W56KGU18F0009

THE PURPOSE OF THIS TASK ORDER (TO), W56KGU18F0009, UNDER CONTRACT W15P7T-14-D-A210 IS AS FOLLOWS: 1. TO PROCURE CONTRACTOR PROVIDED SERVICES, ON-SITE AND OFF-SITE, TO INCLUDE CONTRACT SUPPORT TO INCLUDE RESEARCH AND DEVELOPMENT, ENGINEERING, LOGISTICS, AND BUSINESS OPERATIONS SERVICES SUPPORT IN ACCORDANCE WITH THE PERFORMANCE WORK STATEMENT ENTITLED "MISSION RESEARCH AND DEVELOPMENT (R&D) AND SCIENTIFIC AND ENGINEERING TECHNICAL ASSISTANCE (SETA) SUPPORT."

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW6QK ACC-APG
NAICS541712
PSCR425 — Engineering and Technical Services
Parent award / vehicleW15P7T14DA210
Set-asideNot reported
Pricing typeCOST PLUS FIXED FEE
Obligations$22.7M
Current contract value$23.7M
Potential contract value / ceiling$30.5M
Start dateSep 19, 2018
Current end dateSep 18, 2023
Potential end dateSep 18, 2023
Latest award activityMay 14, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 95 of 95 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 14, 2026P00094$-1.5KTASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE PROGRAM SUPPORT, COMMERCIAL TECHNOLOGY INTEGRATION AND DEVALUATION, SYSTEMS AND SOFTWARE ENGINEERING, AND SYSTEMS ARCHITECTURE SUPPORT.
Mar 5, 2026P00093$-22.3KTASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE PROGRAM SUPPORT, COMMERCIAL TECHNOLOGY INTEGRATION AND DEVALUATION, SYSTEMS, AND SOFTWARE ENGINEERING, AND SYSTEMS ARCHITECTURE SUPPORT.
Aug 22, 2025P00092$-8.9KTASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE PROGRAM SUPPORT, COMMERCIAL TECHNOLOGY INTEGRATION AND DEVALUATION, SYSTEMS AND SOFTWARE ENGINEERING, AND SYSTEMS ARCHITECTURE SUPPORT.
Jun 4, 2025P00091$-51.9KTHIS TASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE PROGRAM SUPPORT, COMMERCIAL TECHNOLOGY INTEGRATION AND DEVALUATION, SYSTEMS AND SOFTWARE ENGINEERING, AND SYSTEMS ARCHITECTURE SUPPORT.
Feb 5, 2025P00090$-49.0KTHIS TASK ORDER IS FOR CONTRACTOR PROVIDED SUPPORT SERVICES TO INCLUDE PROGRAM SUPPORT, COMMERCIAL TECHNOLOGY INTEGRATION AND EVALUATION, SYSTEMS AND SOFTWARE ENGINEERING, AND SYSTEMS ARCHITECTURE SUPPORT.
Feb 1, 2024P00089$-306.2KMODIFICATION P00089 FOR DE-OBLIGATION OF FUNDS PER FAR 52.232-22
Nov 21, 2023P00088$-64.2KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS.
Sep 26, 2023P00087$-522.0KDE-OBLIGATION OF FUNDS
Aug 16, 2023P00086$5.3KTHE PURPOSE OF THIS MODIFICATION IS FOR INCREMENTAL FUNDING.
Aug 3, 2023P00085$13.0KTHE PURPOSE OF THIS MODIFICATION IS FOR INCREMENTAL FUNDING OF $13,000 FOR MATERIALS IN ACCORDANCE WITH FAR 52.232-22 AND ADDED CLAUSES DFARS 252.225-7007 AND FAR 52.204-27
Jun 29, 2023P00084$249.3KTHE PURPOSE OF THIS MODIFICATION IS FOR INCREMENTAL FUNDING TOTALING $249,300 FOR TRAVEL/ODC'S PER FAR 52.232-22
Jun 8, 2023P00083$150.7KINCREMENTAL FUNDING OF $150,700 FOR LABOR PER FAR 52.232-22.
