FieldReported value
AgencyDepartment of Defense
OfficeW6QK ACC-APG CONT CT WASH OFC
NAICS334511 — Search, Detection, Navigation, Guidance, Aeronautical, and Nautical System and Instrument Manufacturing
PSC5855 — Night Vision Equipment, Emitted and Reflected Radiation
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$103.5M
Current contract value$103.5M
Potential contract value / ceiling$165.3M
Start dateJun 29, 2023
Current end dateJun 30, 2029
Potential end dateJun 30, 2029
Latest award activityMay 13, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 23 of 23 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 13, 2026P00022$3.1MTHIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
Mar 11, 2026P00021$393.2KTHIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
Feb 26, 2026P00020$0THIS EFFORT IS FOR THE DEVELOPMENT, MANUFACTURE, AND DELIVERY OF THE THIRD GENERATION FORWARD LOOKING INFRARED B-KITS.
Dec 5, 2025P00019$0THE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER TWENTY-TWO (22) OF THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) B-KITS AND TWENTY-SIX (26) THERMAL RECEIVER UNITS (TRUS) IN ORDER TO MEET
Sep 30, 2025P00018$0THE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER TWENTY-TWO (22) THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) B-KITS AND TWENTY- SIX (26) THERMAL RECEIVER UNITS (TRUS) IN TO MEET MSR REQUIREMENTS.
Aug 20, 2025P00017$35.1MTHE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER TWENTY-TWO (22) 3GEN FLIR B-KITS AND TWENTY- SIX (26) TRUS AS SET FORTH IN TO MEET MSR REQUIREMENTS IN ACCORDANCE WITH (IAW) SECTION 3.1.8.5 OF THE PERFORMANCE WORK STATEMENT (PWS).
Jul 2, 2025P00016$256.4KTHE PURPOSE OF THIS REQUIREMENT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
Jun 3, 2025P00015$138.0KTEH PURPOSE OF THE REQUIREMENT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
Apr 28, 2025P00014$-160.8KTHE PURPOSE OF THE REQUIREMENT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
Apr 17, 2025P00013$0THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW-RATE INITIAL PRODUCTION (LRIP) B-KIT AND TECHNICAL & ENGINERING SERVICES, TEST SERVICES, AND LOGISTICS SERVICES.
Dec 5, 2024P00012$0THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW-RATE INITIAL PRODUCTION (LRIP) B-KIT AND TECHNICAL & ENGINEERING SERVICES, TEST SERVICES, AND LOGISTICS SERVICES.
Oct 31, 2024P00011$0THE OBJECTIVE OF THIS EFFORT IS TO DEVELOP, MANUFACTURE, AND DELIVER THIRD GENERATION FORWARD LOOKING INFARED B-KITS.
Sep 26, 2024P00010$829.3KTHIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW RATE INITIAL PRODUCTION (LRIP) B-KIT TECHNICAL & ENGINEERING SERVICES, TEST SERVICES, AND LOGISTICS SERVICES.
Sep 4, 2024P00009$8.4MTHE OBJECTIVE OF THIS EFFORT IS TO MANUFACTURE AND DELIVER THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) B-KITS AND PROVIDE ASSOCIATED ENGINEERING SERVICES.
Aug 5, 2024P00008$0THIS REQUIREMENT IS FOR THE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LOW-RATE INITIAL PRODUCTION AS WELL AS TECHNICAL AND ENGINEERING SERVICES.
Jun 17, 2024P00007$40.8KRE-OBLIGATING AND DE-OBLIGATING FUNDS TO CORRECT INVOICING
May 16, 2024P00006$-240.8KDE-OBLIGATING FUNDS
Apr 25, 2024P00005$2.1MINC FUNDING, INCORPORATE ECPS AND REVISED PWS
Feb 16, 2024P00004$6.5MPROVIDING INC FUNDS, REDUCE CLIN 1001 AND REALIGN TO CLIN 1027, PROVIDE FUNDING TO SUPPORT YEAR 2 ANNUAL LABOR, AND RECEIVE GFP AND CAP FROM DO W909MY19F0054
Dec 15, 2023P00003$6.6MADDING INC FUNDS, DELETE CLINS, REVISE OPTION CLIN 1014, REVISE DELIVERY DATES, INCORPORATE REVISED CDRLS AND PWS
Nov 30, 2023P00002$8.7MINC FUNDING, EXERCISE OPTIONS, REVISE PRICING, REVISE DELIVERY SCHEDULE, REVISE SHIP TO, REVISE BILLING, DELETE CLINS, AND INCORPORATE REVISED PWS.
Sep 26, 2023P00001$311.5KINCREMENTAL FUNDING, UPDATING CLAUSES AND REVISE ATTACHMENTS
Jun 29, 20230$27.4MTHE THIRD GENERATION FORWARD LOOKING INFRARED (3GEN FLIR) LRIP LOW RATE INITIAL PRODUCTION (LRIP) B-KIT

Estimated positioning window

Jun 30, 2028 – Dec 30, 2028

Recompete signal:
60/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 60/100. Available recorded signals: 55 points.

Contract end 2029-06-30 (972 days from calculation)
+15 points
38 historical awards in this buyer and category group
+15 points
23 recorded award transactions
+10 points
Latest award action: 2026-05-13
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-11-01 10:17:53.997580+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Nov 1, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.