Federal contract award
W56KGY22F0037
THIS TASK ORDER IS FOR THE BLOCK 2 REQUIREMENTS UNDER JTT-NG.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QK ACC-APG |
| NAICS | 334220 — Radio and Television Broadcasting and Wireless Communications Equipment Manufacturing |
| PSC | 6710 — Cameras, Motion Picture |
| Parent award / vehicle | W56KGY20D0013 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $33.7M |
| Current contract value | $33.7M |
| Potential contract value / ceiling | $33.7M |
| Start date | Aug 31, 2022 |
| Current end date | Apr 29, 2027 |
| Potential end date | Apr 29, 2027 |
| Latest award activity | Apr 30, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 36 of 36 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 30, 2026 | P00023 | $185.6K | THIS PROGRAM IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENT. |
| Apr 30, 2026 | P00023 | $185.6K | THIS PROGRAM IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENT. |
| Apr 16, 2026 | P00022 | $0 | THIS PROGRAM IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENT. |
| Apr 16, 2026 | P00022 | $0 | THIS PROGRAM IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENT. |
| Mar 20, 2026 | P00021 | $1.5M | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Mar 20, 2026 | P00021 | $1.5M | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Jan 29, 2026 | P00020 | $700.0K | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Jan 29, 2026 | P00020 | $700.0K | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Dec 10, 2025 | P00019 | $0 | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Dec 10, 2025 | P00019 | $0 | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Sep 30, 2025 | P00018 | $0 | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Sep 30, 2025 | P00018 | $0 | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Sep 29, 2025 | P00017 | $338.1K | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Sep 29, 2025 | P00017 | $338.1K | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Jul 3, 2025 | P00016 | $1.8M | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Jul 3, 2025 | P00016 | $1.8M | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Mar 24, 2025 | P00015 | $385.4K | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Mar 24, 2025 | P00015 | $385.4K | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS. |
| Feb 6, 2025 | P00014 | $1.4M | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS IN SUPPORT OF PROJECT MANAGER INTELLIGENCE SYSTEMS AND ANALYTICS (PM IS&A). |
| Feb 6, 2025 | P00014 | $1.4M | THIS PROCUREMENT IS FOR THE JOINT TACTICAL TERMINAL - NEXT GENERATION PRODUCTION AND SERVICES BLOCK 2 REQUIREMENTS IN SUPPORT OF PROJECT MANAGER INTELLIGENCE SYSTEMS AND ANALYTICS (PM IS&A). |
| Dec 4, 2024 | P00013 | $121.0K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE AND RE-OBLIGATE A SLIN, PROVIDE FUNDING FOR THE BLOCK 1 ATO/RMF EFFORT AND TO UPDATE THE MUOS SECURITY CLASSIFICATION GUIDE. |
| Dec 4, 2024 | P00013 | $121.0K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE AND RE-OBLIGATE A SLIN, PROVIDE FUNDING FOR THE BLOCK 1 ATO/RMF EFFORT AND TO UPDATE THE MUOS SECURITY CLASSIFICATION GUIDE. |
| Oct 31, 2024 | P00012 | $2.8M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING, CORRECT ERRORS AND REVISE THE PERFORMANCE WORK STATEMENT. |
| Oct 31, 2024 | P00012 | $2.8M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING, CORRECT ERRORS AND REVISE THE PERFORMANCE WORK STATEMENT. |
| Sep 24, 2024 | P00011 | $800.0K | THE PURPOSE OF THIS MODIFICATION IS TO RE-ALIGN FUNDING, PROVIDE FUNDING AND UPDATE THE PWS. |
| Jun 27, 2024 | P00010 | $2.0M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING. |
| Feb 29, 2024 | P00009 | $2.5M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING. |
| Nov 30, 2023 | P00008 | $5.0M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING, FUNDING FOR PHASE 1A OF THE EPA RISK REDUCTION AND TO CORRECT AN ERROR IN THE NEGOTIATED TASK ORDER AMOUNT. |
| Sep 28, 2023 | P00007 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD DFARS CLAUSE 252.225-7007 TO THE ORDER. |
| Sep 25, 2023 | P00006 | $-534.9K | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE COST/FEE SPLIT, INCREASE THE CEILING, DE-OBLIGATE FUNDING, AND ADD THE SECURITY GUIDE ATTACHMENT. |
| Sep 18, 2023 | P00005 | $225.2K | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE ERRORS IN FEE, REALIGN FUNDING BETWEEN CLINS, ADD INCREMENTAL FUNDING, ADD FUNDING, UPDATE THE PWS, UPDATE THE GFP, AND UPDATE THE CDRL. |
| May 19, 2023 | P00004 | $2.0M | THE PURPOSE OF THIS MODIFICATION IS TO RE-ALIGN FUNDS AND TO PROVIDE ADDITIONAL INCREMENTAL FUNDING. |
| Mar 31, 2023 | P00003 | $6.0M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING TO CLINS 0024, 0025, AND 0029. |
| Nov 28, 2022 | P00002 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE CLIN NARRATIVES AND TO UPDATE THE CONTRACT DATA REQUIREMENTS LIST. |
| Oct 11, 2022 | P00001 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CLIN 0019AA, 0024AA AND 0025'S INSPECTION/ACCEPTANCE FROM ORIGIN TO DESTINATION. |
| Aug 31, 2022 | 0 | $6.5M | THIS TASK ORDER IS FOR THE BLOCK 2 REQUIREMENTS UNDER JTT-NG. |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
75/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 75/100. Available recorded signals: 70 points.
- Contract end 2027-04-29 (186 days from calculation)
- +35 points
- 10 historical awards in this buyer and category group
- +15 points
- 36 recorded award transactions
- +10 points
- Latest award action: 2026-04-30
- +5 points
- Parent award identifier recorded
- +5 points
- Solicitation identifier recorded
- +0 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.