Federal contract award

SP060021C8348

NATURAL GAS DISTRIBUTION SYSTEM SERVICES AT FORT LEONARD WOOD, MISSOURI

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeDLA ENERGY
NAICS221210 — Natural Gas Distribution
PSCS111 — Gas Services
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIXED PRICE WITH ECONOMIC PRICE ADJUSTMENT
Obligations$46.5M
Current contract value$89.4M
Potential contract value / ceiling$89.4M
Start dateFeb 1, 2016
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activityMay 11, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 90 of 90 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 11, 2026P00089$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND CONTRACT YEAR 10, DEOBLIGATES FUNDS FROM THE NATURAL GAS SUPPLY FOR MARCH, AND DEOBLIGATES THE PROPANE SUPPLY.
Apr 27, 2026P00088$1.4MTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND CONTRACT YEAR 10.
Mar 18, 2026P00087$1.3MTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND CONTRACT YEAR 10 AND RECONCILE THE NATURAL GAS SUPPLY FOR A MONTH AND ADD FUNDS FOR PROPANE.
Feb 26, 2026P00086$1.0MTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND CONTRACT YEAR 10 AND RECONCILE THE NATURAL GAS SUPPLY FOR A FEW MONTHS.
Jan 29, 2026P00085$40.0KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE PROPANE SUPPLY FOR CONTRACT YEAR 10.
Jan 27, 2026P00084$-184.2KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2026 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Dec 30, 2025P00083$0THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION TO EXTEND SERVICES.
Dec 19, 2025P00082$1.9MTHE PURPOSE OF THIS MODIFICATION IS TO FUND THE REMAINING USC FOR CONTRACT YEAR 10.
Nov 24, 2025P00081$1.6MTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE USC FOR CONTRACT YEAR 10.
Sep 30, 2025P00080$657.5KTHE PURPOSE OF THIS MODIFICATION IS TO FUND CLIN 0015.
Sep 19, 2025P00079$-31.7KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2025 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Sep 15, 2025P00078$-63.7KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2025 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Aug 20, 2025P00077$648.1KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE USC FOR CONTRACT YEAR 10.
Aug 14, 2025P00076$626.4KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE USC FOR CONTRACT YEAR 10
Aug 6, 2025P00075$34.1KTHE PURPOSE OF THIS MODIFICATION IS TO FUND CLIN0014.
Jul 24, 2025P00074$-112.9KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2025 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Jul 10, 2025P00073$649.0KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE USC FOR CONTRACT YEAR 10.
Jun 18, 2025P00072$662.0KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE USC FOR CONTRACT YEAR 10.
Jun 10, 2025P00071$0THE PURPOSE OF THIS MODIFICATION IS TO REMOVE AND UPDATE FAR CLAUSES.
May 22, 2025P00069$-98.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2025 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
May 22, 2025P00070$677.4KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE UTILITY SERVICE CHARGE FOR CONTRACT YEAR 10.
May 1, 2025P00068$696.5KTHE PURPOSE OF THIS MODIFICATION IS TO FUND THE UTILITY SERVICE CHARGE FOR CONTRACT YEAR 10.
Apr 29, 2025P00067$0THE PURPOSE OF THIS MODIFICATION IS TO APPLY AN ECONOMIC PRICE ADJUSTMENT TO THE CURRENT UTILITY SERVICE CHARGE.
Apr 2, 2025P00066$0THIS MODIFICATION INCORPORATES THE MOST RECENT PUBLICATIONS FOR SCA AND DBA AS OF THE BEGINNING OF CY10, PERIOD OF PERFORMANCE FROM APRIL 1, 2025, THROUGH JANUARY 31, 2026.
Mar 26, 2025P00065$857.8KTHE PURPOSE OF THIS MODIFICATION IS TO FUND THE REMAINING UTILITY SERVICE CHARGE FOR CONTRACT YEAR 9.
Mar 20, 2025P00064$-131.0KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2025 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Feb 26, 2025P00063$85.0KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND PROPANE SUPPLY FOR CONTRACT YEAR 9.
Feb 6, 2025P00062$950.4KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2025.
