020P00157$141.5KELECTRIC UTILITY SERVICES
May 8, 2020P00156$340.2KELECTRIC UTILITY SERVICES
Mar 26, 2020P00155$890.0KELECTRIC UTILITY SERVICES
Feb 21, 2020P00154$7.8MELECTRIC UTILITY SERVICES
Jan 17, 2020P00153$1.0MELECTRIC UTILITY SERVICES
Dec 19, 2019P00152$1.0MREVISES CLIN 0008, 0054, AND 0058, TO ESTABLISH AND FUND CLIN 008AD TO PROVIDE FUNDING FOR ONE MONTH (88 OF 600) OF THE UTILITY SERVICES CHARGE, PROVIDE FUNDING FOR ONE MONTH (88 OF 600) FOR EACH AMORTIZED PAYMENT FOR HYBRID PROJECTS 1 AND 3.
Oct 31, 2019P00150$1.0MPROVIDE FUNDING FOR ONE MONTH (86 OF 600) OF THE UTILITY SERVICE CHARGE, PROVIDE FUNDING FOR ONE MONTH (86 OF 600) FOR EACH AMORTIZED PAYMENT FOR HYBRID PROJECTS 1 AND 3.
Oct 31, 2019P00151$1.0MPROVIDE FUNDING FOR ONE MONTH (87 OF 600) OF THE UTILITY SERVICE CHARGE, PROVIDE FUNDING FOR ONE MONTH (87 OF 600) FOR EACH AMORTIZED PAYMENT FOR HYBRID PROJECTS 1 AND 3.
Sep 18, 2019P00148$381.6KESTABLISH AND FUND CONTRACT LINE ITEM NUMBER 0128 AUTHORIZING CITY LIGHT POWER ABERDEEN TO COMPLETE PROJECT APG-E-RFP-19-09, NEW SERVICE CONNECTION TO BUILDING 328.
Sep 18, 2019P00149$114.4KESTABLISH AND FUND CLIN 0129 FOR PROJECT APG-E-RFP-19- 11, ATC SMALL ARMS AND CLIN 0130 FOR PROJECT APG-E-RFP-19-08, FY19 AVIAN PROTECTION. BOTH PROJECTS TO BE PERFORMED AT ABERDEEN PROVING GROUND, MD.
Aug 8, 2019P00147$5.8KESTABLISH AND FUND CONTRACT LINE ITEM NUMBER 0127 AUTHORIZING CITY LIGHT POWER ABERDEEN CLPA TO COMPLETE PROJECT APG-E-RFP-19-07, NEW SERVICE TO SECURITY GATE AT GRACES QUARTERS.
Jun 27, 2019P00146$1.6MTHIS MODIFICATION REVISES THE PERIOD OF PERFORMANCE OF CLINS 0054 AND 0058 TO REFLECT COMPLETION OF ABERDEEN AREA AND EDGEWOOD AREA 35KV SYSTEM UPGRADES AHEAD OF SCHEDULE; CLARIFIES THE STRUCTURE OF CLINS 0054, 0055, 0058 AND 0059 TO DISTINGUISH THE PERIOD OF PERFORMANCE OF THE ISDC FROM THE AMORTIZATION PERIOD; AND PROVIDES FY19 FUNDING FOR SUBCLINS 0054AA AND 0058AA FOR CONTRACT MONTHS 83 THROUGH 85 OF 406.
Apr 22, 2019P00145$238.6KTHIS MODIFICATION ESTABLISHES AND FUNDS CLIN 0126 TO AUTHORIZE CLPA TO COMPLETE NEW SERVICE CONNECTION, APG-E-PR-19-04, B384F HOUSE POWER
Apr 17, 2019P00144$130.4KTHIS MODIFICATION ESTABLISHES AND FUNDS CLINS 0123, 0124 AND 0125 TO AUTHORIZE CLPA TO COMPLETE NEW SERVICE CONNECTION PROJECTS IDENTIFIED AS APG-E-PR-19-01, BLDG 1059 FIRE STATION, APG-E-PR-19-03, LIVING LEGACY MEMORIAL, AND APG-E-PR-19-05, HARFORD BLVD CROSSWALK.
Apr 11, 2019P00143$115.2KTHIS MODIFICATION ESTABLISHES AND FUNDS CLIN 0122, TO AUTHORIZE CLPA TO COMPLETE PROJECT IDENTIFIED AS APG-E-PR-05, EDGEWOOD AREA 3200 BLOCK.
