Federal contract award
W9123620C2025
CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING (PHASE 2) AND HANGAR FACILITY (PHASE 3) AT (JEB) EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST NORFOLK |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1AZ — CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $149.0M |
| Current contract value | $149.0M |
| Potential contract value / ceiling | $149.0M |
| Start date | Oct 13, 2020 |
| Current end date | Jan 12, 2025 |
| Potential end date | Jan 12, 2025 |
| Latest award activity | Jun 5, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 132 of 132 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 5, 2026 | A00109 | $13.7K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO ADD DROPPED CEILING AND REVISE SPRINKLERS AND LIGHTING AT THE FIRING RANGE QUEUING AREA. |
| May 21, 2026 | A00108 | $27.2K | FORT EUSTIS, BATTALION COMPLEX PHASE 3, FIELD MODIFICATION TO REVISE BREAKERS IN ASSOCIATED PANEL FOR HRC-1 AND TO PROVIDE A SEQUENCE OF OPERATION FOR THE HANGAR DESTRATIFICATION FANS. |
| May 13, 2026 | A00107 | $203.6K | FORT EUSTIS, BATTALION COMPLEX PHASE 3, FIELD MODIFICATION TO REVISE NATURAL GAS STUB UPS AT GENERATORS, ADD GYPBOARD TO ASP-3 CEILINGS, RECONFIGURE HVAC DUCT, REVISE TELECOMMUNICATION IN COOP, ADD DUCT SMOKE DETECTORS, AND ADD SIDEWALK. |
| Apr 14, 2026 | A00106 | $220.0K | FORT EUSTIS, BATTALION COMPLEX PHASE 3, FIELD MODIFICATION TO PROVIDE UPGRADES TO THE NATURAL GAS SYSTEM AND TO PROVIDE AN ADDITIONAL FUME EXTRACTOR ARM. |
| Apr 2, 2026 | P00022 | $1.2M | CONSTRUCT BATTALION COMPLEX PHASE 2 AND 3 |
| Mar 19, 2026 | A00105 | $61.8K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE GROUNDING FOR THE COOP SHIELDING, ELECTRICAL REVISIONS IN AREA A, A REVISED ROLL-UP DOOR AT THE AID STATION, AND REVISED TELECOMMUNICATIONS OUTLET BOXES. |
| Mar 17, 2026 | A00104 | $66.4K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE CONDENSATE PUMPS FOR THE DOAS UNITS IN PHASE 2 AND TO PROVIDE ELECTRICAL RECEPTACLES FOR THE FIRING RANGE TARGETING SYSTEM. |
| Mar 5, 2026 | A00103 | $87.7K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE CONDENSATE PUMPS FOR THE DOAS UNITS IN PHASE 2 AND TO PROVIDE ELECTRICAL RECEPTACLES FOR THE FIRING RANGE TARGETING SYSTEM. |
| Feb 26, 2026 | A00102 | $158.5K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO PROVIDE ADDITIONAL EMI/RF SHIELDING FOR THE COOP CALL CENTER. |
| Dec 4, 2025 | A00101 | $39.0K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS TO PARTITION WALLS IN THE OPERATIONS BUILDING. |
| Nov 20, 2025 | A00100 | $26.8K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE MISSING ROOF DECK EDGE MATERIAL, CIRCUIT BREAKERS, HANDRAILING, AND A MISSING CANOPY LIGHT |
| Oct 24, 2025 | A00099 | $120.9K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS THE CAA OUTLETS, CABLE TRAY REDISTRIBUTION, AND EXTERIOR FLASHING DETAILS. |
| Sep 29, 2025 | A00098 | $14.4K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE AN EMERGENCY EXIT SIGN AND RELOCATE MASS NOTIFICATION SPEAKERS IN LOG WAREHOUSE. |
| Sep 25, 2025 | A00097 | $112.5K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS TO THE CLOUD CEILINGS IN THE LOBBY AND TEAM ROOM. |
| Sep 18, 2025 | A00096 | $0 | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO ADD 10 CALENDAR DAYS TO THE CONTRACT DUE TO ADVERSE WEATHER INCURRED JAN 2021 THROUGH MAY 2025 |
| Sep 11, 2025 | P00021 | $4.2M | W9123620C2025 P00021 - BATTALION COMPLEX PHASE 2 AND 3 - RESOLVE FAA AND PILE CAP DELAY FOR MANGANARO, HEAT EXCHANGER, AND TEMPORARY HEAT WINTERIZATION REA AND RE-ESTABLISH THE CONTRACT COMPLETION DATE. |
