Federal contract award
W15QKN25F0006
THE PURPOSE OF DO W15QKN25F0006 IS TO FUND THE CAPACITY INCREASE OF THE MODULAR ARTILLERY CHARGE SYSTEM LOAD, ASSEMBLE, AND PACK M231/M232 TYPE FOR THE 155MM PROPELLING CHARGES FROM 25K-50K UNITS PER MONTH, INCREASING UP TO 80,000 UNITS PER MONTH.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QK ACC-RI-PICATINNY |
| NAICS | 332993 — Ammunition (except Small Arms) Manufacturing |
| PSC | 1320 — Ammunition, over 125 mm |
| Parent award / vehicle | W15QKN19D0109 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.2M |
| Current contract value | $2.2M |
| Potential contract value / ceiling | $2.2M |
| Start date | Dec 31, 2024 |
| Current end date | Sep 26, 2025 |
| Potential end date | Sep 26, 2025 |
| Latest award activity | Sep 4, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 4, 2025 | P00001 | $0 | MODIFICATION P00001 TO DELIVERY ORDER W15QKN25F0006 UNDER CONTRACT W15QKN-19-D-0109 IS TO REVISE THE SCHEDULE DATE FOR THE CAPACITY I IN PRODUCTION TO 80K PER MONTH FOR MACS LAP. |
| Sep 4, 2025 | P00001 | $0 | MODIFICATION P00001 TO DELIVERY ORDER W15QKN25F0006 UNDER CONTRACT W15QKN-19-D-0109 IS TO REVISE THE SCHEDULE DATE FOR THE CAPACITY I IN PRODUCTION TO 80K PER MONTH FOR MACS LAP. |
| Dec 31, 2024 | 0 | $2.2M | THE PURPOSE OF DO W15QKN25F0006 IS TO FUND THE CAPACITY INCREASE OF THE MODULAR ARTILLERY CHARGE SYSTEM LOAD, ASSEMBLE, AND PACK M231/M232 TYPE FOR THE 155MM PROPELLING CHARGES FROM 25K-50K UNITS PER MONTH, INCREASING UP TO 80,000 UNITS PER MONTH. |
| Dec 31, 2024 | 0 | $2.2M | THE PURPOSE OF DO W15QKN25F0006 IS TO FUND THE CAPACITY INCREASE OF THE MODULAR ARTILLERY CHARGE SYSTEM LOAD, ASSEMBLE, AND PACK M231/M232 TYPE FOR THE 155MM PROPELLING CHARGES FROM 25K-50K UNITS PER MONTH, INCREASING UP TO 80,000 UNITS PER MONTH. |