Mar 20, 2019P00142$28.1KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FISCAL YEAR 2019 (FY19) UNEXPLODED ORDINANCE(UXO) SWEEPS FOR ROUTINE O&M TASKS AND PLANNED OUTAGES DURING NON-DUTY HOURS AND TO EXTEND THE PERIOD OF PERFORMANCE (POP) FOR THE NEW UNDERGROUND ELECTRICAL SERVICES WORK TO BUILDING 250 AT CLIN 0114.
Feb 22, 2019P00141$207.0KTHIS MODIFICATION AUTHORIZES CITY LIGHT AND POWER ABERDEEN TO COMPLETE PROJECT APG-E-PR-18-009, IN ACCORDANCE WITH CONTRACT SECTION C.11.3, CONNECTIONS AND DISCONNECTIONS. INSTALL NEW SERVICE TO THE UH-72 SIMULATION FACILITY LOCATED ON THE EDGEWOOD AREA OF ABERDEEN PROVING GROUND, MD,
Feb 3, 2019P00140$4.6MTHIS MODIFICATION REDUCES THE UTILITY SERVICE CHARGE (USC) DUE TO TAX CUTS AND JOBS ACT; FUND CLIN 0007AC REFLECTING A ONE TIME CREDIT FOR OVER OBLIGATED USCS IN OCT - DEC 2018; ESTABLISH AND FUND CLINS 0007AD AND 0008AA FOR THE JAN - SEPT 2019 USC; AND ESTABLISH AND FUND CLIN 0008AB FOR THE REMAINING USCS IN CONTRACT YEAR 8.
Dec 31, 2018P00139$0CORRECTS PREVIOUSLY ESTABLISHED ACRN; PERFORMS VARIOUS NO-COST POP EXTENSIONS, AND INCORPORATES FAR CLAUSE 52.204-23: PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018).
Nov 8, 2018P00138$1.6MTHIS MODIFICATION ESTABLISHES AND FUNDS ON SUBCLIN 0007AB FOR 3 MONTHS OF UTILITY SERVICE CHARGES(USC)(MONTHS 74-76 OF 600) AND TO ESTABLISH SUBCLIN 0007AC FOR THE 8 MONTHS OF USC (MONTHS 77-84 OF 600) IN CONTRACT YEAR 7; AND TO ESTABLISH ACRN CX TO FUND SUBCLIN 0007AB.
Sep 27, 2018P00137$126.2KTHIS MODIFICATION ESTABLISHES AND FUNDS CLIN 0119, TO AUTHORIZE CLP TO COMPLETE A NEW SERVICE CONNECTION IDENTIFIED AS PROJECT APG-E-PR-18-007, NEW SERVICE CONNECTION AT EDGEWOOD BUILDING 5106.
Sep 26, 2018P00136$0THIS MODIFICATION DEOBLIGATES ALL FUNDS ON ACRN CS AND ESTABLISHES ACRN CW TO REPLACE THE FUNDING ON CLIN 0115 FOR THE REMOVAL OF AN UNDERGROUND STORAGE TANK FROM ABERDEEN AREA 3500 BLOCK OF RODMAN ROAD.
Sep 20, 2018P00135$58.6KESTABLISHES AND FUNDS CLIN 0118, FOR WORK IDENTIFIED AS PROJECT APG-E-PR-18-008, INSTALL AVIAN PROTECTION, TO REPLACE AND/OR REPOSITION FAILED DEVICES.
Sep 19, 2018P00134$27.6KESTABLISHES AND FUNDS CLIN 0116, TO INCORPORATE FY18 UNEXPLODED ORDINANCE (UXO) SWEEPS FOR ROUTINE O&M TASKS AND PLANNED OUTAGES DURING NON-DUTY HOURS.
Jul 12, 2018P00133$13.6KESTABLISHES AND FUNDS CLIN 0115, AUTHORIZING CLPA TO COMPLETE REMOVE AN UNDERGROUND STORAGE TANK (UST) LOCATED VICINITY OF 18SVJ 01400 49703, 3500 BLOCK RODMAN ROAD, CL&P HYBRID PROJECT SUBSTATION 1.
Jul 10, 2018P00132$112.0KESTABLISHES AND FUNDS CLIN 0114, AUTHORIZING CLPA TO COMPLETE PROJECT APG-E-PR-18-002, PROVIDE NEW UNDERGROUND ELECTRICAL SERVICE TO BUILDING 250. PERIOD OF PERFORMANCE EXTENSIONS FOR PROJECTS APG-E-PR-16-006 BUILDING 5016, APG-E-PR-16-007 BUILDING 5046, APG-E-PR-18-001 BUILDING E5803 AND E5804.