| Sep 8, 2025 | P00020 | $661.5K | W9123620C2025 P00020 CONSTRUCTION OF BATTALION COMPLEX - M0112 STORMWATER REALIGNMENT, M0187 PH3 DECK ANGLE STEEL, M0185 LAUNDRY ROOM DRAIN, M0156 P-8 THRU P-16 SOO, M0006-3E DOMINION PILE, M0008-2E DOMINION FAA, M0188 WILLIAMSON AND WILMER REA. |
| Aug 19, 2025 | A00095 | $197.1K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION DIRECTING THE CONTRACTOR TO PROCEED REDESIGNED SHIELDING IN THE COOP |
| Aug 4, 2025 | P00019 | $0 | P00019 IS HEREBY MODIFIED TO IMPLEMENT CLASS DEVIATION 2025-O0003 AND CLASS DEVIATION O0004. |
| Jul 23, 2025 | A00094 | $59.4K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION, M0170-2/A00094 IS TO PROVIDE AN NTP FOR PREPARATION WORK AND MATERIAL PURCHASE FOR LONG LEAD ITEMS. |
| Jul 9, 2025 | A00092 | $30.4K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION TO ADD FIRE PROTECTION TO GYM STEEL COLUMN, REVISE THERAPY TUB SERVICE LINES, AND ADD A HEATER TO ROOM 1300. |
| Jul 9, 2025 | A00093 | $24.5K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATION TO REVISE THE SEQUENCE OF OPERATIONS FOR EXHAUST FANS AND REVISE LOUVER CONFLICTS FOR THE HVAC SYSTEM |
| Jul 2, 2025 | A00091 | $152.2K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, MODIFICATION A00091 IS HEREBY MODIFIED TO SETTLE COSTS RELATED TO THE SUBCONTRACTOR, RAYHAVEN, FOR THE FAA AND PILE CAP REDESIGN DELAYS. |
| Jun 25, 2025 | A00088 | $44.5K | FORT EUSTIS, BATTALION COMPLEX PHASE 2, FIELD MODIFICATION, DEMOLITION AND ADDITIONAL SUBMITTAL REVIEWS FOR A CALL CENTER REDESIGN EFFORT |
| Jun 25, 2025 | A00089 | $46.6K | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING & HANGAR FACILITY AT JOINT BASE EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. FIELD MODIFICATION TO PROVIDE REVISIONS TO THE COOLING TOWER MAKE-UP WATER SYSTEM AND THE SUMP PUMP CONTROLS. |
| Jun 25, 2025 | A00090 | $7.7K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FEILD MODIFICATION FOR A NECESSARY FENCE LINE ACCESS GATE AND STATIC DISSIPATIVE FLOORING IN A TELECOM ENTRANCE FACILITY (TEF) |
| Jun 24, 2025 | P00018 | $1.4M | BATTALION COMPLEX PHASE II AND III MODIFICATION P00018 IS HEREBY MODIFIED TO SETTLE COSTS RELATED TO THE SUBCONTRACTOR, JRC MECHANICAL FOR THE FAA AND PILE CAP REDESIGN DELAY. |
| May 29, 2025 | A00087 | $73.5K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATION TO REVISE/REMOVE CEILINGS IN TELECOM ROOMS TO AVOID SPACE CONFLICTS. |
| May 23, 2025 | A00086 | $34.9K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATIONS M0132 TITLE: PH3 WSHP CONFLICTS, M0160 TITLE: PH2 AC-1 MISSING REQUIREMENTS, M0162 TITLE: ADD DUCT SECURITY BARS AT CAA, M0163 TITLE: PH3 ADD FD TO AREA T EYEWASH |
| May 14, 2025 | A00085 | $65.5K | FORT EUSTIS, BATTALION COMPLEX PHASES 2 AND 3, FIELD MODIFICATION, PROVIDE ADDITIONAL REQUIRED ELECTRICAL FEEDERS FOR 12 (EA) GENERATORS. |
| Apr 17, 2025 | A00084 | $58.2K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATION TO PROVIDE ADDITIONAL ELECTRICAL AND TELECOM OUTLETS FOR PHASE 2 AND CORRECT CONFLICTS WITH CANOPY STEEL AND BLOCKWORK FOR PHASE 3. |
| Apr 2, 2025 | A00082 | $44.1K | FT EUSTIS, BATTALION COMPLEX PH 2 AND 3, FIELD MODIFICATION, MOISTURE PROTECTION ON CANOPIES |
| Apr 2, 2025 | A00083 | $27.3K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATION, REVISED CANOPY LIGHTS, REVISED KITCHEN MAKE UP AIR UNIT, HVAC SECURITY DUCTBARS |