Apr 27, 2023P00082$181.0KINCREMENTAL FUNDING OF $181K IN ACCORDANCE WITH FAR 52.232-22 FOR LABOR AND MATERIAL AND IMPLEMENT AN ADMINISTRATIVE CHANGE TO UPDATE THE COR.
Apr 10, 2023P00081$264.8KINCREMENTAL FUNDING IN ACCORDANCE WITH FAR 52.232-22
Mar 13, 2023P00080$17.9KTHE PURPOSE OF MODIFICATION P00080 IS TO PROVIDE INCREMENTAL FUNDING AND TO DE-OBLIGATE FUNDING.
Feb 22, 2023P00079$613.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Feb 16, 2023P00078$0THE PURPOSE OF THIS MODIFICATION IS TO ADD MEM CONTRACTING, INC. AS A SUBCONTRACTOR TO THIS TASK ORDER.
Feb 3, 2023P00077$452.0KTHE PURPOSE OF THIS MODIFICATION IS TO REALIGN CEILING AND PROVIDE INCREMENTAL FUNDING FOR ODC.
Feb 1, 2023P00076$70.0KTHE PURPOSE OF THIS MODIFICATION IS TO REALIGN THE CEILING AND PROVIDE INCREMENTAL FUNDING FOR MATERIALS.
Dec 20, 2022P00075$86.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR ODC AND MATERIAL.
Dec 14, 2022P00074$-24.1KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDING AND REALIGN EXISTING FUNDING.
Nov 22, 2022P00073$237.5KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR OCD AND LABOR.
Nov 15, 2022P00072$100.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR LABOR.
Sep 26, 2022P00071$0THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING AND EXTEND PERIOD OF PERFORMANCE FOR MATERIAL PURCHASES.
Sep 15, 2022P00070$1.6MTHE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD FOUR (4) AND TO PROVIDE INCREMENTAL FUNDING.
Aug 25, 2022P00069$631.9KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR LABOR AND MATERIAL.
Jul 15, 2022P00068$7.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Jul 12, 2022P00067$-94.9KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDING.
Jun 24, 2022P00066$144.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Jun 1, 2022P00065$230.2KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
May 22, 2022P00064$0THE PURPOSE OF THIS MODIFICATION IS TO ADD RATIONA-3 LLC AS A SUBCONTRACTOR.
May 5, 2022P00063$269.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Apr 19, 2022P00062$194.1KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Apr 5, 2022P00061$-335.2KTHE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDING, REALIGN FUNDING, AND TO PROVIDE AN UPDATED DD254.
Mar 23, 2022P00060$288.1KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Feb 16, 2022P00059$188.8KTHE PURPOSE OF THIS MODIFICATION IS PROVIDE INCREMENTAL FUNDING.
Feb 15, 2022P00058$-3.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDING.
Jan 21, 2022P00057$220.1KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Jan 18, 2022P00056$165.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Dec 22, 2021P00055$150.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Dec 21, 2021P00054$-23.1KTHE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDING.
Nov 23, 2021P00053$0THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING.
Oct 18, 2021P00052$155.6KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Sep 24, 2021P00051$200.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Sep 20, 2021P00050$350.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Sep 14, 2021P00048$143.1KTHE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD THREE, PROVIDE INCREMENTAL FUNDING, AND TO REALIGN FUNDING.
Sep 14, 2021P00049$363.7KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING.
Aug 23, 2021P00047$3.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Jul 13, 2021P00046$3.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Jun 30, 2021P00045$270.6KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING AND INCORPORATE TWO (2) NEW ATTACHMENTS.
May 3, 2021P00044$7.9KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Apr 23, 2021P00043$0THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE AN APPROVED EULA ONTO THE TASK ORDER.