Jul 3, 2018P00131$2.1MFUND SUBCLIN 0006AH FOR THREE MONTHS OF UTILITY SERVICE CHARGE (USC) FOR MONTHS 70-72, JUN 1 THROUGH AUG 31, 2018; ESTABLISH CLIN 0007, FOR CONTRACT YEAR 7 USC, ESTABLISH AND FUND SUBCLIN 0007AA FOR MONTH 73, SEP 1 THROUGH 30, 2018, AND ESTABLISH BUT NOT FUND SUBCLIN 0007AB FOR THE REMAINING 11 MONTHS OF CONTRACT YEAR 7.
Jun 19, 2018P00130$66.4KESTABLISHES AND FUNDS CLIN 0113, AUTHORIZING CLP TO COMPLETE PROJECT APG-E-PR-18-006, INSTALL PAD MOUNTED TRANSFORMER TO BUILDING 463.
Jun 7, 2018P00129$521.9KTHIS MODIFICATION IS REVISE SUBCLIN 0006AG TO FUND ONE MONTH OF UTILITY SERVICE CHARGE FOR MONTH 69, MAY 1-31, 2018; AND TO ESTABLISH BUT NOT FUND SUBCLIN 0006AH FOR THE REMAINING THREE MONTHS OF CONTRACT YEAR 6.
May 22, 2018P00128$237.0KCITY LIGHT,POWER ABERDEEN(CLPA)TO COMPLETE SERVICE UPGRADE PROJECT APG-E-PR-18-005, REWORK PRIMARY SERVICE AROUND DEER CREEK AND MARYLAND INTERSECTION. CLIN 0112 IS ESTABLISHED AND FUNDED TO AUTHORIZE CLPA TO COMPLETE.
Apr 20, 2018P00127$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO FUND SUBCLIN 0006AF TO FUND ONE MONTH OF UTILITY SERVICE CHARGE FOR MONTH 68, APR 1-30, 2018; AND TO ESTABLISH BUT NOT FUND SUBCLIN 0006AG FOR THE REMAINING FOUR MONTHS OF CONTRACT YEAR 6. THIS MODIFICATION WILL ALSO CORRECT THE ERRONEOUS ACRN PROVIDED FOR SUBCLIN 0105AB ON THE PREVIOUSLY ISSUED MODIFICATION P00121.
Apr 6, 2018P00126$56.2KTHIS MODIFICATION ESTABLISHES AND FUNDS CLIN 0111 TO COMPLETE THE SERVICE CONNECTIONS IDENTIFIED AS PROJECT APG-E-PR-18-003, INSTALL NEW UNDERGROUND ELECTRICAL SERVICE TO SHORE PARK POOL.
Feb 28, 2018P00125$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO REVISE AND FUND SUBCLIN 0006AE TO FUND TWO MONTHS OF UTILITY SERVICE CHARGES FOR MONTHS 66 - 67, FEB 1, 2018 MAR 31, 2018; AND TO ESTABLISH BUT NOT FUND SUBCLIN 0006AF FOR THE REMAINING FIVE MONTHS OF CONTRACT YEAR 6.
Feb 23, 2018P00124$165.5KTHIS MODIFICATION ESTABLISHES AND FUNDS CLIN 0110 TO COMPLETE THE SERVICE CONNECTION IDENTIFIED AS PROJECT APG-E-PR-18-004, NEW UNDERGROUND ELECTRIC SERVICE TO M FIELD.
Jan 31, 2018P00123$521.9KTHIS MODIFICATION REVISES AND FUNDS SUBCLIN 0006AD FOR ONE MONTH OF UTILITY SERVICE CHARGE FOR MMONTH 65, AND ESTABLISHES BUT DOES NOT FUND SUBCLIN 0006AE FOR THE REMAINING EIGHT MONTHS OF CONTRACT YEAR 6; ALSO ISSUES A NO-COST PERIOD OF PERFORMANCE EXTENSION FOR THE PROJECTS IDENTIFIED AS APG-E-PR-16-006, AND APG-E-PR-16-007.
Jan 29, 2018P00122$124.8KTHIS MODIFICATION ESTABLISHES CLIN 0109 FOR THE SERVICE CONNECTION IDENTIFIED AS PROJECT APG-E-PR-18-001, NEW UNDERGROUND ELECTRIC SERVICE TO BUILDINGS E5803 AND E5804.
