Federal contract award

W56KGY19F0057

TASK ORDER AWARD FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PROGRAM EXECUTIVE OFFICE INTELLIGENCE, ELECTRONIC WARFARE AND SENSORS (PEO IEW&S) HEADQUARTERS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW6QK ACC-APG
NAICS541712
PSCR408 — Program Management/Support Services
Parent award / vehicleW15P7T17D0113
Set-asideNot reported
Pricing typeCOST PLUS FIXED FEE
Obligations$19.0M
Current contract value$19.0M
Potential contract value / ceiling$38.5M
Start dateApr 29, 2019
Current end dateApr 28, 2024
Potential end dateApr 28, 2024
Latest award activityDec 2, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 64 of 64 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Dec 2, 2025P00062$-29.6KTHE MODIFICATION OF THIS TASK ORDER IS REQUIRED FOR SYSTEM ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PROGRAM EXECUTIVE OFFICE INTELLIGENCE, ELECTRONIC WARFARE AND SENSORS (PEO IEW&S)
Dec 2, 2025P00062$-29.6KTHE MODIFICATION OF THIS TASK ORDER IS REQUIRED FOR SYSTEM ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PROGRAM EXECUTIVE OFFICE INTELLIGENCE, ELECTRONIC WARFARE AND SENSORS (PEO IEW&S)
Aug 19, 2024P00061$-365.5KTO DE-OBLIGATE EXCESS FUNDS FROM THE TASK ORDER.
Aug 13, 2024P00060$-14.0KTO DE-OBLIGATE EXCESS FUNDS FROM THE TASK ORDER.
Jun 21, 2024P00059$0TO UPDATE CONTRACT OFFICER'S REPRESENTATIVE.
Apr 24, 2024P00058$0TO RE-ALIGN CEILING AND FUNDING UNDER OPTION PERIOD 4.
Dec 14, 2023P00057$81.0KPROVIDE INCREMENTAL FUNDING FOR OPTION PERIOD 4.
Dec 4, 2023P00056$465.0KRE-ALIGN CEILING CLINS AND PROVIDE INCREMENTAL FUNDING FOR OPTION PERIOD 4.
Oct 20, 2023P00055$-53.5KTO DE-OBLIGATE UNEXPENDED FUNDS FROM OPTION PERIOD 3.
Oct 4, 2023P00054$109.0KPROVIDE INCREMENTAL FUNDING TO SURGE CLIN OPTION PERIOD 4.
Sep 27, 2023P00053$52.5KTO RE-ALIGN FUNDING & CEILING CLINS AND PROVIDE INCREMENTAL FUNDING FOR OPTION PERIOD 4.
Sep 6, 2023P00052$30.0KPROVIDE INCREMENTAL MATERIAL FUNDING FOR OPTION PERIOD 4.
Aug 28, 2023P00051$509.2KPROVIDE INCREMENTAL FUNDING UNDER OPTION PERIOD 4.
Jul 17, 2023P00050$1.0MTO PROVIDE INCREMENTAL FUNDING UNDER OPTION PERIOD 4.
Apr 27, 2023P00049$3.9KTO RE-OBLIGATE FUNDING BACK TO SLIN 200303.
Apr 18, 2023P00048$1.6MTHE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 4, SURGE OPTION, RE-ALIGN MULTIPLE CEILING CLINS, AND PROVIDE INCREMENTAL FUNDING FOR MULTIPLE CLINS UNDER OPTION PERIOD 4.
Mar 30, 2023P00047$62.5KRE-ALIGN CEILING CLIN, DE-OBLIGATE EXCESS FUNDS UNDER OPTION YEAR 2, AND PROVIDE FUNDING FOR OPTION YEAR 3 COST OVERRUN.
Sep 29, 2022P00046$205.3KRE-ALIGN CEILING CLIN AND PROVIDE INCREMENTAL FUNDING FOR MULTIPLE CLINS UNDER OPTION PERIOD 3.
Sep 27, 2022P00045$242.1KRE-ALIGN MULTIPLE CEILING CLINS AND PROVIDE INCREMENTAL FUNDING FOR MULTIPLE CLINS UNDER OPTION PERIOD 3.
Sep 9, 2022P00044$194.6KRE-ALIGN CEILING CLIN AND PROVIDE INCREMENTAL FUNDING FOR OPTION PERIOD 3.
Aug 18, 2022P00043$0ADDITION OF THE SUBCONTRACTOR.
Jun 30, 2022P00042$2.5MRE-ALIGN CEILING CLIN, EXERCISE SURGE OPTION, AS WELL AS PROVIDE INCREMENTAL FUNDING FOR OY3.
