Federal contract award
W911KB19C0001
LRDR POWER PLANT (LPP) CONSTRUCTION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SN ENDIST ALASKA |
| NAICS | 237130 — Power and Communication Line and Related Structures Construction |
| PSC | Y1BC — CONSTRUCTION OF RADAR AND NAVIGATIONAL FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $142.5M |
| Current contract value | $142.5M |
| Potential contract value / ceiling | $142.5M |
| Start date | Mar 8, 2019 |
| Current end date | Oct 18, 2022 |
| Potential end date | Oct 18, 2022 |
| Latest award activity | May 6, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 68 of 68 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 6, 2026 | P00067 | $52.5K | CONTRACT FOR CLR039C, LRDR POWER PLANT (LPP) AT CLEAR AFS, ALASKA REFERENCE NO. R0006800063 BREAKER AND RELAY PROTECTION SETTINGS |
| Mar 26, 2026 | P00066 | $108.5K | W911KB19C0001, CLR039C, LRDR POWER PLANT (LPP), MODIFICATION P00066, CR#64 LEVEL TRANSMITTER REPLACEMENT-PILOT REFERENCE NO. R00067 |
| Feb 12, 2026 | P00065 | $445.6K | W911KB19C0001, CLR039C, LRDR POWER PLANT (LPP), MODIFICATION P00065, CR#54-2 (POST BOD INTEGRATION SUPPORT) |
| Aug 20, 2025 | P00064 | $793.2K | CLR039C LPP P00064 R00065 CR00062- NIU INTEGRATION |
| Aug 19, 2025 | P00063 | $915.0K | POWER PLANT (LPP) - CHANGE P00063 |
| May 1, 2025 | P00062 | $299.1K | CLR039C LRDR POWER PLANT REA FOR COVID-19 SHUTDOWN DELAYS UNDER CARES ACT. |
| Apr 30, 2025 | A00001 | $45.1K | W911KB19C0001, CLR039C, POWER PLANT (LPP), CP#3, CLEAR SFS, ALASKA CR#60 (HEMP SHIELDED CABINET REPAIR), MOD A00001 |
| Sep 10, 2024 | P00061 | $249.4K | MCF DAY TANK PUMP AND BACKFLOW PREVENTER |
| Dec 20, 2023 | P00060 | $245.6K | NETWORK GATEWAYS AND BULK TANK FUEL VALVE |
| Nov 21, 2023 | P00059 | $2.4M | REPLACE ETHERNET SWITCHES PART 2 |
| Jul 15, 2022 | P00058 | $225.0K | POST BOD INTEGRATION SUPPORT |
| May 20, 2022 | P00057 | $-48.0K | DELETE CLIN 0010. THIS MODIFICATION INCLUDES A CORRECTION TO AN ERROR MADE ON P00056 |
| May 13, 2022 | P00056 | $-18.0K | DELETE CLIN 0009 (UNSUITABLE SOILS) |
| Mar 30, 2022 | P00055 | $225.0K | REPLACE ETHERNET SWITCHES |
| Mar 14, 2022 | P00054 | $32.0K | RADAR STATUS POINTS |
| Mar 10, 2022 | P00053 | $3.2M | GENERATOR COOLANT AND VENT PIPING REWORK |
| Dec 17, 2021 | P00051 | $0 | OPENING 106A & EXPOSED PLYWOOD |
| Dec 17, 2021 | P00052 | $0 | CHANGES IN RELAY SETTINGS |
| Oct 7, 2021 | P00050 | $48.4K | PARTIAL SUSPENSION OF WORK - FUEL SYSTEM |
| Sep 15, 2021 | P00049 | $156.2K | 10" GLYCOL CHILLED WATER PIPING REVISION |
| Aug 19, 2021 | P00048 | $250.0K | GENERATOR COOLANT AND VENT PIPING REWORK |
| Jul 1, 2021 | P00047 | $30.4K | FIREWORKS PROGRAMMING |
| Jun 28, 2021 | P00046 | $42.1K | CORROSION PROTECTION AND FIRESTOPPING |
| Jun 24, 2021 | P00045 | $25.3K | DGE 7L BLACK START |
| Jun 15, 2021 | P00044 | $50.0K | 10IN GLYCOL CHILLED WATER PIPING REVISION CI-0048-1 |
| May 28, 2021 | P00043 | $113.6K | LOOP ROAD ASPHALT PATCHES |
| May 26, 2021 | P00041 | $41.3K | CORROSION PROTECTION EXHAUST TOWER |
| May 26, 2021 | P00042 | $568.5K | BULK FUEL TANK SEISMIC REA |
| May 21, 2021 | P00038 | $117.4K | DIESEL GENERATOR EXHAUST PIPE SUPPORT |
| May 21, 2021 | P00039 | $50.7K | CMU HILTI BOLT EMBEDMENT AND LINK FLOOR |
| May 21, 2021 | P00040 | $13.4K | DECONFLICT PCMS IP ADDRESSES |
| May 20, 2021 | P00037 | $145.6K | DH GLYCOL PIPE BRACE/FUEL FLOW INDICATOR |
| May 17, 2021 | P00036 | $224.1K | MISSION CRITICAL-1 DUCT BRACING |
| May 14, 2021 | P00035 | $63.8K | MOVE TEMPORARY TENT SHELTER |
| May 11, 2021 | P00034 | $785.9K | GENERATOR CRANKCASE VENTILATION - P & I |
| May 10, 2021 | P00033 | $86.6K | PNEUMATIC HEMP DOOR 107A |
| May 7, 2021 | P00032 | $199.9K | REDUNDANT CPU MODULE PAIR |