Dec 20, 2017P00121$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FY18 FUNDING FOR DECEMBER 2017 UTILITY SERVICE CHARGE. ALSO TO ISSUE A "NO COST TO THE GOV'T" EXTENSION TO SUBCLIN 0105AB PERIOD OF PERFORMANCE FOR TWO MONTHS FROM FEBRUARY 1, 2018 UNTIL APRIL 1, 2018.
Oct 17, 2017P00120$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND 2 MONTHS OF FY18 FUNDING FOR OCTOBER 1 - NOVEMBER 30, 2017 UTILITY SERVICE CHARGES.
Oct 16, 2017P00119$0THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION G CONTRACT ADMINISTRATION DATA, PARAGRAPH G.1 CONTRACTING OFFICER TO UPDATE THE CONTRACTING OFFICER NAME AND CONTACT INFORMATION.
Sep 21, 2017P00118$0THE PURPOSE OF THIS MODIFICATION IS TO CORRECT AN ADMINISTRATIVE ERROR ON THE UNIT PRICE.
Sep 13, 2017P00117$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION FOR THE PROJECTS IDENTIFIED AS APG-E-PR-16-006 BUILDING 5016 AND APG-E-PR-16-007 BUILDING 5046.
Aug 15, 2017P00116$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION FOR THE ABERDEEN KENNEL PROJECT IDENTIFIED IN THE CONTRACT AS APG-E-PR-17-004.
Aug 11, 2017P00115$0THE PURPOSE OF THIS MODIFICATION IS TO ADD CLPA'S CONTACT INFO.
Aug 10, 2017P00114$0THE PURPOSE OF THIS MODIFICATION IS TO ACKNOWLEDGE CITY LIGHT&POWER ABERDEEN'S ASSIGNMENT OF CLAIMS.
Aug 2, 2017P00113$0THIS MODIFICATION ISSUES A NO-COST PERIOD OF PERFORMANCE EXTENSION FOR THE ARC BUILDING PROJECT IDENTIFIED AS APG-E-PR-17-006.
Jul 18, 2017P00112$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION B.3 SCHEDULE AND SECTION G.6 ACCOUNTING AND APPROPRIATION DATA, TO ESTABLISH AND FUND TWO (2) MONTHS OF UTILITY SERVICE CHARGES (USC) FOR THE REMAINING TWO (2) MONTHS OF FY17.
Jul 14, 2017P00110$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AJ FOR ONE (1) MONTH OF FY17 UTILITY SERVICE CHARGE.
Jul 14, 2017P00111$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION FOR THE PROJECT IDENTIFIED AS APG-E-PR-15-006 C4ISR INTERTIE AUTOMATION.
Jun 19, 2017P00109$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AH FOR ONE (1) MONTH OF FY17 UTILITY SERVICE CHARGE.
Jun 14, 2017P00107$0THE PURPOSE OF THIS MODIFICATION IS TO RECOGNIZE THE CHANGE IN THE CONTRACTOR'S NAME.
Jun 14, 2017P00108$0THE PURPOSE OF THIS MODIFICATION IS FOR ADMINISTRATIVE CHANGES TO UPDATE CONTRACT CLAUSES.
May 15, 2017P00106$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AG FOR ONE (1) MONTH OF FY17 UTILITY SERVICE CHARGE.
May 12, 2017P00105$0THE PURPOSE FOR THIS MODIFICATION IS TO INCORPORATING ATTACHMENT J12, SAMPLE AMORTIZATION SCHEDULE FOR REVISED SCHEDULE 3.
May 3, 2017P00104$0THE PURPOSE OF THIS MODIFICATION IS TO REVISE THE B.3 SCHEDULE FOR CONTRACT LINE ITEM NUMBER (CLIN) 0091. CLIN 0091 ORIGINALLY ESTABLISHED IN MODIFICATION P00056 AND LAST REVISED IN P00077, IS FURTHER REVISED BY THIS MODIFICATION TO ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION FOR THE PUBLIC HEALTH COMMAND PROJECT IDENTIFIED IN THE CONTRACT AS APG-E-PR-15-004.
Apr 20, 2017P00103$0THE PURPOSE OF THIS MODIFICATION IS TO RECOGNIZE A NOVATION AGREEMENT BETWEEN CITY LIGHT&POWER AND CITY LIGHT&POWER ABERDEEN. THE ADDRESS AND EFT INFORMATION HAS NOT BEEN CHANGED AT THE TIME THIS MODIFICATION WAS EXECUTED.
