Federal contract award

VA26117C0197

IGF::OT::IGF PROVIDE EMERGENCY POWER UPGRADE FOR BUILDINGS 100 AND 101 AT VA PALO ALTO MEDICAL CAMPUS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Veterans Affairs
Office261-NETWORK CONTRACT OFFICE 21 (36C261)
NAICS237130 — Power and Communication Line and Related Structures Construction
PSCY1NZ — CONSTRUCTION OF OTHER UTILITIES
Parent award / vehicleNot reported
Set-asideSERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Pricing typeFIRM FIXED PRICE
Obligations$12.2M
Current contract value$12.2M
Potential contract value / ceiling$12.2M
Start dateSep 18, 2017
Current end dateSep 10, 2026
Potential end dateSep 10, 2026
Latest award activityAug 6, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 18 of 18 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Aug 6, 2026P00017$0EMERGENCY POWER UPGRADE PERIOD OF PERFORMANCE TIME EXTENSION.
Mar 10, 2026P00016$2.6KEMERGENCY POWER UPGRADE PERIOD OF PERFORMANCE TIME EXTENSION.
Feb 9, 2026P00015$0EMERGENCY POWER UPGRADE PERIOD OF PERFORMANCE TIME EXTENSION.
Nov 5, 2025P00014$0EMERGENCY POWER UPGRADE PERIOD OF PERFORMANCE TIME EXTENSION.
Sep 30, 2025P00013$700.0KEMERGENCY POWER UPGRADE SUSPENSION COSTS
Aug 5, 2025P00012$363.5KMECHANICAL AND STRUCTURAL ENGINEERING, REHIRE STRUCTURAL SUB-CONTRACTOR
Jun 27, 2025P00011$85.6KWORK WITHIN SCOPE COMMUNICATION PATHWAY RFI 135,120 DAY POP EXTENSION
Sep 20, 2024P00010$23.0K120 DAY POP EXTENSION
Mar 20, 2024P00009$0120 DAY POP EXTENSION
Nov 29, 2023P00008$60.8KADD IN-SCOPE WORK TO INCLUDE BUILDING SIGNAGE, AIR PERMIT, ATS TROUGH, ANNUNICATOR AND RE-ROUTE DRAINAGE PIPE.
Jun 9, 2023P00007$250.0KDESCOPE ELECTRICAL POWER SUPPLY SYSTEM FROM BUILDING 104
Oct 12, 2022P00006$0REPLACE EXPIRED FY2017 FUNDING ONLY WITH FY2023 FUNDING
Feb 8, 2021P00005$500MODIFICATION P00005 FOR SWPPP REPORTING REQUIREMENTS
Sep 16, 2020P00004$53.4KMODIFICATION TO PROVIDE FOR 17" ANNUNCIATOR DUE TO INACCURATE SPECIFICATIONS.
Jun 1, 2020P00003$30.1KPROVIDE FOR CHANGES TO PROJECT DUE TO RFI RESPONSES TO INCLUDE ELECTRICAL AND FIBER OPTIC WORK.
Sep 24, 2019P00002$36.0KPROVIDE FOR CHANGES TO PROJECT DUE TO RFI RESPONSES TO INCLUDE BOLLARDS, AND SLOPING OF ELECTRICAL TROUGHS AND ADD FUEL PIPING STRUCTURAL SUPPORTS.
Feb 27, 2019P00001$50.0KIGF::OT::IGF PROVIDE FOR CHANGES TO PROJECT DUE TO RFI RESPONSES TO INCLUDE BOLLARDS, AND SLOPING OF ELECTRICAL TROUGHS AND ADD FUEL PIPING STRUCTURAL SUPPORTS.
Sep 25, 20170$10.6MIGF::OT::IGF PROVIDE EMERGENCY POWER UPGRADE FOR BUILDINGS 100 AND 101 AT VA PALO ALTO MEDICAL CAMPUS.