| Mar 25, 2025 | A00081 | $46.4K | FORT EUSTIS, BATTALION COMPLEX PHASE 2 AND 3, FIELD MODIFICATION, PROVIDE GENERATOR MAINTENANCE DURING GOVERNMENT DELAY PERIOD. |
| Mar 6, 2025 | P00017 | $198.4K | W9123620C2025 P00017 IS HEREBY MODIFIED TO PROVIDE THE DEFERRED PAYMENT TO THE PRIME CONTRACTOR FOR THE SUBCONTRACTOR, CLEVELAND CEMENT CONTRACTOR'S REA RELATED TO THE FAA AND PILE CAP DELAY. |
| Feb 5, 2025 | P00016 | $1.1M | BATTALION COMPLEX PHASE II AND III MODIFICATION P00016 - SUBCONTRACTOR JC DRISKILL PORTION OF THE FAA AND PILE DELAY SETTLEMENT. |
| Jan 31, 2025 | A00080 | $128.8K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, FIELD MODIFICATION |
| Jan 21, 2025 | A00078 | $24.2K | BATTALION COMPLEX PHASE 2 - OPS BUILDING FIELD MODIFICATION TO ADD CASED OPENING BETWEEN THE KO AND RM OFFICE SUITES. |
| Jan 21, 2025 | A00079 | $119.1K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Nov 25, 2024 | A00077 | $978 | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION. |
| Nov 18, 2024 | A00076 | $131.8K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Nov 11, 2024 | A00075 | $6.4K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Oct 28, 2024 | A00074 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG PAINT BOOTH, FIELD MODIFICATION |
| Oct 22, 2024 | A00073 | $50.1K | FT. EUSTIS, VA. BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATIONS. |
| Oct 21, 2024 | A00072 | $64.1K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Sep 26, 2024 | A00071 | $34.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Sep 25, 2024 | A00069 | $61.0K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Sep 25, 2024 | A00070 | $68.0K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Sep 23, 2024 | A00066 | $2.1K | FT. EUSTIS, VA, BATTALION COMPLEX PH2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Sep 23, 2024 | A00067 | $42.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Sep 23, 2024 | A00068 | $40.3K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Sep 19, 2024 | P00015 | $633.5K | W9123620C2025 P00015 IS HEREBY MODIFIED TO REVISE THE DESIGN AND INSTALL THE SAND OIL SEPARATOR ON THE PROJECT. THE ELEVATION OF THE ORIGINAL SAND OIL SEPARATOR WAS DESIGNED BELOW THE NECESSARY LENGTHS NEEDED TO SUPPORT THE BATTALION COMPLEX. |
| Aug 30, 2024 | A00065 | $219.2K | FT. EUSTIS, VA, BATTALION COMPLEX PH2&3, HANGER BUILDING, FIELD MODIFICATION |
| Aug 28, 2024 | A00064 | $32.6K | FT. EUSTIS, VA, BATTALION COMPLEX PH2&3, HANGER, FIELD MODIFICATION |
| Aug 27, 2024 | A00062 | $121.4K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE2&3, OPS BUILDING, FIELD MODIFICATION |
| Aug 27, 2024 | A00063 | $180.0K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BUILDING, FIELD MODIFICATION |
| Aug 26, 2024 | A00061 | $47.5K | FT. EUSTIS, VA, BATTALION COMPLEX PH2&3, OPS BUILDING, FIELD MODIFICATION |
| Aug 23, 2024 | A00060 | $17.3K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION |
| Jun 6, 2024 | A00059 | $73.0K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS AND HANGAR BUILDINGS, ROOF DECK EDGE CHANGES MODIFICATION |
| May 31, 2024 | A00058 | $132.4K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, SANITARY PIPE DIFFERING SITE CONDITION MODIFICATION |
| May 28, 2024 | A00057 | $14.6K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| May 22, 2024 | A00056 | $56.5K | FT. EUSTIS, VA, BATTALION COMPLEX PH2&3, HANGAR BLDG, FIELD MODIFICATION |
| May 21, 2024 | A00055 | $11.2K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| May 15, 2024 | A00054 | $14.6K | FT. EUSTIS, VA, BATTALION COMPLEX PH2&3, OPS BUILDING, FIELD MODIFICATION. |