Jan 22, 2025P00061$1.9MTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2025.
Nov 22, 2024P00060$-116.2KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2025 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Nov 6, 2024P00059$-61.4KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Nov 1, 2024P00058$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE DFARS CLAUSE 252.232-7006.
Oct 25, 2024P00057$0THE PURPOSE OF THIS MODIFICATION IS TO CORRECT A CLERICAL ERROR IN A PREVIOUS MOD.
Oct 24, 2024P00056$879.5KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2025.
Oct 23, 2024P00054$726.3KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY FUND THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2025.
Oct 23, 2024P00055$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE DFARS 252.204-7012 AND 252.204-7020.
Sep 25, 2024P00053$67.2KTHE PURPOSE OF THIS MODIFICATION IS TO FUND CLIN 0013.
Sep 17, 2024P00052$-92.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Sep 10, 2024P00051$-77.2KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Aug 26, 2024P00050$535.8KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISAL YEAR FUNDS UNDER THE CONTINUED CONTRACT AND TO COVER THE REMAINING UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
Jul 18, 2024P00049$504.5KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISAL YEAR FUNDS UNDER THE CONTINUED CONTRACT AND TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024 AND UPDATE DFARS CLAUSE.
Jun 20, 2024P00048$238.7KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISAL YEAR FUNDS UNDER THE CONTINUED CONTRACT AND TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
May 23, 2024P00047$655.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
May 7, 2024P00046$667.1KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
Apr 29, 2024P00045$749.5KTHE PURPOSE OF THIS MODIFICATION IS TO APPLY AN ECONOMIC PRICE ADJUSTMENT TO THE CURRENT UTILITY SERVICE CHARGE, PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AND UPDATE THE WAGE DETERMINATION FOR CONTRACT YEAR 9.
Apr 3, 2024P00044$323.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT AND TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
Feb 13, 2024P00043$2.0MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
Jan 25, 2024P00042$125.0KTHE PURPOSE OF THIS MODIFICATION IS TO PARTIALLY COVER THE PROPANE SUPPLY FOR FY2024.
Dec 21, 2023P00041$651.4KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2024 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT AND PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
Dec 20, 2023P00040$-34.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE 2023 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Nov 29, 2023P00039$872.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024.
Oct 11, 2023P00038$692.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2024 AND CORRECT A CLERICAL ERROR IN P00037.
Sep 29, 2023P00037$934.1KTHE PURPOSE OF THIS MODIFICATION IS TO FUND CLINS 0011 AND 0012.
Sep 21, 2023P00036$-31.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATES 2023 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Aug 18, 2023P00035$-431.0KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATES 2023 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Aug 4, 2023P00034$1.2MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2023 AND INCORPORATES FAR CLAUSE 52.204-27 PROHIBITION ON A BYTEDANCE COVERED APPLICATION (JUNE 2023) INTO THE CONTRACT.
Jul 19, 2023P00033$1.2MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2023 AND INCORPORATES THE REQUIREMENT FOR THE SYSTEM OWNER TO SUBMIT AN ANNUAL ASSESSMENT OF THE SYSTEM.
Apr 28, 2023P00032$-460.2KTHIS MODIFICATION DEOBLIGATES 2023 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Apr 13, 2023P00031$700.2KTHIS PROVIDES FUNDING FOR THE UTILITY SERVICE CHARGE FOR 2023 FISCAL YEAR.
Apr 3, 2023P00030$0THE PURPOSE OF THIS MODIFICATION IS TO CORRECT A CLERICAL ERROR ON MODIFICATION P00029.
Mar 27, 2023P00029$801.1KTHE PURPOSE OF THIS MODIFICATION IS TO APPLY AN ECONOMIC PRICE ADJUSTMENT TO THE CURRENT MONTHLY UTILITY SERVICE CHARGE AND PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, INCORPORATE THE MSPR REQUIREMENT, AND UPDATE THE WAGE DETERMINATION.
Mar 10, 2023P00028$-300.0KTHIS MODIFICATION DEOBLIGATES 2023 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Feb 16, 2023P00027$1.0MTHIS PROVIDES FUNDING FOR THE UTILITY SERVICE CHARGE FOR 2023 FISCAL YEAR.