Apr 14, 2021P00042$486.2KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Mar 25, 2021P00041$156.0KINCREMENTAL FUNDING FOR LABOR AND TRAVEL
Mar 17, 2021P00040$615.0KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Mar 10, 2021P00039$1.1MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING
Feb 24, 2021P00038$320.0KMODIFICATION TO ADD INCREMENTAL FUNDING FOR OST AND PM TR SUPPORT.
Jan 15, 2021P00037$376.1KMODIFICATION TO ADD INCREMENTAL FUNDING FOR LABOR
Jan 6, 2021P00036$110.0KINCREMENTAL FUNDING FOR LABOR
Dec 17, 2020P00035$566.6KOBLIGATE FUNDS FOR LABOR
Dec 10, 2020P00034$0CHANGE ADMINISTRATION OFFICE FROM S3101A TO W56KGU
Dec 2, 2020P00033$149.5KMODIFICATION TO ADD INCREMENTAL FUNDING FOR OST SUPPORT.
Nov 20, 2020P00032$0REALIGN FUNDS FROM ODC TO LABOR IN THE AMOUNT OF 107,00.00
Oct 14, 2020P00031$0FUNDING REALIGNMENT AND ADMIN UPDATES
Sep 28, 2020P00030$-143.9KDEOBLIGATE FUNDS FROM ACRN BG
Sep 22, 2020P00029$350.0KINCREMENTAL FUNDING FOR SETA SUPPORT
Sep 18, 2020P00028$1.5MINCREMENTAL FUNDING SETA SUPPORT
Jun 30, 2020P00027$14.0KFUNDS FOR OST SUPPORT.
Jun 3, 2020P00026$90.0KSEVERABLE FUNDS ARE PROVIDED FOR LABOR FOR OST SUPPORT
May 12, 2020P00025$160.0KNON-SEVERABLE FUNDS ARE HEREBY PROVIDED FOR THE CONTRACTOR ENGINEERS TO WORK WITH A TEAM OF S&TCD ENGINEERS TO CONTINUE HMS RADIO PRODUCTS INTEGRATION, DEMONSTRATION AND TEST PLANNING, TESTING AND EXECUTION ANALYSIS.
Apr 30, 2020P00024$-158.0KTO DEOBLIGATE FUNDS PROVIDED FOR LABOR AND TRAVEL FOR TCD CT BRANCH FOR STRI EFFORT.
Apr 24, 2020P00023$585.4KFUNDS ARE HEREBY PROVIDED FOR EPIC CONTRACT TO ASSIST PM TACTICAL NETWORK DURING FY20 BETWEEN PM TACTICAL NETWORK SIGNAL MOD AND CERDEC S&TCD, AND FOR TCD CT BRANCH IVAS ITN EFFORT.
Apr 7, 2020P00022$-525.8KDEOBLIGATE LABOR FUNDS
Mar 25, 2020P00021$480.4KSEVERABLE FUNDS ARE HEREBY PROVIDED FOR SETA ENGINEERING SUPPORT TO ASSIST PM TACTICAL NETWORK
Mar 13, 2020P00019$-287.9KDEOBIGATE FUNDING FOR OST SUPPORT AND LABOR OY1 (STCD OPS/IT LABOR) - OVERHEAD
Mar 13, 2020P00020$762.5KFUNDS ARE HEREBY PROVIDED FOR TCD TR BRANCH RPTS PROGRAM AND LABOR FOR OST SUPPORT SETA
Jan 30, 2020P00018$525.0KFUNDS ARE PROVIDED FOR OST SUPPORT AND LABOR OY1 (STCD OPS/IT LABOR) - OVERHEAD
Jan 9, 2020P00017$1.2MFUNDS ARE PROVIDED FOR TCD TR BRANCH RPTS PROGRAM AND OST SUPPORT
Nov 22, 2019P00016$459.6KFUNDS ARE PROVIDED FOR SETA ENGINEERING SUPPORT
Oct 29, 2019P00015$452.6KFUNDS ARE PROVIDED FOR SETA ENGINEERING SUPPORT
Sep 18, 2019P00014$0POP EXTENSION FOR NON-SEVERABLE ACTIONS
Aug 30, 2019P00013$1.3MINCREMENTAL FUNDING FOR SETA SUPPORT AND EXERCISE OPTION ONE
Aug 16, 2019P00012$69.0KINCREMENTAL FUNDING
Jul 10, 2019P00011$276.6KTHE PURPOSE OF THIS MODIFICATION (P00011) IS TO MAKE CHANGES PURSUANT TO FAR 52.243-2, CHANGES COST REIMBURSEMENT.