| May 14, 2024 | A00053 | $230.2K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| May 13, 2024 | A00052 | $48.5K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Apr 17, 2024 | A00050 | $15.4K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION |
| Mar 25, 2024 | A00051 | $48.6K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2 & 3, OPS BUILDING, FIELD MODIFICATION |
| Feb 14, 2024 | P00014 | $685.8K | MOD P00014 IS BEING ISSUED TO SETTLE THE PRIME CONTRACTOR'S TIME AND OVERHEAD COST FOR THE CONTRACT DELAY RELATED TO PILE CAP RE-DESIGN CHANGES. |
| Dec 22, 2023 | A00049 | $2.7K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BUILDING, FIELD MODIFICATION. |
| Dec 21, 2023 | A00048 | $36.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Dec 20, 2023 | A00046 | $99.8K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION. |
| Dec 20, 2023 | A00047 | $194.0K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION. |
| Dec 15, 2023 | A00045 | $36.8K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Dec 14, 2023 | A00044 | $23.0K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BUILDING BLDG, FIELD MODIFICATION |
| Dec 8, 2023 | A00043 | $249.8K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, FIELD MODIFICATION |
| Dec 7, 2023 | P00013 | $534.8K | MOD P00013 - HEAT EXCHANGER UPGRADES |
| Nov 8, 2023 | P00012 | $2.5M | MODIFICATION P00012 - SUBCONTRACTOR (CLEVELAND CEMENT CONTRACTORS) DELAY SETTLEMENT |
| Oct 16, 2023 | A00042 | $40.8K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFCATION |
| Sep 29, 2023 | P00011 | $0 | MODIFICATION P00011 - ADDITIONAL 19 TV3S AND BRACKETS |
| Sep 28, 2023 | A00040 | $18.6K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGER, FIELD MODIFICATION. M0054, M0068. |
| Sep 28, 2023 | A00041 | $11.6K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BUILDING, FIELD MODIFICATION, M0027, M0075. |
| Sep 27, 2023 | A00039 | $216.0K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, OPS BUILDING, FIELD MODIFICATION. |
| Sep 24, 2023 | A00038 | $38.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, FIELD MODIFICATION |
| Sep 7, 2023 | A00037 | $308.4K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BUILDING, FIELD MODIFICATION |
| Aug 30, 2023 | A00035 | $22.2K | FT. EUSTIS, VA, HANGAR AND OPS BLDGS, FIELD MODIFICATION |
| Aug 30, 2023 | A00036 | $49.1K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BLDG, FIELD MODIFICATION |
| Aug 13, 2023 | A00034 | $84.1K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Jul 27, 2023 | A00033 | $41.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Jul 10, 2023 | A00032 | $321.0K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Jun 29, 2023 | A00031 | $96.9K | FT. EUSTUS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Jun 7, 2023 | A00030 | $28.5K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, FIELD MODIFICATION. |
| Jun 5, 2023 | A00029 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, FIELD MODIFICATION |
| May 23, 2023 | A00028 | $33.5K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, OPS BUILDING, FIELD MODIFICATION. |
| May 19, 2023 | A00027 | $47.5K | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| May 15, 2023 | A00026 | $113.3K | FT. EUSTIS, VA, BN CMPX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| May 9, 2023 | A00025 | $-383 | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Apr 15, 2023 | A00024 | $42.3K | FT. EUSTIS, VA BN CMPX PH 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Mar 23, 2023 | P00010 | $0 | MOD 10 - INCLUDE DEFENSE PRIORITY AND ALLOCATION REQUIREMENTS |
