Federal contract award

W911KB23C0027

FTW469 CONSTRUCT PP BARRACKS B3718

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW2SN ENDIST ALASKA
NAICS236220 — Commercial and Institutional Building Construction
PSCY1FC — CONSTRUCTION OF TROOP HOUSING FACILITIES
Parent award / vehicleNot reported
Set-aside8A COMPETED
Pricing typeFIRM FIXED PRICE
Obligations$30.7M
Current contract value$30.7M
Potential contract value / ceiling$30.7M
Start dateSep 22, 2023
Current end dateFeb 2, 2026
Potential end dateFeb 2, 2026
Latest award activityMay 18, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 23 of 23 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 18, 2026P00007$354.7KCONTRACT FOR FTW469 REPAIR BARRACKS B3718 AT FORT WAINWRIGHT, ALASKA REFERENCE NO. R00002100005-4 MECHANICAL REVISIONS PART 2
May 15, 2026A00016$108.0KCONTRACT FOR FTW469 REPAIR BARRACKS B3718 AT FORT WAINWRIGHT, ALASKA REFERENCE NO. R00002100005-4 MECHANICAL REVISIONS PART 2
Mar 27, 2026P00006$1.4MCONTRACT FOR FTW469 REPAIR BARRACKS B3718 AT FORT WAINWRIGHT, ALASKA REFERENCE NO. R00002100005-4 MECHANICAL REVISIONS PART 2
Mar 3, 2026A00015$216.4KCONTRACT FOR FTW469 REPAIR BARRACKS B3718 AT FT. WAINWRIGHT REFERENCE NO. R00020A00015 CR#00004-2, CR#00024
Sep 30, 2025A00014$200.3KFTW469 REPAIR BARRACKS B3718 A00014 CR#17, 18, 20-2, 21
Sep 3, 2025P00005$1.6MFTW469 REPAIR BARRACKS B3718 P00005 CR#5-3 MECHANICAL REVISIONS PART 1C
Jul 24, 2025A00013$20.6KFTW469 REPAIR BARRACKS B3718 A00013 CR#22 THIRD FLOOR AHU DUCT CONFLICT
Jun 24, 2025A00012$409.0KFTW469 REPAIR BARRACKS B3718 A00012 CR#013 BUILDING ACCESS DELAY
Jun 17, 2025A00011$100.1KFTW469 REPAIR BARRACKS B3718 A00011 CR#23 ADD HEAT MAIN EXPANSION JOINTS
Jun 10, 2025A00010$91.1KFTW469 REPAIR BARRACKS B3718 A00010 CR#19 ADD CONCRETE STOOPS
May 28, 2025P00004$94.5KFTW469 REPAIR BARRACKS B3718 P00004 CR#05-2 MECHANICAL REVISIONS 5-1B
May 9, 2025A00009$292.2KFTW469 CONSTRUCT PP BARRACKS B3718 A00009 CR#7 ADDITIONAL CLIN0005 QUANTITY
Apr 21, 2025A00008$35.0KFTW469 CONSTRUCT PP BARRACKS B3718 A00008 CR#20-1 ARMS VAULT REDESIGN
Apr 18, 2025A00007$77.3KFTW469 CONSTRUCT PP BARRACKS B3718 A00007 CR#12-2 STRUCTURAL REVISIONS
Apr 8, 2025A00006$348.3KFTW469 CONSTRUCT PP BARRACKS B3718 A00006 CR#11 REMOVE PLYWOOD BEHIND GWB
Nov 20, 2024A00004$125.8KCONSTRUCT PP BARRACKS B3718
Nov 20, 2024A00005$7.4KCONSTRUCT PP BARRACKS B3718 - CI00014 EXTERIOR PAINTING PCB TESTING
Sep 27, 2024A00002$52.7KFTW469 CI#1,2,3,9 A00002
Sep 20, 2024P00003$1.1MP00003 CI #04-1, #05-1, & #12-1
May 2, 2024A00001$31.3KCONSTRUCT PP BARRACKS B3718
Apr 22, 2024P00002$32.6KFTW469 CONSTRUCT PP BARRACKS B3718 - OPTIONS MOD FOR CLINS 0004 AND 0005
Feb 1, 2024P00001$0FTW469 CONSTRUCT PP BARRACKS B3718 - ADMIN MODIFICATION P00001 TO ADJUST CLIN NUMBERING
Sep 26, 20230$24.0MFTW469 CONSTRUCT PP BARRACKS B3718