Jun 12, 2019P00010$12.6KINCREMENTAL FUNDING
May 16, 2019P00009$118.0KTHE PURPOSE OF THIS MODIFICATION (P00009) IS TO PROVIDE INCREMENTAL FUNDS TO THE CONTRACT PURSUANT TO FAR 52.232-22 LIMITATION OF FUNDS.
Apr 16, 2019P00008$1.0MTHE PURPOSE OF THIS MODIFICATION (P00008) IS TO PROVIDE INCREMENTAL FUNDS TO THE CONTRACT PURSUANT TO FAR 52.232-22 LIMITATION OF FUNDS.
Apr 1, 2019P00007$506.7KTHE PURPOSE OF THIS MODIFICATION (P00007) IS TO MAKE CHANGES PURSUANT TO FAR 52.243-2 CHANGES COST REIMBURSEMENT.
Feb 27, 2019P00006$-425.1KTHE PURPOSE OF THIS MODIFICATION (P00006) IS TO MAKE CHANGES PURSUANT TO FAR 52.243-2 CHANGES COST REIMBURSEMENT.
Jan 9, 2019P00005$1.4MTHE PURPOSE OF THIS MODIFICATION (P00005) IS TO PROVIDE INCREMENTAL FUNDS TO THE CONTRACT PURSUANT TO FAR 52.232-22 LIMITATION OF FUNDS.
Nov 29, 2018P00004$748.4KTHE PURPOSE OF THIS MODIFICATION (P00004) IS TO MAKE CHANGES PURSUANT TO FAR 52.243-2 CHANGES COST REIMBURSEMENT.
Nov 6, 2018P00003$1.0MTHE PURPOSE OF THIS MODIFICATION (P00003) IS TO PROVIDE INCREMENTAL FUNDS TO THE CONTRACT PURSUANT TO FAR 52.232-22 LIMITATION OF FUNDS.
Oct 4, 2018P00002$124.0KTHE PURPOSE OF THIS MODIFICATION (P00002) IS TO PROVIDE INCREMENTAL FUNDS TO THE CONTRACT PURSUANT TO FAR 52.232-22 LIMITATION OF FUNDS.
Sep 26, 2018P00001$325.0KTHE PURPOSE OF THIS MODIFICATION (P00001) IS TO PROVIDE INCREMENTAL FUNDS TO THE CONTRACT PURSUANT TO FAR 52.232-22 LIMITATION OF FUNDS.
Sep 19, 20180$409.4KTHE PURPOSE OF THIS TASK ORDER (TO), W56KGU18F0009, UNDER CONTRACT W15P7T-14-D-A210 IS AS FOLLOWS: 1. TO PROCURE CONTRACTOR PROVIDED SERVICES, ON-SITE AND OFF-SITE, TO INCLUDE CONTRACT SUPPORT TO INCLUDE RESEARCH AND DEVELOPMENT, ENGINEERING, LOGISTICS, AND BUSINESS OPERATIONS SERVICES SUPPORT IN ACCORDANCE WITH THE PERFORMANCE WORK STATEMENT ENTITLED "MISSION RESEARCH AND DEVELOPMENT (R&D) AND SCIENTIFIC AND ENGINEERING TECHNICAL ASSISTANCE (SETA) SUPPORT."