Federal contract award
W9123623C2001
DEEP CREEK BRIDGE CONSTRUCTION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST NORFOLK |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1LB — CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $62.7M |
| Current contract value | $62.7M |
| Potential contract value / ceiling | $62.7M |
| Start date | Apr 19, 2023 |
| Current end date | Sep 12, 2026 |
| Potential end date | Sep 12, 2026 |
| Latest award activity | Jun 4, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 23 of 23 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 4, 2026 | A00018 | $8.5K | A. SCOPE OF WORK CHANGE: 00025 TITLE: REA: BSCL PIER PHS 1 WALL OPENING SIZE APROVIDE ALL MATERIAL, EQUIPMENT, AND LABOR REQUIRED TO PERFORM THE FOLLOWING WORK:SETTLEMENT FOR LETTER S-0024; BASCULE PIER PHASE I WALL OPENING SIZE AND LOCATION DESIGN D |
| May 28, 2026 | A00017 | $200.0K | A. SCOPE OF WORK CHANGE: 00025 TITLE: REA: BSCL PIER PHS 1 WALL OPENING SIZE APROVIDE ALL MATERIAL, EQUIPMENT, AND LABOR REQUIRED TO PERFORM THE FOLLOWING WORK:SETTLEMENT FOR LETTER S-0024; BASCULE PIER PHASE I WALL OPENING SIZE AND LOCATION DESIGN D |
| Jan 12, 2026 | A00016 | $0 | A. SCOPE OF WORK CHANGE: 00025 TITLE: REA: BSCL PIER PHS 1 WALL OPENING SIZE APROVIDE ALL MATERIAL, EQUIPMENT, AND LABOR REQUIRED TO PERFORM THE FOLLOWING WORK:SETTLEMENT FOR LETTER S-0024; BASCULE PIER PHASE I WALL OPENING SIZE AND LOCATION DESIGN D |
| Sep 30, 2025 | P00004 | $0 | DEEP CREEK BRIDGE CONSTRUCTION W9123623C2001 P00004 IS HEREBY MODIFIED TO INCORPORATE BUY AMERICAN EXCEPTION FOR SPLIT HVAC UNITS. |
| Sep 29, 2025 | A00013 | $10.7K | BRIDGE CONSTRUCTION |
| Sep 29, 2025 | A00014 | $94.2K | BRIDGE CONSTRUCTION |
| Sep 29, 2025 | A00015 | $70.2K | BRIDGE CONSTRUCTION |
| Aug 22, 2025 | A00012 | $64.2K | BRIDGE CONSTRUCTION |
| Aug 11, 2025 | A00011 | $145.0K | BRIDGE CONSTRUCTION |
| Jun 30, 2025 | A00010 | $8.9K | BRIDGE CONSTRUCTION |
| Jun 30, 2025 | P00003 | $909.4K | DEEP CREEK BRIDGE REPLACEMENT - 8-INCH WATERLINE GEORGE WASHINGTON HIGHWAY SOUTH (DIRECT COSTS) |
| Jun 10, 2025 | A00009 | $20.0K | BRIDGE CONSTRUCTION |
| May 8, 2025 | A00008 | $126.4K | BRIDGE CONSTRUCTION |
| Apr 25, 2025 | A00007 | $426.7K | BRIDGE CONSTRUCTION |
| Apr 22, 2025 | A00006 | $283.0K | BRIDGE CONSTRUCTION |
| Apr 8, 2025 | A00005 | $256.3K | BRIDGE CONSTRUCTION |
| Jan 20, 2025 | A00004 | $156.8K | BRIDGE CONSTRUCTION |
| Nov 22, 2024 | P00002 | $0 | DEEP CREEK BRIDGE CONSTRUCTION PROJECT MODIFICATION P00002 PROGRESS PAYMENT AUTHORIZATION UNDER FAR 52.232-5 FOR STORED MATERIAL. |
| Sep 24, 2024 | A00003 | $3.3K | BRIDGE CONSTRUCTION |
| Feb 13, 2024 | A00002 | $24.1K | BRIDGE CONSTRUCTION |
| Oct 13, 2023 | A00001 | $50.0K | BRIDGE CONSTRUCTION |
| Jun 6, 2023 | P00001 | $0 | DCB NOTICE TO PROCEED |
| Apr 17, 2023 | 0 | $59.6M | DEEP CREEK BRIDGE CONSTRUCTION |