Mar 23, 2017P00102$0THE PURPOSE OF THIS MODIFICATION IS TO RECOGNIZED AN AGREEMENT BETWEEN CLP AND UP POWER.
Mar 17, 2017P00101$0THE PURPOSE OF THIS MODIFICATION IS TO PROCESS AN AGREEMENT BETWEEN US POWER AND CLP.
Mar 9, 2017P00100$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AF FOR TWO (2) MONTHS OF FY17 UTILITY SERVICE CHARGE.
Feb 23, 2017P00099$21.8KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE THE CONTRACTOR TO PERFORM THE SERVICE CONNECTION IDENTIFIED AS PROJECT APG-E-PR-17-005 FOR BUILDING 4508.
Feb 21, 2017P00096$108.6KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE CITY LIGHT&POWER (CLP) TO PERFORM THE SERVICE CONNECTION IDENTIFIED AS PROJECT APG-E-PR-17-004 - ABERDEEN MILITARY DOG KENNEL.
Feb 21, 2017P00097$64.0KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE CITY LIGHT&POWER (CLP) TO PERFORM THE SERVICE CONNECTION IDENTIFIED AS PROJECT APG-E-PR-17-003.
Feb 21, 2017P00098$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AE FOR ONE (1) MONTH OF FY17 UTILITY SERVICE CHARGE.
Feb 13, 2017P00095$371.3KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH CLIN 0105 AND AUTHORIZE CITY LIGHT&POWER (CLP) TO PERFORM THE SERVICE CONNECTION IDENTIFIED AS APG-E-PR-17-006 - ARC BUILDING.
Jan 27, 2017P00094$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE NO-COST PERIOD OF PERFORMANCE EXTENSIONS FOR PROJECTS APG-E-PR-15-004 BUILDING 359, APG-E-PR-16-006 BUILDING 5016 AND APG-E-PR-16-007 BUILDING 5046.
Jan 17, 2017P00092$41.6KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE UXO SWEEPS FOR ROUTINE O&M TASKS AND PLANNED OUTAGES DURING NON-DUTY HOURS IN ACCORDANCE WITH SECTION C.9.1 ROUTINE WORK AND SECTION H.9 HAZARDOUS SUBSTANCES OF THE CONTRACT.
Jan 17, 2017P00093$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AD FOR ONE (1) MONTH OF FY17 UTILITY SERVICE CHARGE.
Dec 16, 2016P00091$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0005AC FOR ONE (1) MONTH OF FY17 UTILITY SERVICE CHARGE.
Dec 14, 2016P00090$84.8KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE CITY LIGHT AND POWER TO PERFORM THE SERVICE CONNECTION AS PROJECT APG-E-PR-17-001-BLDG 1150G.
Dec 12, 2016P00089$64.5KIGT::OT::IGF INCORPORATE SERVICE CONNECTION APG-E-PR-16-008, BLDG 384
Dec 7, 2016P00088$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSIONS FOR PROJECT APG-EPR-15-005 (COGEN) FROM 31 MAY 2017 TO 31 AUGUST 2017 AND APG-E-PR-15-006 (C4ISR) FROM APRIL 30, 2017 TO AUGUST 31, 2017.
Nov 17, 2016P00087$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO REVISE B.3 SCHEDULE TO ESTABLISH AND FUND YEAR 5 OF THE UTILITY SERVICE CHARGE. B.3 SCHEDULE IS HEREBY REVISED TO ESTABLISH SUB-CLIN 0005AB TO PROVIDE ONE (1)MONTH OF FY17 FUNDING FOR UTILITY SERVICE CHARGES.
Oct 13, 2016P00086$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO REVISE B.3 SCHEDULE TO ESTABLISH AND FUND YEAR 5 OF THE UTILITY SERVICE CHARGE. B.3 SCHEDULE IS HEREBY REVISED TO ESTABLISH SUBCLIN 0005AA TO PROVIDE ONE (1) MONTH OF FY17 FUNDING FOR UTILITY SERVICE CHARGES. SECTIONS B.3, AND G.6 ARE HEREBY REVISED AS A RESULT OF THESE CHANGES.
