Federal contract award

W56HZV19C0073

DRY SUPPORT BRIDGE LOAD REDESIGN HARDWARE DUE TO THE INCREASE IN LENGTH OF THE DSB FROM 40 METERS TO 46 METERS. SERVICES INCLUDED TO ASSIST IN US GOVERNMENT TESTING AND IN SUPPORT OF HARDWARE INSTALLATION.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeDCMA EUROPE
NAICS332312 — Fabricated Structural Metal Manufacturing
PSC5420 — Bridges, Fixed and Floating
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$153.3K
Current contract value$153.3K
Potential contract value / ceiling$2.1M
Start dateMay 22, 2019
Current end dateSep 19, 2019
Potential end dateApr 14, 2023
Latest award activityMay 22, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 1 of 1 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 22, 2025ARZ999$0THIS CONTRACT IS FOR DRY SUPPORT BRIDGE LOAD REDESIGN HARDWARE DUE TO THE INCREASE IN LENGTH OF THE DSB FROM 40 METERS TO 46 METERS. SERVICES INCLUDED TO ASSIST IN US GOVERNMENT TESTING AND IN SUPPORT OF HARDWARE INSTALLATION. THIS MOD IS TO DE OBLIGATE EXCESS FUNDS.

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Check the stated set-aside against the solicitation and current certifications.