Feb 1, 2023P00026$25.0KTHIS PROVIDES FUNDING TO PARTIALLY COVER THE PROPANE SUPPLY FOR FY2023.
Jan 25, 2023P00025$2.7MTHIS PROVIDES FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE 2023 FISCAL YEAR.
Jan 10, 2023P00024$601.7KTHIS PROVIDES FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE 2023 FISCAL YEAR.
Oct 21, 2022P00023$1.2MTHIS PROVIDES FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE 2023 FISCAL YEAR.
Oct 17, 2022P00022$849.5KTHIS MODIFICATION DEOBLIGATES 2022 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT AND PROVIDES FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE 2023 FISCAL YEAR.
Sep 14, 2022P00021$-80.0KTHIS MODIFICATION DEOBLIGATES 2022 FISCAL YEAR FUNDS UNDER THE CONTINUED CONTRACT.
Sep 6, 2022P00020$614.9KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022.
Aug 15, 2022P00019$-354.4KTHIS MODIFICATION DEOBLIGATES 2022 FISCAL YEAR FUNDS UNDER THE CONTINUED AND ADDRESSES THE DEOBLIGATED FUNDS ON THE PREDECESSOR CONTRACT.
Jul 26, 2022P00018$871.3KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022
Jun 28, 2022P00017$796.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022
May 27, 2022P00016$748.3KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022
May 2, 2022P00015$0THIS MODIFICATION UPDATES THE NATURAL GAS PIPELINE RESERVATION CHARGE TO FORT LEONARD WOOD.
Apr 21, 2022P00014$709.9KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022.
Apr 15, 2022P00013$730.0KTHE PURPOSE OF THIS MODIFICATION IS TO APPLY AN ECONOMIC PRICE ADJUSTMENT TO THE CURRENT MONTHLY UTILITY SERVICE CHARGE (MUSC) AND PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022.
Mar 9, 2022P00012$1.1MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022. THIS MODIFICATION ALSO ADDS FAR CLAUSE 52.249-2 AND UPDATES DFARS 252.232-7006.
Feb 23, 2022P00011$-762.9KTHIS MODIFICATION DEOBLIGATES 2022 FISCAL YEARS FUNDS.
Feb 2, 2022P00010$0THIS MODIFICATION REDUCES THE NATURAL GAS PIPELINE RESERVATION CHARGE TO FORT LEONARD WOOD.
Jan 20, 2022P00009$0THIS MODIFICATION UPDATES CLAUSE 252.204-7012, ADD CLAUSE 252.204-7020, ADD 52.204-21, AND UPDATED REGISTER OF WAGE DETERMINATION UNDER THE SERVICE CONTRACT ACT AND GENERAL DECISION FOR CONSTRUCTION WAGE RATES UNDER THE DAVIS-BACON ACT.
Jan 12, 2022P00008$0THE PURPOSE OF THIS MODIFICATION IS TO CORRECT A CLERICAL ERROR ON MODIFICATION P00007, SUBCLIN CORRECTION.
Jan 11, 2022P00007$1.3MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022.
Dec 17, 2021P00006$2.8MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR THE FISCAL YEAR 2022.
Nov 16, 2021P00005$0EO14042:THIS MODIFICATION INCORPORATES DFARS CLAUSE 252.223-799, ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (DEVIATION 2021-O0009) (OCT 2021) INTO THE CONTRACT IN ACCORDANCE WITH EXECUTIVE ORDER 14042.
Nov 1, 2021P00004$1.2MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE NATURAL AND PROPANE GAS, AS WELL AS THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2022.
Oct 25, 2021P00003$-50.8KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDS TO COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2021.
Oct 8, 2021P00002$766.5KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2022.
Sep 9, 2021P00001$665.6KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING TO PARTIALLY COVER THE UTILITY SERVICE CHARGE FOR FISCAL YEAR 2021.
Sep 3, 20210$0NATURAL GAS DISTRIBUTION SYSTEM SERVICES AT FORT LEONARD WOOD, MISSOURI