Federal contract award
W15QKN19C0017
EXCALIBUR IB PRODUCTION BASE AWARD
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QK ACC-RI-PICATINNY |
| NAICS | 332993 — Ammunition (except Small Arms) Manufacturing |
| PSC | 1320 — Ammunition, over 125 mm |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.0B |
| Current contract value | $1.0B |
| Potential contract value / ceiling | $1.0B |
| Start date | Apr 30, 2019 |
| Current end date | Jan 31, 2028 |
| Potential end date | Jan 31, 2028 |
| Latest award activity | Jun 5, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 85 of 85 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 5, 2026 | P00039 | $0 | EXCALIBUR: CONSIDERATION WITH REBASELINE, DD254, SCG, CMOP, ADMIN |
| Mar 23, 2026 | P00037 | $0 | DELIVERY SCHEDULE RE-BASELINE |
| Jun 17, 2025 | P00036 | $0 | EXCALIBUR CSDR, AAE, POP TESTING UPDATES |
| May 14, 2025 | P00035 | $0 | EXCALIBUR ECP, WAWF, E.O'S, GFP |
| Feb 12, 2025 | P00034 | $0 | UPDATE TO DFAS PAYMENT OFFICE |
| Jan 16, 2025 | P00033 | $0 | EXCALIBUR PRODUCTION - ADMIN MOD - TO INCLUDE FULL COUNTRY CASE CODE, UPDATE DCMA CAO, GFP, DELIVERY SCHED, ACWS NARRATIVE |
| Jan 31, 2024 | P00032 | $0 | ADD UPDATED DD254 TO CONTRACT. |
| Dec 8, 2023 | P00031 | $2.4M | TO PROCURE SELECTIVE AVAILABILITY ANTI-SPOOFING MODULE (SAASM) COMPONENTS. |
| Sep 11, 2023 | P00029 | $0 | ADMINISTRATIVE CHANGES. |
| Aug 30, 2023 | P00030 | $276.5M | UKRAINE EXERCISE OPTION IV TO PROCURE 155MM EXCALIBUR INCREMENT IB PROJECTILES. |
| Jul 12, 2023 | A00045 | $0 | A00045 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF JUNE 2023. |
| Jun 9, 2023 | P00028 | $115.9K | TO ADD COUNTRY SPECIFIC ADDERS, NSP DESICCANT BAGS, UPDATE PBP SCHEDULES AND NO COST ECPS TO CONTRACT. |
| Jun 7, 2023 | A00044 | $0 | A00044 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF MAY 2023. |
| Apr 5, 2023 | A00043 | $0 | A00043 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF MARCH 2023. |
| Apr 3, 2023 | P00026 | $0 | ADMINISTRATIVE MODIFICATION AT NO COST OR SCHEDULE IMPACT TO THE CONTRACT. |
| Mar 3, 2023 | A00042 | $0 | A00042 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF FEBRUARY 2023. |
| Feb 28, 2023 | P00027 | $207.5M | EXERCISE OPTION III US ARMY FOR A TOTAL OF 3,086 EXCALIBUR 155MM INCREMENT IB PROJECTILES. |
| Feb 28, 2023 | P00027 | $4.1M | PROCUREMENT OF 56 155MM INCREMENT IB PROJECTILES FOR FMS JORDAN. |
| Feb 8, 2023 | A00041 | $0 | A00041 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF JANUARY 2023. |
| Jan 11, 2023 | A00040 | $0 | A00040 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF DECEMBER 2022. |
| Dec 8, 2022 | A00039 | $0 | A00039 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF NOVEMBER 2022. |
| Nov 29, 2022 | A00038 | $0 | A00027 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF OCTOBER 2022. |
| Nov 29, 2022 | P00025 | $84.1M | TO EXERCISE OPTION III UNDER CONTRACT W15QKN-19-C-0017, FOR THE PROCUREMENT OF ONE THOUSAND THIRTY-SIX (1,036) 155MM EXCALIBUR INCREMENT IB PROJECTILES. |
| Oct 11, 2022 | A00037 | $0 | A00037 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF SEPTEMBER 2022. |
| Sep 14, 2022 | A00036 | $0 | A00036 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF AUGUST 2022. |
| Sep 13, 2022 | P00024 | $0 | THE PURPOSE OF THIS MOD IS FOR ADMINISTRATIVE UPDATES, GFP TRANSFERS AND INCORPORATE AN RFV AND ECP AT NO COST. |
| Aug 8, 2022 | A00035 | $0 | A00035 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF JULY 2022. |
| Jul 12, 2022 | A00034 | $0 | A00034 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF JUNE 2022. |