Apr 5, 2022P00041$1.1MTHE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 3, SURGE OPTION 3, AND PROVIDE INCREMENTAL FUNDING FOR MULTIPLE CLINS.
Mar 22, 2022P00040$401.1KRE-ALIGNMENT OF MULTIPLE CEILING CLINS AND PROVIDE INCREMENTAL FUNDING FOR MULTIPLE CLINS UNDER REMAINDER OF OY2.
Feb 18, 2022P00039$300.0KREALIGNMENT OF MULTIPLE CEILING CLINS AND PROVIDE INCREMENTAL FUNDING FOR MULTIPLE CLINS UNDER OY2.
Jan 6, 2022P00038$0FUNDS REALLOCATION UNDER OY2.
Dec 7, 2021P00037$408.5KRE-ALIGN CEILING, EXERCISE SURGE OPTION, AS WELL AS PROVIDE FUNDING FOR OY2.
Nov 4, 2021P00036$0INCORPORATE PROPOSED PAYMENT INSTRUCTIONS.
Sep 29, 2021P00035$0UPDATE COR DESIGNATION AND LCAT REQUIREMENTS.
Sep 17, 2021P00034$614.4KRE-ALIGN CEILING, RE-ALLOCATE FUNDING, AS WELL AS PROVIDE FUNDING FOR MULTIPLE CLINS UNDER OY2.
Aug 31, 2021P00033$0INCORPORATE PAYMENT INSTRUCTIONS.
Jul 19, 2021P00032$500.0KPROVIDE FUNDING FOR MULTIPLE CLINS UNDER OY2.
Jul 9, 2021P00031$600.0KRE-ALIGN CEILING, EXERCISE SURGE OPTION CLIN, PROVIDE FUNDING FOR MULTIPLE CLINS UNDER OY2, AND INCORPORATE GFP LIST.
Jun 4, 2021P00030$379.6KRE-ALIGN CEILING, RE-ALLOCATE FUNDING, EXERCISE SURGE OPTION, AS WELL AS PROVIDE FUNDING FOR OY2.
May 24, 2021P00029$0UPDATING PWS, DD FORM 254 AND SECURITY APPENDIX TO PWS.
Mar 19, 2021P00028$810.1KTHE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION PERIOD 2, SURGE OPTION, AND PROVIDE FUNDING FOR MULTIPLE CLINS, AS WELL AS INCORPORATE ALTERNATE COR.
Mar 5, 2021P00027$112.2KRE-ALIGN CEILING, EXERCISE SURGE OPTION, AS WELL AS PROVIDE FUNDING FOR OY1.
Feb 25, 2021P00026$375.9KPROVIDE FUNDING FOR OY1 COST OVERRUN, INCORPORATE GFP LIST, AND REDUCING FEE AS A RESULT OF SCOPE CHANGE.
Jan 28, 2021P00025$0INCORPORATE UPDATED PWS AND LABOR CATEGORY REQUIREMENTS AND RE-ALIGN CEILING FOR MULTIPLE CLINS UNDER BASE, OPTION PERIOD 1, AND OPTION PERIOD 2 DUE TO WITHIN SCOPE CHANGE.
Jan 12, 2021P00024$66.7KINCREMENTALLY FUNDING UNDER OPTION YEAR 1.
Oct 30, 2020P00023$0INCORPORATE PWS AND LCAT REQUIREMENTS.
Oct 23, 2020P00022$0ADDITION OF THE SUBCONTRACTOR.
Sep 3, 2020P00021$0THE PURPOSE OF THIS MODIFICATION IS TO REALIGN FUNDING FROM CLIN 1004 TO CLIN 1011 UNDER OPTION PERIOD 1.
Aug 25, 2020P00020$868.2KTHE PURPOSE OF THIS MODIFICATION TO REALIGN CLIN CEILINGS UNDER OPTION PERIOD 1, TRANSFER GFP, AND PROVIDE FUNDING TO MULTIPLE CLINS AS SET FORTH BELOW:
Jul 23, 2020P00019$0REALIGN FUNDING FROM MULTIPLE SLINS
Jun 8, 2020P00018$673.0KPROVIDE INCREMENTAL FUNDING AND CHANGE THE KO
Apr 28, 2020P00017$1.7M1. THE PURPOSE OF MODIFICATION P00017 IS TO EXERCISE OPTION PERIOD 1, IN ACCORDANCE WITH FAR 52.217-9, OPTION TO EXTEND THE TERM OF THE CONTRACT AND TO MAKE IN-SCOPE CHANGES TO THE LEVEL OF EFFORT (LOE) OF OPTION PERIOD 1, PURSUANT TO FAR 52.243-2 - CHANGES.
