Federal contract award
W900KK20F0149
MH-47-1 CMS UPGRADE MANUFACTURE, INSTALL, AND INTEGRATE MH-47G BLOCK II UPGRADES INTO THE MH-47-1 COMBAT MISSION SIMULATOR (CMS). IN ACCORDANCE WITH SOW-2019-26
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QK ACC-APG-ORLANDO |
| NAICS | 333318 |
| PSC | 6930 — Operation Training Devices |
| Parent award / vehicle | W900KK20D0014 |
| Set-aside | Not reported |
| Pricing type | FIXED PRICE INCENTIVE |
| Obligations | $3.6M |
| Current contract value | $3.6M |
| Potential contract value / ceiling | $3.6M |
| Start date | Aug 24, 2020 |
| Current end date | Jul 31, 2023 |
| Potential end date | Jul 31, 2023 |
| Latest award activity | Apr 4, 2024 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 4, 2024 | P00006 | $0 | SPECIAL OPERATIONS FORCES AVIATION SYSTEMS TRAINERS ENHANCEMENTS II. DELIVERY ORDER FOR MH-47 COMBAT MISSION SIMULATOR (CMS) UPGRADE. MODIFICATION CAPTURES THE NOVATION EXECUTION BY DCMA VIA MASS MODIFICATION ARZ997. |
| Jan 26, 2024 | P00005 | $-530.2K | THE PURPOSE OF THIS MODIFICATION IS TO REMOVE EXCESS FUNDS AS PART OF THE CLOSEOUT PROCESS. |
| Jan 9, 2023 | P00004 | $0 | MODIFICATION TO EXTEND PERFORMANCE FOR ALL CONTRACT LINE ITEMS TO 31 JULY 2023 AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| Sep 1, 2021 | P00003 | $53.5K | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO 30 JANUARY 2023, INCORPORATE THE REVISED PERFORMANCE SPECIFICATION INTO SECTION J, AND INCREASE CLIN 0001 COST IN ACCORDANCE WITH THE AWARDED ECP. |
| Feb 4, 2021 | P00002 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD THE SURVEILLANCE CRITICALITY DESIGNATOR (SCD) CODE. THIS IS IN RESPONSE TO CDR CN77281. |
| Nov 19, 2020 | P00001 | $0 | MODIFICATION TO CHANGE PERIOD OF PERFORMANCE TO 06 SEPTEMBER 2021 AND TO CHANGE CLIN 0001 TO FFP. |
| Aug 25, 2020 | 0 | $4.0M | MH-47-1 CMS UPGRADE MANUFACTURE, INSTALL, AND INTEGRATE MH-47G BLOCK II UPGRADES INTO THE MH-47-1 COMBAT MISSION SIMULATOR (CMS). IN ACCORDANCE WITH SOW-2019-26 |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.