| Jun 9, 2022 | A00033 | $0 | A00033 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF MAY 2022. |
| Jun 6, 2022 | P00023 | $0 | TO UPDATE THE DD254 AND CHANGE CLIN 0022 ACRN FROM BK TO BU IN SECTION H. |
| May 10, 2022 | A00032 | $0 | A00032 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF APRIL 2022. |
| Apr 11, 2022 | A00031 | $0 | A00031 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF MARCH 2022. |
| Mar 23, 2022 | A00030 | $0 | A00030 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTHS OF JAN & FEB 2022. |
| Mar 23, 2022 | P00022 | $0 | EXTEND THE DELIVERY SCHEDULES FOR LOT 5 PROJECTILES UNDER CLINS 0001AE, 0001AG, AND 0002AC (TOTAL QUANTITY 354) ARE REVISED FROM 31 JANUARY 2022 TO 30 APRIL 2022. |
| Feb 10, 2022 | P00021 | $0 | EXTEND THE PERIOD OF PERFORMANCE (POP) FOR LOT 7 PRODUCTION CLINS 0001AE, 0001AH, AND 0002AC UNDER THE REFERENCE CONTRACT FROM 28 FEBRUARY 2022 TO 30 APRIL 2022. |
| Jan 27, 2022 | P00020 | $66.2M | ACQUISITION OF THE 622 EXCALIBUR IB PROJECTILES. |
| Jan 19, 2022 | P00017 | $918.6K | CAS CCA PWA OBSOLESCENCE REDESIGN AND QUALIFICATION, P00017 |
| Dec 14, 2021 | A00027 | $0 | A00027 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF NOVEMBER 2021. |
| Dec 13, 2021 | P00019 | $0 | REVISE THE DELIVERY SCHEDULE FOR SPAIN. |
| Nov 30, 2021 | P00018 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO PROCURE 19 155MM EXCALIBUR IB PROJECTILES. |
| Nov 30, 2021 | P00018 | $1.6M | THE PURPOSE OF THIS MODIFICATION IS TO PROCURE 19 EXCALIBUR IB ROUNDS FOR FMS SPAIN. |
| Nov 15, 2021 | P00016 | $0 | TRANSFER GFP FROM THE 08 EXCALIBUR PRODUCTION CONTRACT TO THE 19 PRODUCTION CONTRACT. |
| Nov 9, 2021 | A00026 | $0 | A00026 ISSUED FOR CONTRACTUAL TRACKING OF APPROVED NO-COST CLASS I OR MAJOR SUPPLIER REQUESTS, CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS PROVIDED BY THE EXCALIBUR PROGRAM OFFICE REPRESENTATIVE AND REVIEWED BY THE DCMA ENGINEER FOR CONTRACT W15QKN-19-C-0017 FOR THE MONTH OF OCTOBER 2021. |
| Oct 25, 2021 | A00025 | $0 | REVISE THE DELIVERY SCHEDULE OF LOT 4 IMPACTING 1B PROJECTILE DELIVERY SCHEDULE OF SLINS 0001AE, 0001AF, 0001AG, AND 0002AC TO 01 31 2022 AND UPDATE ATTACHMENT 17 PRODUCTION DELIVERY SCHEDULE TO 10 18 21 ALONG WITH SECTION J. |
| Oct 6, 2021 | A00024 | $0 | APPROVED ERB, SRS, CCB,CNS, VS, RDWS AND ECPS FOR THE MONTHS OF AUG 01-31 AND 01-31 SEP. |
| Aug 24, 2021 | P00015 | $0 | TO EXTEND THE PERIOD OF PERFORMANCE FOR LOT 5 DELIVERABLES. |
| Aug 5, 2021 | A00023 | $0 | APPROVED ERB, SRS, CCB,CNS, VS, AND RDWS FOR THE MONTH OF JULY 01 - 30 202. THERE WERE NO ECPS DURING THIS TIMEFRAME. |
| Jul 19, 2021 | A00022 | $0 | APPROVED ERB, SRS, CCB, CNS, VS, RDW, AND ECP FOR THE MONTH OF JUNE 01 - 30 2021 |
| Jul 13, 2021 | P00014 | $0 | ADMINISTRATIVE IN NATURE. OPERATIONAL FLIGHT SOFTWARE (OFS) BLOCK CHAIN PRODUCTION CUT-IN PWS UPDATE. DRAWING AND ATTACHMENT UPDATES. |
| Jun 15, 2021 | P00011 | $9.1M | THE PURPOSE OF THIS MODIFICATION IS TO PROCURE 102 EXCALIBUR IB PROJECTILES. |
| Jun 15, 2021 | P00012 | $20.3M | THE PURPOSE OF THIS MODIFICATION IS TO PROCURE 205 EXCALIBUR PROJECTILES. |
| Jun 15, 2021 | P00013 | $0 | EXERCISE OPTION II TO PROCURE 111 EXCALIBUR 155MM INCREMENT IB PROJECTILES. |
| Jun 15, 2021 | P00013 | $9.2M | ARMY BUYBACK FOR 111 PROJECTILES AND COUNTRY SPECIFIC ADDERS FOR INDIA. |
| Jun 9, 2021 | A00021 | $0 | APPROVED ERB, SRS, CCB, CNS, VS, RDW, AND ECP FOR THE MONTH OF MAY 01 - 30 2021 |
| May 11, 2021 | A00020 | $0 | APPROVED ERB, SRS, CCB, CNS, VS, RDW, AND ECP FOR THE MONTH OF APRIL 01 - 30 2021 |
| Apr 19, 2021 | A00019 | $0 | GFP TRANSFER ACCEPTANCE OF THIS MODIFICATION IS FOR 21 SERIALLY MANAGED PROJECTILE PAINT CARTS FROM W15QKN 18 D 0002-0002 (MODIFICATION 1L, CLIN 0009) PTR202010954. |