Oct 7, 2016P00085$0MODIFICATION WAS ISSUED TO CORRECT TYPOGRAPHICAL ERRORS MADE UNDER MODIFICATION P00079 FOR PROJECT APG-E-PR-16-005, UXO SWEEPS FOR ROUTINE O&M TASKS AND PLANNED OUTAGES DURING NON-DUTY HOURS. SPECIFICALLY, THE CONTRACT LINE ITEM NUMBERS AND SUBCLINS WERE INCORRECTLY TYPED AS 0094, 0094AA, AND 0094AB. THE CORRECT CLIN AND SUBCLIN NUMBERS SHOULD HAVE BEEN 0098, 0098AA AND 0098AB.
Sep 29, 2016P00082$193.5KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE CITY LIGHT&POWER (CLP) TO PERFORM THE SERVICE CONNECTION IDENTIFIED AS PROJECT # APG-E-PR-16-006 B5016 AT THE NEWLY ESTABLISHED CLIN 0099 IN ACCORDANCE WITH SECTION C.11.3, CONNECTIONS AND DISCONNECTIONS, OF THE CONTRACT.
Sep 29, 2016P00083$234.4KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE CITY LIGHT&POWER (CLP) TO PERFORM THE SERVICE CONNECTION IDENTIFIED AS PROJECT # APG-E-PR-16-007 B5046 IN ACCORDANCE WITH SECTION C.11.3, CONNECTIONS AND DISCONNECTIONS, OF THE CONTRACT.
Sep 29, 2016P00084$1.3MTHE PURPOSE OF THIS MODIFICATION IS TO REVISE THE B.3 SCHEDULE FOR CONTRACT LINE ITEM NUMBER (CLIN) 0093 WHICH WAS ESTABLISHED IN P00058 AND LAST REVISED IN P00071. ADDITIONALLY, THIS MODIFICATION REVISES THE CONTRACT ADMINISTRATION DATA IN SECTION G TO FULLY FUND THE C4ISR INTERTIE AUTOMATION PROJECT APG-E-PR-15-006.
Sep 28, 2016P00080$-440.9KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF $440,939.00 FROM CONTRACT LINE ITEM NUMBER (CLIN) 0060.
Sep 28, 2016P00081$0THE PURPOSE OF THIS MODIFICATION IS TO MAKE AN ADMINISTRATIVE CHANGE TO THE MIPR NUMBER ASSOCIATED WITH FUNDING OF THE PUBLIC HEALTH COMMAND PROJECT APG-E-PR-15-004, AS PROVIDED IN MODIFICATIONS P00065 AND P00077, FROM W81W3G53377027 TO W81W3G62649662. THE ACRN AND LINE OF ACCOUNTING REMAIN UNCHANGED.
Sep 23, 2016P00079$39.2KTHE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE MUTUAL AGREEMENT OF THE PARTIES REGARDING PROJECT APG-E-PR-16-005, UXO SWEEPS FOR ROUTINE O&M TASKS AND PLANNED OUTAGES DURING NON-DUTY HOURS IN ACCORDANCE WITH SECTION C.9.1 ROUTINE WORK AND SECTION H.9 HAZARDOUS SUBSTANCES OF THE CONTRACT.
Aug 29, 2016P00078$2.3MTHE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO PROVIDE FUNDS IN THE AMOUNT OF $2,332,456 TO FULLY FUND THE COGEN INTERTIE SWITCHGEAR PROJECT.
Aug 24, 2016P00076$10.8KTHIS MODIFICATION AUTHORIZES THE SYSTEM OWNER TO PERFORM NECESSARY TASKS ASSOCIATED WITH THE INSTALLATION OF BIRD FLAPPERS ALONG SECURE AREAS OF THE INSTALLATION.
Aug 24, 2016P00077$879.5KTHE PURPOSE OF THIS MODIFICATION IS TO FULLY FUND THE PUBLIC HEALTH COMMAND UNDER PROJECT APG-E-PR-15-004.
Jun 18, 2016P00075$1.6MPROVIDES THREE (3) MONTHS OF UTILITY SERVICE FUNDING FOR THE PERIOD JULY 01, 2016 - SEPTEMBER 30, 2016.
Jun 12, 2016P00074$0THIS ACQUISITION MODIFIES THE EXISTING CONTRACT TO UPGRADE THE EXISTING ELECTRICAL DISTRIBUTION SYSTEM AT ABERDEEN PROVING GROUND, MD FROM 2.4KV AND 4.16KV TO 35KV AND 15KV.
