IAW THE ATTACHED SOW: THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO REPLACE THE EXISTING 2 PIPE BOILER/CHILLER FAN COIL SYSTEM WITH A WATER SOURCE HEAT PUMP SYSTEM.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QM MICC-FT BENNING |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z1AZ — MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | W911SF20D0003 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $2.1M |
| Current contract value | $2.1M |
| Potential contract value / ceiling | $2.1M |
| Start date | Sep 19, 2025 |
| Current end date | Apr 28, 2026 |
| Potential end date | Apr 28, 2026 |
| Latest award activity | Sep 29, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 29, 2025 | P00001 | $0 | IAW THE ATTACHED SOW: THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO REPLACE THE EXISTING 2 PIPE BOILER/CHILLER FAN COIL SYSTEM WITH A WATER SOURCE HEAT PUMP SYSTEM. |
| Sep 18, 2025 | 0 | $2.1M | IAW THE ATTACHED SOW: THE OBJECTIVE OF THIS MECHANICAL SCOPE IS TO REPLACE THE EXISTING 2 PIPE BOILER/CHILLER FAN COIL SYSTEM WITH A WATER SOURCE HEAT PUMP SYSTEM. |