Federal contract award
W56KGY17C0011
IGF::OT::IGF CONTRACT FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PRODUCT MANAGER (PDM) RADARS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QK ACC-APG |
| NAICS | 541330 — Engineering Services |
| PSC | R425 — Engineering and Technical Services |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $48.7M |
| Current contract value | $49.1M |
| Potential contract value / ceiling | $52.6M |
| Start date | May 24, 2017 |
| Current end date | Apr 22, 2026 |
| Potential end date | Apr 22, 2026 |
| Latest award activity | Apr 22, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 38 of 38 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 22, 2026 | P00033 | $46.5K | SOFTWARE, ENGINEERING AND TECHNICAL ASSISTANCE FOR THE Q53/50 RADAR SYSTEM |
| Aug 12, 2022 | P00032 | $-972.8K | MODIFICATION TO TRANSFER GOVERNMENT FURNISHED EQUIPMENT TO ORDER W56KGY21F0025 OF CONTRACT W15P7T-19-D-0131. |
| Mar 10, 2022 | P00031 | $1.2K | MODIFICATION TO REESTABLISH FUNDING TO SLIN 0203AJ. |
| Jan 25, 2022 | P00030 | $-307.9K | MODIFICATION TO DE-OBLIGATE EXCESS FUNDING. |
| Dec 20, 2021 | P00029 | $776.6K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE BY 30 DAYS TO ALLOW FOR THE ON BOARDING OF THE FOLLOW ON CONTRACT. |
| Nov 19, 2021 | P00028 | $847.9K | MODIFICATION TO EXERCISE OPTION O4. |
| Oct 29, 2021 | P00027 | $-412.2K | MODIFICATION TO DE-OBLIGATE FUNDING, PROVIDE FUNDING FOR ADDITIONAL FIELDERS, AND ADD THE COVID-19 CLAUSE. |
| Sep 30, 2021 | P00026 | $0 | FUNDING RE-ALIGNMENT |
| Sep 28, 2021 | P00025 | $0 | MODIFICATION TO FIX TYPOS IN PERIOD OF PERFORMANCE. |
| Sep 20, 2021 | P00024 | $1.8M | THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION AND INCREMENTALLY FUND. |
| Aug 26, 2021 | P00023 | $-46.7K | MODIFICATION TO DE-OBLIGATE FUNDS. |
| Aug 4, 2021 | P00022 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE INFORMATIONAL CLINS TO STAND ALONE CLINS. |
| Jul 21, 2021 | P00021 | $1.8M | THE PURPOSE OF THIS MODIFICATION IS TO BRIDGE THIS CONTRACT ONTO THE NEXT DUE TO A PROTEST THAT HAS DELAYED ACCEPTANCE OF THE NEW CONTRACT. |
| Jul 2, 2021 | P00020 | $-1.1M | MODIFICATION TO DE-OBLIGATE FUNDING. |
| May 7, 2021 | P00018 | $-60.0K | DE-OB MOD |
| May 7, 2021 | P00019 | $181.8K | THE PURPOSE OF MODIFICATION (P00019) ON W56KGY-17-C-0011 IS TO PROVIDE THE REMAINING FUNDING IN THE AMOUNT OF $181,784.86 FOR THE SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES 12 WEEK PERIOD OF PERFORMANCE (POP) EXTENSION. SEE SECTION B AND G OF THIS CONTRACT FOR FURTHER INFORMATION. |
| Apr 26, 2021 | P00017 | $2.5M | THE PURPOSE OF MODIFICATION (P00017) ON W56KGY-17-C-0011 IS TO EXTEND THE PERIOD OF PERFORMANCE (POP) BY 12 WEEKS AND PROVIDE FUNDING FOR THE POP EXTENSION. |
| Feb 19, 2021 | P00016 | $2.0M | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE (POP) BY NINE (9) WEEKS AND PROVIDE FUNDING FOR THE POP EXTENSION. |
| Oct 14, 2020 | P00015 | $3.7M | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE (POP) BY FOUR (4) MONTHS AND PROVIDE FUNDING FOR THE POP EXTENSION. |
| Sep 30, 2020 | P00013 | $77.1K | COVID-19 3610. THIS MODIFICATION PROVIDES FUNDING FOR A CARES ACT 3610 REIMBURSEMENT. |
| Sep 24, 2020 | P00014 | $0 | MODIFICATION TO REALIGN FUNDING |
| Mar 31, 2020 | P00012 | $5.5M | MODIFICATION TO EXERCISE A SIX MONTH OPTION PERIOD. |
| Mar 19, 2020 | P00011 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDS IN ORDER TO FUND A COST OVERRUN. |
| Jan 9, 2020 | ARZ999 | $0 | OT CONTRACT FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PRODUCT MANAGER (PDM) RADARS. |
| Oct 17, 2019 | P00010 | $2.1M | THIS MODIFICATION PROVIDES ADDITIONAL FUNDING TO FULLY FUND OPTION YEAR 2 |
| Apr 19, 2019 | P00009 | $8.5M | THIS MODIFICATION TO CONTRACT NO. W56KGY17C0011 EXERCISE OPTION YEAR 2 AND PROVIDES FUNDING FOR THIS OPTION. |
| Apr 19, 2019 | P00009 | $339.0K | THIS MODIFICATION TO CONTRACT NO. W56KGY17C0011 EXERCISE OPTION YEAR 2 AND PROVIDES FUNDING FOR THIS OPTION. |
| Mar 28, 2019 | P00008 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD THE STATUS OF FORCES AGREEMENT (SOFA) CLAUSES TO SECTION H NARRATIVE. |
| Feb 6, 2019 | P00007 | $0 | MODIFICATION TO REALIGN FUNDS. |
| Jul 10, 2018 | P00006 | $425.3K | AUTHORIZED FOR RADARS SETA CONTRACTOR SUPPORT TO THE C-UAS AND FMS PROGRAMS UNDER ESP CONTRACT |
| Jun 15, 2018 | P00005 | $0 | CHANGE THE OBLIGATION CODES ON SLINS 200101, 200102, 200201, 200202, 200301, 200302, 200303, AND 200304 FROM CODE "1" TO CODE "2". |
| Jun 4, 2018 | P00004 | $10.4M | REALIGNMENT OF FUNDING, EXERCISE OPTION YEAR ONE, AND PROVIDE FUNDING FOR OPTION YEAR ONE. |
| May 17, 2018 | P00003 | $0 | THE PURPOSE OF MODIFICATION P00003 TO CONTRACT W56KGY-17-C-0011 IS TO INCORPORATE A REVISED PERFORMANCE WORK STATEMENT (PWS) IN ACCORDANCE WITH FAR 52.243-2 "CHANGES -- COST REIMBURSEMENT". |
| May 15, 2018 | A00001 | $0 | IGF::OT::IGF CONTRACT FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PRODUCT MANAGER (PDM) RADARS. |
| Mar 7, 2018 | P00002 | $0 | THE PURPOSE OF THIS MODIFICATION IS FOR REALIGNING THE FUNDING. |
| Jun 21, 2017 | P00001 | $0 | IGF::OT::IGF MODIFICATION TO CHANGE THE PERIOD OF PERFORMANCE START DATE, CHANGE PAYMENT INSTRUCTIONS, AND MAKE ADMINISTRATIVE CHANGES TO THE PERFORMANCE WORK STATEMENT (PWS). |
| May 24, 2017 | 0 | $11.0M | IGF::OT::IGF CONTRACT FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PRODUCT MANAGER (PDM) RADARS. |
| May 24, 2017 | 0 | $0 | CONTRACT FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PRODUCT MANAGER (PDM) RADARS. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.