| Mar 1, 2023 | A00023 | $36.2K | FT. EUSTIS, VA, PHASE 2&3, FIELD MODIFICATION |
| Feb 12, 2023 | A00022 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, FIELD MODIFICATION. |
| Feb 9, 2023 | A00021 | $102.9K | FT. EUSTIS, VA, BATTALION COMPLEX, PH. 2 & 3, FIELD MODIFICATION |
| Feb 7, 2023 | P00009 | $9.6M | PAINT BOOTH SHOP MODIFICATION |
| Dec 29, 2022 | P00008 | $816.0K | P00008 FEDERAL AVIATION ADMINISTRATION PERMIT FOR PERMANENT STRUCTURES TIME DELAY FOR THE PRIME CONTRACTOR |
| Dec 13, 2022 | A00020 | $209.0K | FT. EUSTIS, VA, BN COMPLEX HANGAR BLDG, FIELD MODIFICATION. |
| Dec 7, 2022 | P00007 | $0 | ADMINISTRATIVE MOD TO CORRECT APPROPRIATION DATA |
| Dec 2, 2022 | A00019 | $6.4K | FT. EUSTIS, VA, HANGAR BLDG, FIELD MODIFICATION. |
| Nov 21, 2022 | A00018 | $99.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH.2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Oct 10, 2022 | A00015 | $-46.2K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, HANGAR BLDG, FIELD MODIFICATION. |
| Sep 30, 2022 | P00006 | $3.7M | P00006 AWARD OPTION 0023 FOR FURNITURE, FIXTURES, AND EQUIPMENT AND TO INCORPORATE TV REQUIREMENTS AS REFLECTED BY THE ATTACHED TECHNICAL DOCUMENTS. |
| Sep 28, 2022 | A00017 | $172.8K | FT. EUSTIS, VA, BATTALION COMPLEX HANGAR BLDG, FIELD MODIFICATION. |
| Aug 15, 2022 | A00016 | $85.7K | FT. EUSTIS, VA BATTALION COMPLEX PH. 2&3, OPS BUILDING, HANGER, FIELD MODIFICATION. |
| Jul 6, 2022 | P00005 | $110.1K | MODIFICATION P00005 - EXERCISE OPTIONS 0024, 0025, 0033, 0034 |
| May 26, 2022 | A00014 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, HANGAR BLDG, FIELD MODIFICATION |
| May 11, 2022 | A00013 | $132.0K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, OPS BLDG, FIELD MODIFICATION |
| Mar 30, 2022 | A00012 | $-83.8K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Mar 29, 2022 | A00011 | $67.6K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, SITE WORK, PHASE 3, FIELD MODIFICATION |
| Mar 3, 2022 | A00010 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3,HANGAR BLDG, FIELD MODIFICATION |
| Mar 2, 2022 | A00009 | $182.2K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, OPS BUILDING, FIELD MODIFICATION |
| Mar 1, 2022 | A00008 | $146.7K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Feb 22, 2022 | A00007 | $23.1K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2 AND 3,HANGAR BLDG, FIELD MODIFICATION |
| Feb 18, 2022 | P00004 | $2.8M | HANGAR BLDG |
| Jan 19, 2022 | A00006 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Jan 13, 2022 | A00005 | $11.5K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, HANGAR BLDG, FIELD MODIFICATION |
| Oct 25, 2021 | A00004 | $203.3K | FT. EUSTIS, VA, BATTALION COMPLEX PHASE 2&3,HANGAR BLDG, FIELD MODIFICATION |
| Oct 13, 2021 | A00003 | $0 | FT. EUSTIS, VA, BATTALION COMPLEX PH 2&3, FIELD MODIFICATION |
| Oct 4, 2021 | A00002 | $153.8K | FT. EUSTIS, VA BATTALION COMPLEX PH. 2, FIELD MODIFICATION |
| Jul 26, 2021 | A00001 | $13.9K | FT. EUSTIS, VA, BATTALION COMPLEX PH. 2&3, FIELD MODIFICATION |
| Jul 9, 2021 | P00003 | $1.4M | EXERCISE OF OPTIONS MOD BNC |
| Jan 11, 2021 | P00002 | $0 | BATTALION (AVIATION) COMPLEX NOTICE TO PROCEED (NTP) |
| Sep 30, 2020 | P00001 | $0 | HANGAR BLDG |
| Sep 29, 2020 | 0 | $104.5M | CONSTRUCTION OF THE BATTALION COMPLEX OPERATIONS BUILDING (PHASE 2) AND HANGAR FACILITY (PHASE 3) AT (JEB) EUSTIS-LANGLEY, NEWPORT NEWS, VIRGINIA. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.