THE PURPOSE OF THIS PROJECT IS TO RESTORE THE COOLING TOWER SYSTEM. THE CONTRACTOR SHALL REPLACE DAMAGED PIPING WITH UPGRADED MATERIALS AND INSTALL COMPONENTS TO WITHSTAND FREEZING WEATHER AND OTHER ELEMENTS. POC IS GEORGE.JACKSON@USACE.ARMY.MIL
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SD ENDIST NORFOLK |
| NAICS | 238220 — Plumbing, Heating, and Air-Conditioning Contractors |
| PSC | Z2NZ — REPAIR OR ALTERATION OF OTHER UTILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $11.8K |
| Current contract value | $11.8K |
| Potential contract value / ceiling | $11.8K |
| Start date | Mar 18, 2026 |
| Current end date | Jun 18, 2026 |
| Potential end date | Jun 18, 2026 |
| Latest award activity | May 21, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 21, 2026 | P00001 | $2.4K | THE PURPOSE OF THIS PROJECT IS TO RESTORE THE COOLING TOWER SYSTEM. THE CONTRACTOR SHALL REPLACE DAMAGED PIPING WITH UPGRADED MATERIALS AND INSTALL COMPONENTS TO WITHSTAND FREEZING WEATHER AND OTHER ELEMENTS. |
| Mar 18, 2026 | 0 | $9.4K | THE PURPOSE OF THIS PROJECT IS TO RESTORE THE COOLING TOWER SYSTEM. THE CONTRACTOR SHALL REPLACE DAMAGED PIPING WITH UPGRADED MATERIALS AND INSTALL COMPONENTS TO WITHSTAND FREEZING WEATHER AND OTHER ELEMENTS. POC IS GEORGE.JACKSON@USACE.ARMY.MIL |