Federal contract award

W909MY22C0023

THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LRIP LOW RATE INITIAL PRODUCTION (LRIP) DEWAR COOLER BENCH (DCB) PROGRAM

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW6QK ACC-APG CONT CT WASH OFC
NAICS334511 — Search, Detection, Navigation, Guidance, Aeronautical, and Nautical System and Instrument Manufacturing
PSC1240 — Optical Sighting and Ranging Equipment
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$62.6M
Current contract value$62.6M
Potential contract value / ceiling$101.4M
Start dateAug 23, 2022
Current end dateJan 31, 2029
Potential end dateJan 31, 2029
Latest award activityJun 12, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 29 of 29 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 12, 2026P00019$0THIS REQUIREMENT IS TO PROCURE THE LOT NINE (9) MINIMUM SUSTAINING RATE FOR THE MANUFACTURE, ASSEMBLE, TEST, AND DELIVERY IF A QUANTITY OF FORTY-EIGHT 3GEN FLIR DEWAR COOLER BENCHES IN ACCORDANCE WITH THE PERFORMANCE WORK STATEMENT.
Apr 29, 2026P00018$20.2MTHIS REQUIREMENT IS FOR THE PROCUREMENT OF LOW RATE INITIAL PRODUCTION OF THE 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Apr 29, 2026P00018$20.2MTHIS REQUIREMENT IS FOR THE PROCUREMENT OF LOW RATE INITIAL PRODUCTION OF THE 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Nov 25, 2025P00017$102.1KTHIS REQUIREMENT IS TO PROCURE THE LOT 9 MINIMUM SUSTAINING RATE FOR THE MANUFACTURE, ASSEMBLE, TEST, AND DELIVERY IF A QUANTITY OF FORTY-EIGHT THIRD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES IN ACCORDANCE WITH THE PWS.
Nov 25, 2025P00017$102.1KTHIS REQUIREMENT IS TO PROCURE THE LOT 9 MINIMUM SUSTAINING RATE FOR THE MANUFACTURE, ASSEMBLE, TEST, AND DELIVERY IF A QUANTITY OF FORTY-EIGHT THIRD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES IN ACCORDANCE WITH THE PWS.
Sep 11, 2025P00016$22.9MTHIS REQUIREMENT IS TO PROCURE THE LOT 9 MINIMUM SUSTAINING RATE FOR THE MANUFACTURE, ASSEMBLE, TEST, AND DELIVERY OF A QUANTITY OF FORTY-EIGHT 3GEN FLIR DEWAR COOLER BENCHES IN ACCORDANCE WITH 3.1.7.9 OF PERFORMANCE WORK STATEMENT.
Sep 11, 2025P00016$22.9MTHIS REQUIREMENT IS TO PROCURE THE LOT 9 MINIMUM SUSTAINING RATE FOR THE MANUFACTURE, ASSEMBLE, TEST, AND DELIVERY OF A QUANTITY OF FORTY-EIGHT 3GEN FLIR DEWAR COOLER BENCHES IN ACCORDANCE WITH 3.1.7.9 OF PERFORMANCE WORK STATEMENT.
Jun 3, 2025P00015$1.7MTHE PURPOSE OF THIS REQUIREMENT IS TO PROCURE LOW-RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Jun 3, 2025P00015$1.7MTHE PURPOSE OF THIS REQUIREMENT IS TO PROCURE LOW-RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Apr 17, 2025P00014$0THE PURPOSE OF THIS REQUIREMENT IS TO PROCURE LOW-RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Apr 17, 2025P00014$0THE PURPOSE OF THIS REQUIREMENT IS TO PROCURE LOW-RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Mar 21, 2025P00013$0THIS REQUIREMENT IS FOR THE PURCHASE OF LOW RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Mar 21, 2025P00013$0THIS REQUIREMENT IS FOR THE PURCHASE OF LOW RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Feb 26, 2025P00012$0THIS REQUIREMENT IS FOR THE PURCHASE OF LOW RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Feb 26, 2025P00012$0THIS REQUIREMENT IS FOR THE PURCHASE OF LOW RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Dec 11, 2024P00011$562.3KTHIS REQUIREMENT IS FOR THE PURCHASE OF LOW RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Dec 11, 2024P00011$562.3KTHIS REQUIREMENT IS FOR THE PURCHASE OF LOW RATE INITIAL PRODUCTION OF 3RD GENERATION FORWARD LOOKING INFRARED DEWAR COOLER BENCHES.