Apr 15, 2020P00016$-10.6KTHE PURPOSE OF THIS MODIFICATION IS TO CORRECT MOD P00015&TO
Apr 1, 2020P00014$0THE PURPOSE OF THIS MODIFICATION P00014 IS TO ADD GOVERNMENT FURNISHED PROPERTY (GFP) TO THE ORDER.
Mar 30, 2020P00015$241.5KTHE PURPOSE OF MODIFICATION P00015 IS TO FUND A LABOR COST OVERRUN, ON THE BASE PERIOD, IN THE TOTAL AMOUNT OF $241,504.20.
Mar 3, 2020P00013$120.8KPEO IEW&S SETA FUNDING MODIFICATION TO RE-ALIGN MATERIAL COST TO TRAVEL COST AND COMPLETE FUNDING OF BASE POP
Jan 13, 2020P00012$0THE PURPOSE OF MODIFICATION P00012 IS TO CORRECT TYPOGRAPHICAL ERRORS FROM P00012.
Jan 6, 2020P00011$615.0KTHE PURPOSE OF MODIFICATION P00011 IS TO PROVIDE ADDITIONAL FUNDING, PURSUANT TO FAR 52.232-22 - LIMITATION OF FUNDS AND TO CLARIFY PAYMENT INSTRUCTIONS IN ACCORDANCE WITH DFARS PGI 204.7108, PAYMENT INSTRUCTIONS.
Dec 11, 2019P00010$0MODIFICATION TO DEFINITIZE A CHANGE ORDER AND PROVIDE COST OVERRUN FUNDING.
Oct 31, 2019P00009$695.6KPURPOSE IS TO PROVIDE ADDITIONAL FUNDING FOR BASE SERVICES AND CORRECT NARRATIVE ASSOCIATED TO SLIN 001201 FOR PEO IEWS SETA
Oct 22, 2019P00008$53.6KTHE PURPOSE OF MODIFICATION P00008 IS TO EXERCISE THE BASE PERIOD SURGE OPTION FOR HR PROGRAM ANALYST SUPPORT AND TO REVISE THE SECTION A AND CLIN NARRATIVES ASSOCIATED WITH MODIFICATION P00007 TO PROVIDE ADDITIONAL CLARIFICATION.
Sep 27, 2019P00007$275.0KTHIS ACTION IS BEING COMPLETED TO REALIGN TRAVEL FUNDING AND ADD $275000.00 ON CLIN 0002 IAW FAR 52.232-22, LIMITATION OF FUNDS DUE TO OFFICIAL NOTIFICATION OF CONTRACTOR EXCEEDING COSTS OF 75% OF ALLOCATED FUNDING.
Sep 5, 2019P00006$0ADDED OCONUS TRAVEL CLAUSES.
Aug 29, 2019P00005$0PEO IEWS SETA - CHANGE MODIFICATION TO UPDATE PWS, UPDATE LABOR CATEGORY REQUIREMENTS, UPDATE ASSOCIATED DD254 AND UPDATE ASSOCIATED CDRLS
Aug 2, 2019P00004$0THIS ADMINISTRATIVE MOD CORRECTS THE SERVICE APPROVER AND SERVICE ACCEPTOR DODAAC IN DFARS CLAUSE 252.232-7006 - WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS.
Jul 31, 2019P00003$0THE PURPOSE OF THIS MODIFICATION (P00004) IS TO MAKE CORRECTIONS TO THE ADMINISTRATION OFFICE, DODAAC INFORMATION IN THE WAWF SECTION OF THE PWS AND INFORMATION OF WAWF CLAUSE AND TO DELETE REMAINING REFERENCES TO CDRL A001 PURSUANT TO FAR 43.103(B)
Jun 7, 2019P00002$0THE PURPOSE OF THIS MODIFICATION (07) IS TO REALIGN TRAVEL FUNDS TO BETTER ALIGN WITH MISSION REQUIREMENTS PURSUANT TO FAR 52.232-22,LIMITATION OF FUNDS.
May 24, 2019P00001$0THIS MODIFICATION ADDS CONTRACT DATA REQUIREMENTS LIST (CDRL) FOR SMALL BUSINESS PARTICIPATION REPORTING AND INCORPORATES AN UPDATED SECURITY CLASSIFICATION SPECIFICATION FORM (DD254) AND PERFORMANCE WORK STATEMENT (PWS).
Apr 29, 20190$1.6MTASK ORDER AWARD FOR SYSTEMS ENGINEERING AND TECHNICAL ASSISTANCE (SETA) SUPPORT SERVICES FOR PROGRAM EXECUTIVE OFFICE INTELLIGENCE, ELECTRONIC WARFARE AND SENSORS (PEO IEW&S) HEADQUARTERS.

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.