Jun 7, 2016P00073$34.8KTHE PURPOSE OF THIS MODIFICATION IS TO ISSUE A BILATERAL CHANGE ORDER IN ACCORDANCE WITH FAR 52.243-1(A)(1), CHANGES FIXED PRICE (ALTERNATE I), AUTHORIZING CITY LIGHT POWER (CLP) TO COMPLETE THE SERVICE CONNECTIONS IDENTIFIED BELOW IN ACCORDANCE WITH SECTION C.11.2, SDCS/UPGRADES/CONNECTIONS AND RENEWALS AND REPLACEMENTS, OF THE CONTRACT.
Apr 22, 2016P00072$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0004AF TO PROVIDE TWO (2) MONTH OF FY16 FUNDING FOR UTILITY SERVICE CHARGES. SECTIONS B.3, AND G.6 ARE HEREBY REVISED AS A RESULT OF THESE CHANGES.
Apr 20, 2016P00071$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE NO-COST PERIOD OF PERFORMANCE EXTENSIONS FOR PROJECTS APG-E-PR-15-005 (COGEN) AND APG-E-PR-15-006 (C4ISR). THE COGEN PROJECT WAS ESTABLISHED AS CLIN 0092 AND INCORPORATED INTO THE CONTRACT BY MODIFICATION P00057 DATED SEPTEMBER 25, 2015. THE C4ISR PROJECT WAS ESTABLISHED AS CLIN 0093 AND INCORPORATED INTO THE CONTRACT BY MODIFICATION P00058 DATED SEPTEMBER 28, 2015 AND LATER REVISED BY MODIFICATION P00059 DATED OCTOBER 10, 2015.
Apr 14, 2016P00070$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0004AE TO PROVIDE ONE (1) MONTH OF FY16 FUNDING FOR UTILITY SERVICE CHARGES.
Jan 29, 2016P00069$1.6MTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0004AD TO PROVIDE THREE (3) MONTHS OF FY16 FUNDING FOR UTILITY SERVICE CHARGES. SECTIONS B.3, AND G.6 ARE HEREBY REVISED AS A RESULT OF THESE CHANGES.
Jan 25, 2016P00068$40.5KTHE PURPOSE OF THIS MODIFICATION IS TO ISSUE A BILATERAL CHANGE ORDER IN ACCORDANCE WITH FAR 52.243-1(A)(1), CHANGES - FIXED PRICE (ALTERNATE I), AUTHORIZING CITY LIGHT&POWER (CLP) TO COMPLETE THE PLANNED OUTAGES AND UNEXPLODED ORDINANCE (UXO) SWEEPS IDENTIFIED IN APG-E-USR-15-007, PLANNED OUTAGES DURING NON-DUTY HOURS AND UXO SWEEPS FOR ROUTINE O&M TASKS, AS DESCRIBED IN CLP'S PROPOSAL SUBMITTED ON OCTOBER 28, 2015, AND IN ACCORDANCE WITH SECTION C.3.1, UTILITY SERVICE REQUIREMENT, OF THE CONTRACT.
Jan 22, 2016P00067$41.5KTHE PURPOSE OF THIS MODIFICATION IS TO ISSUE A BILATERAL CHANGE ORDER IN ACCORDANCE WITH FAR 52.243-1(A)(1), CHANGES - FIXED PRICE (ALTERNATE I), AUTHORIZING CITY LIGHT&POWER (CLP) TO COMPLETE THE SERVICE CONNECTIONS IDENTIFIED BELOW IN ACCORDANCE WITH SECTION C.11.2, SDCS/UPGRADES/CONNECTIONS AND RENEWALS AND REPLACEMENTS, OF THE CONTRACT.
Dec 31, 2015P00066$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH AND FUND SUBCLIN 0004AC TO PROVIDE ONE (1) MONTH OF FY16 FUNDING FOR UTILITY SERVICE CHARGES. SECTIONS B.3, AND G.6 ARE HEREBY REVISED AS A RESULT OF THESE CHANGES.
Dec 30, 2015P00065$3.9MTHE PURPOSE OF THIS MODIFICATION IS TO REVISE THE B.3 SCHEDULE FOR CONTRACT LINE ITEM NUMBER (CLIN) 0091, WHICH WAS ESTABLISHED IN P00056 AND LATER REVISED IN P00060. ADDITIONALLY, THIS MODIFICATION REVISES THE CONTRACT ADMINISTRATION DATA IN SECTION G TO ADD FUNDS TO CLIN 0091 AND TO INCORPORATE PAYMENT INSTRUCTIONS.