Nov 15, 2024P00010$0THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW RATE INITIAL PRODUCTION (LRIP) DEWAR COOLER BENCH (DCB) PROGRAM. DCB PROVIDES THE ABILITY TO DETECT THREATS AT GREATER DISTANCES UNDER A FULL SPECTRUM OF CONFLICT AND BATTLEFIELD CONDITIONS.
Nov 15, 2024P00010$0THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW RATE INITIAL PRODUCTION (LRIP) DEWAR COOLER BENCH (DCB) PROGRAM. DCB PROVIDES THE ABILITY TO DETECT THREATS AT GREATER DISTANCES UNDER A FULL SPECTRUM OF CONFLICT AND BATTLEFIELD CONDITIONS.
Sep 26, 2024P00009$382.4KTHE THIRD GENERATION FORWARD LOOKING INFRARED LOW RATE INITIAL PRODUCTION DEWAR COOLER BENCH PROGRAM IS THE NEXT GENERATION OF RECONNAISSANCE, SURVEILLANCE AND TARGET ACQUISITION SIGHTS IMPROVING RANGE AND RESOLUTION FOR USE IN ARMY COMBAT VEHICLES.
Jul 30, 2024P00008$17.6KINCREMENTAL FUNDING, REALIGN FUNDS, AND POP NO-COST EXTENSION
May 9, 2024P00007$0GFM TRANSFER AND CONSIDERATIONS
Feb 21, 2024P00006$0EXTENDING POPS FOR SLINS 0004AD, 0004AE, 0004AF, 0004AJ, 0004AK, ADD NSP CLIN 1008, AND INCORPORATE PBP INVOICING INSTRUCTIONS.
Jan 17, 2024P00005$307.5KPROVIDING INC FUNDING FOR DCB REPAIRS AND YEAR 2 CDRLS, REALIGNING CEILING FROM 0007 TO 1007, 2007 & 3007, RECEIVING GFP TRANSFER.
Aug 25, 2023P00004$7.9MFUNDING SERVICES, REVISE FACILITY CODE, REASSIGN PLACE OF PERFORMANCE, UPDATE ROUTING TABLE, INCORPORATE REVISED PWS, AND EXERCISE OPTION 1004.
Mar 24, 2023P00003$1.4MTHE PURPOSE OF MODIFICATION [P00003] IS TO EFFECT THE FOLLOWING: EXERCISE OPTION CLIN FOR ABRAMS LOT 2, INCORPORATE PBP INVOICING FOR CLIN 0003, FUNDING CLIN 0004 FOR VAM AND FAT PLANNING, REVISE TITLE FOR CLIN 0007, INCORPORATE REVISED PWS
Jan 24, 2023P00002$25.9KTHE PURPOSE OF MODIFICATION [P00002] IS TO INCORPORATE FOUR (4) ENGINEERING CHANGE PROPOSALS (ECPS) AND PROVIDE INCREMENTAL FUNDING UNDER CLIN 0004 FOR ECP IMPLEMENTATION.
Nov 21, 2022P00001$556.9KMOD TO TRANSFER CEILING FROM CLIN 0004 TO CLIN 0007, OBLIGATE INCREMENTAL FUNDS FOR CLIN 0007 BASE PROCUREMENT CDRLS, INCORPORATE PBP INVOICING INSTRUCTIONS AND DFARS CLAUSE FOR CLINS 0001 AND 0007, AND REVISE CDRLS
Aug 23, 20220$6.6MTHE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LRIP LOW RATE INITIAL PRODUCTION (LRIP) DEWAR COOLER BENCH (DCB) PROGRAM

Estimated positioning window

Jan 31, 2028 – Jul 31, 2028

Recompete signal:
45/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 45/100. Available recorded signals: 40 points.

Contract end 2029-01-31 (829 days from calculation)
+15 points
1 historical awards in this buyer and category group
+0 points
29 recorded award transactions
+10 points
Latest award action: 2026-06-12
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.