Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW2SN ENDIST ALASKA
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-aside8A COMPETED
Pricing typeFIRM FIXED PRICE
Obligations$10.7M
Current contract value$10.7M
Potential contract value / ceiling$10.7M
Start dateSep 1, 2021
Current end dateJan 11, 2023
Potential end dateJan 11, 2023
Latest award activityFeb 12, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 12 of 12 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Feb 12, 2025P00004$533.9KCONSTRUCT CATM RANGE - 0021 FINAL GLOBAL PAYMENT FOR CR003 AND CR009.
Feb 11, 2025A00031$10.0KCONSTRUCT CATM RANGE - CI0027 POL2 BUFFER
Feb 11, 2025P00003$360.6KCONSTRUCT CATM RANGE - 0003-2 PART PAYMENT OF GLOBAL SETTLEMENT CR003 AND 0009-3 SAME.
Feb 10, 2025A00027$9.0KCONSTRUCT CATM RANGE - FIRE WATER TANK SYSTEM
Feb 10, 2025A00028$6.2KCONSTRUCT CATM RANGE - VARIATION IN ESTIMATED QUANTITY ACTION
Feb 10, 2025A00029$9.5KCONSTRUCT CATM RANGE - CI0025 DOOR 104 ES IN LIEU OF MAGLOCK
Feb 10, 2025A00030$52.0KCONSTRUCT CATM RANGE - CI0022 SMART METER FOR PANEL H
Feb 7, 2025A00023$-1.5KCONSTRUCT CATM RANGE - CHANGE
Feb 7, 2025A00024$46.8KCONSTRUCT CATM RANGE - CLIN 0003 REVISED TEMP UTILITIES 2.0
Feb 7, 2025A00025$39.3KCONSTRUCT CATM RANGE - POL SOIL DISPOSAL CI0018
Feb 7, 2025A00026$1.4KCONSTRUCT CATM RANGE - ADD DOOR CLOSURE TO ARCTIC ENTRY DOOR CI0023
Feb 3, 2025A00022$10.0KCONSTRUCT CATM RANGE - EIE391 CR0016-1 FIRE WATER MONITORING SYSTEM