Dec 16, 2015P00064$0THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION AND REALIGN FUNDING FOR PROJECT APG-E-PR-15-002. THIS PROJECT WAS ESTABLISHED AS CLIN 0088 AND INCORPORATED INTO THE CONTRACT BY MODIFICATION P00050 DATED JUNE 1, 2015
Dec 9, 2015P00063$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO MAKE AN ADMINISTRATIVE CORRECTION TO SUBCLIN 0004AA IN THE B.3 SCHEDULE OF THE CONTRACT AS ESTABLISHED IN P00061. ADDITIONALLY, THIS MODIFICATION ALSO ESTABLISHES AND FUNDS SUBCLIN 0004AB TO PROVIDE ONE (1) MONTH OF FY16 FUNDING FOR UTILITY SERVICE CHARGE.
Oct 26, 2015P00062$0THE PURPOSE OF THIS MODIFICATION IS TO PERFORM THE FOLLOWING ADMINISTRATIVE CHANGES: 1) ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION AND REALIGN FUNDING FOR PROJECT APG-E-15-001. THIS PROJECT WAS ESTABLISHED AS CLIN 0084 AND INCORPORATED INTO THE CONTRACT BY MODIFICATION P00044 DATED APRIL 13, 2015. 2) ISSUE A NO-COST PERIOD OF PERFORMANCE EXTENSION AND REALIGN FUNDING FOR PROJECT APG-E-15-004. THIS PROJECT WAS ESTABLISHED AS CLIN 0085 AND INCORPORATED INTO THE CONTRACT BY MODIFICATION P00047 DATED APRIL 28, 2015.
Oct 23, 2015P00061$521.9KTHE PURPOSE OF THIS MODIFICATION IS TO REVISE B.3 SCHEDULE TO ESTABLISH CLIN 0004 TO FUND YEAR 4 OF THE UTILITY SERVICE CHARGE. B.3 SCHEDULE IS HEREBY REVISED TO ESTABLISH SUBCLIN 0004AA TO PROVIDE ONE (1) MONTH OF FY16 FUNDING FOR UTILITY SERVICE CHARGE.
Oct 22, 2015P00060$0THE PURPOSE OF THIS MODIFICATION IS TO REVISE THE B.3 SCHEDULE FOR CONTRACT LINE ITEM NUMBER (CLIN) 0091, WHICH WAS ESTABLISHED IN P00056. THIS MODIFICATION INCORPORATES THE NEGOTIATED PRICES IN THE INFORMATIONAL SUBLINE ITEMS (INFOSLINS).
Oct 7, 2015P00059$0THE PURPOSE OF THIS MODIFICATION IS TO PERFORM THE FOLLOWING ACTIONS: 1) MAKE AN ADMINISTRATIVE CORRECTION TO THE FUNDING BREAKDOWN AMOUNTS FOR ACRN BM AS STATED IN MODIFICATION P00058 UNDER G.6 ACCOUNTING AND APPROPRIATION DATA 2) REVISE THE STATED OBLIGATED AMOUNTS IN PARAGRAPH E.
Sep 28, 2015P00058$347.0KPROJECT NO. APG-E-PR-15-006, CITY LIGHT AND POWER, INC. (CLP) IS HEREBY AUTHORIZED TO INSTALL INTERTIE AUTOMATION TO ACCOMMODATE THE 35KV UNDERGROUND INTERTIE CIRCUIT BETWEEN C4ISR MAIN SWITCHGEAR AND THE 35KV NORTH AND SOUTH FEEDERS AT ABERDEEN PROVING GROUND (APG).
Sep 25, 2015P00056$159.7KTHE PURPOSE OF THIS MODIFICATION IS TO ISSUE A BILATERAL CHANGE ORDER IN ACCORDANCE WITH FAR 52.243-1(A)(1), CHANGES - FIXED PRICE (ALTERNATE I), AUTHORIZING CITY LIGHT ANDPOWER (CLP) TO COMPLETE THE SERVICE CONNECTIONS IDENTIFIED BELOW IN ACCORDANCE WITH SECTION C.11.2, SDCS/UPGRADES/CONNECTIONS AND RENEWALS AND REPLACEMENTS, OF THE CONTRACT.

Estimated positioning window

Aug 31, 2061 – Feb 28, 2062

Recompete signal:
50/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 50/100. Available recorded signals: 45 points.

Contract end 2062-08-31 (13094 days from calculation)
+5 points
20 historical awards in this buyer and category group
+15 points
257 recorded award transactions
+10 points
Latest award action: 2026-06-02
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.