| May 6, 2021 | P00025 | $56.5K | POWER PLANT (LPP) - FIRST RESPONDER ALMR RADIO SYSTEM |
| May 6, 2021 | P00026 | $91.2K | POWER PLANT (LPP) - LPP ROOF BIRD MITIGATION |
| May 6, 2021 | P00027 | $31.3K | POWER PLANT (LPP) - FINISHED FLOOR AT DIAGONAL TUBE BRACE |
| May 6, 2021 | P00028 | $82.5K | POWER PLANT (LPP) - FUEL TANK SEISMIC PART 2 |
| May 6, 2021 | P00029 | $11.4K | POWER PLANT (LPP) - SEQUENCE OF OPERATIONS |
| May 6, 2021 | P00030 | $209.8K | POWER PLANT (LPP)- PROFINET REMOTE I/O & CONTROLLER |
| May 6, 2021 | P00031 | $23.8K | POWER PLANT (LPP) |
| May 5, 2021 | P00019 | $0 | POWER PLANT (LPP) - COVID-19 CONTRACT TIME EXTENSION, NO CHANGE TO CONTRACT PRICE, DRAWINGS, OR SPECIFICATIONS |
| May 5, 2021 | P00020 | $40.0K | POWER PLANT (LPP) - PART ONE OF FUEL TANK SEISMIC MODIFICATION |
| May 5, 2021 | P00021 | $10.6K | POWER PLANT (LPP) - INSTALL MAINTENANCE ACCESS HATCHES ON EACH ROOF DRAIN |
| May 5, 2021 | P00022 | $8.9K | POWER PLANT (LPP) - PROVIDE AND INSTALL A MONORAIL SYSTEM WITH MANUAL HOIST OVER FUEL PUMP AREA |
| May 5, 2021 | P00023 | $17.2K | POWER PLANT (LPP) - DAY TANK PIPE SUPPORTS |
| May 5, 2021 | P00024 | $41.2K | POWER PLANT (LPP) - NON-STRUCTURAL SEISMIC NAMEPLATE |
| May 4, 2021 | P00017 | $23.3K | POWER PLANT (LPP)CHANGE ORDER FOR EXTERIOR FOUNDATIONS FOR 8TH GENERATOR |
| May 4, 2021 | P00018 | $18.4K | POWER PLANT (LPP) - DAY TANK ROOM STRUCTURAL STEEL |
| Jul 14, 2020 | P00014 | $71.0K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00014, CHANGE ITEM NO. 00020 (ROOF EXPANSION JOINT) |
| Jul 14, 2020 | P00015 | $25.5K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00015, CHANGE ITEM NO. 00019 (RADIATOR PIPE SUPPORT FOUNDATIONS) |
| Jul 14, 2020 | P00016 | $521.7K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00016, CHANGE ITEM NO. 00005-2 (00005-2 DISTRICT HEAT&ELECTRIC DUCTBANK-PART 2) |
| Jun 11, 2020 | P00013 | $140.6K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00013, CHANGE ITEM NO. 00013 (WEATHER VESTIBULE ROOF DRAINS) |
| Jun 8, 2020 | P00012 | $8.8K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00012, CHANGE ITEM NO. 00010 (VESTIBULE AREA SPRINKLER SYSTEMS) |
| May 29, 2020 | P00011 | $132.8K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00011, CHANGE ITEM NO. 00008 (LIGHTNING MASTS FOUNDATIONS) |
| Apr 15, 2020 | P00010 | $59.1K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00009, CHANGE ITEM NO. 00004 (STRUCTURAL STEEL SHOP DRAWING REVISIONS) |
| Apr 14, 2020 | P00009 | $6.8K | LRDR POWER PLANT (LPP, MODIFICATION NO. P00008, CHANGE ITEM NO. 00012 (CORIOLIS METER) |
| Dec 20, 2019 | P00007 | $4.4K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00007, CHANGE ITEM NO. 00009 (INDUSTRIAL POE INJECTORS) |
| Dec 6, 2019 | P00006 | $43.5K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00006, CHANGE ITEM NO. 00007 (TANK OVERFILL PREVENTION VALVE) |
| Nov 4, 2019 | P00005 | $-298.4K | LRDR POWER PLANT (LPP), MODIFICATION NO. P00005, CHANGE ITEM NO. 00002 (RMF/CYBER SECURITY CHANGES) |
| Oct 2, 2019 | P00004 | $25.0K | POWER PLANT (LPP), MODIFICATION NO. P00004, CHANGE ITEM NO. 00006-1 (GENERATOR CRANKCASE VENTILATION-PART 1) |
| Sep 25, 2019 | P00003 | $250.0K | POWER PLANT (LPP), MODIFICATION P00003, CHANGE ITEM NO. 00005-1 (DISTRICT HEAT&ELECTRIC DUCTBANK-PART 1) |
| Aug 5, 2019 | P00002 | $0 | POWER PLANT (LPP), MODIFICATION P00002, CHANGE ITEM NO. 00003 (REVISIONS TO CC FAR 52.211-10 AND 12. |
| Aug 2, 2019 | P00001 | $4.4K | POWER PLANT (LPP), MODIFICATION NO. P00001, CHANGE ITEM NO. 00001 - SHARED PARTNERING COST |
| Mar 8, 2019 | 0 | $128.7M | LRDR POWER PLANT (LPP) CONSTRUCTION |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.