| Apr 5, 2021 | A00018 | $0 | TRACKING OF APPROVED NO-COST CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS DURING MARCH 2021. NO COST ECPS DURING 03 2021 |
| Mar 22, 2021 | A00017 | $0 | TRACKING OF APPROVED NO-COST CLASS I ENGINEERING CHANGE NOTICES, MAJOR VARIANCES, AND CLASS I ENGINEERING CHANGE PROPOSALS DURING FEBRUARY 2021. NO ECPS DURING 02 2021 |
| Mar 11, 2021 | P00010 | $0 | THE PURPOSE OF MODIFICATION P00010 IS TO REMOVE THE REQUIREMENT TO ADD EXCHANGE RATE ADJUSTMENTS FOR QUANTITIES UNDER MODIFICATIONS P00005, P00007, P00008 AND P00009 AND REMOVE THE EXCHANGE RATE CLAUSE (SECTION H.4) FROM OPTION I FORWARD. ADD LANGUAGE TO SECTION A OF THE CONTRACT THAT INCLUDES A CREDIT FOR SIX (6) MONTHS OF PRODUCTION GAP COSTS FOR THE GOVERNMENT. INCORPORATE ENGINEERING CHANGE PROPOSAL (ECP) 030430 INTO CONTRACT AS A SECTION J ATTACHMENT. REVISE LANGUAGE IN FAR 52.217-7 AND UPDATE CONTRACT CDRLS (B001-B023) TO INCLUDE THE CONTRACTING OFFICERS AND SPECIALIST IN THE DISTRIBUTION LISTS. |
| Feb 10, 2021 | P00009 | $53.9M | THE PURPOSE OF THIS MODIFICATION IS TO PROCURE 655 EXCALIBUR IB PROJECTILES. |
| Feb 8, 2021 | A00016 | $0 | TRACKING OF APPROVED NO-COST CLASS 1 OR MAJOR SUPPLIER REQUEST, CLASS 1 ECP NOTICES, MAJOR VARIANCES AND CLASS1 ECP DURING THE MONTH OF JANUARY 2021 |
| Jan 11, 2021 | A00015 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Nov 30, 2020 | P00008 | $31.1M | THE PURPOSE OF THIS MODIFICATION IS TO PROCURE 395 EXCALIBUR IB PROJECTILES. |
| Nov 16, 2020 | A00014 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Oct 22, 2020 | A00013 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Sep 23, 2020 | A00012 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Sep 23, 2020 | P00007 | $9.8M | TO PROCURE 124 155MM EXCALIBUR IB PROJECTILES IN SUPPORT OF THE USMC. |
| Aug 28, 2020 | A00011 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Aug 18, 2020 | A00010 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Aug 4, 2020 | A00009 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Jun 24, 2020 | A00008 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Jun 9, 2020 | P00006 | $902.5K | OPERATIONAL FLIGHT SOFTWARE (OFS) BLOCK CHANGE PRODUCTION CUT-IN |
| May 4, 2020 | P00004 | $1.3M | TM CCA REDESIGN AND QUALIFICATION |
| Apr 16, 2020 | A00006 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Mar 26, 2020 | P00005 | $85.7M | TO PROCURE EXCALIBUR IB PROJECTILES FOR US ARMY. |
| Mar 25, 2020 | P00003 | $0 | ADMINISTRATIVE MODIFICATION |
| Mar 10, 2020 | A00005 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Jan 16, 2020 | A00004 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Nov 25, 2019 | A00003 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Oct 21, 2019 | A00002 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Sep 26, 2019 | P00002 | $-3.3M | EXCHANGE RATE ADJUSTMENT, PBP UPDATE, AND IMU GYROSCOPIC SENSOR QUALIFICATION |
| Sep 12, 2019 | P00001 | $7.5M | US ARMY (FMS BUYBACK) |
| Sep 10, 2019 | A00001 | $0 | EXCALIBUR IB PRODUCTION BASE AWARD |
| Apr 30, 2019 | 0 | $200.2M | EXCALIBUR IB PRODUCTION BASE AWARD |
| Apr 30, 2019 | 0 | $0 | FMS CAR |
Estimated positioning window
Jan 31, 2027 – Jul 31, 2027
70/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 70/100. Available recorded signals: 65 points.
- Contract end 2028-01-31 (456 days from calculation)
- +25 points
- 76 historical awards in this buyer and category group
- +15 points
- 85 recorded award transactions
- +10 points
- Latest award action: 2026-06-05
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.