Federal contract award
W9123818F0104
IGF::OT::IGF PROJECT TITLE AND LOCATION: FOLSOM DAM RAISE PROJECT, DIKES 7 AND 8 AND MORMON ISLAND AUXILIARY DAM (MIAD); COMPLETE 35% AND 65% DESIGN, WITH OPTION FOR 95% AND 100% DESIGN.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST SACRAMENTO |
| NAICS | 541330 — Engineering Services |
| PSC | C211 — Architect - Engineer Services (including landscaping, interior layout, and designing) |
| Parent award / vehicle | W9123816D0018 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $7.6M |
| Current contract value | $7.6M |
| Potential contract value / ceiling | $7.8M |
| Start date | Aug 2, 2018 |
| Current end date | Oct 22, 2026 |
| Potential end date | Oct 22, 2026 |
| Latest award activity | Sep 11, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 2 of 2 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Sep 11, 2025 | P00011 | $486.7K | PROJECT TITLE AND LOCATION: FOLSOM DAM RAISE PROJECT, DIKES 7 AND 8 AND MORMON ISLAND AUXILIARY DAM (MIAD). THIS MODIFICATION IS ADDING TASKS 19-22 FOR DIKE 7 STORMWATER COLLECTION DESIGN, 100% DESIGN FINALIZATION, AND ADDITIONAL EDC FOR MIAD. |
| Apr 23, 2025 | P00010 | $0 | PROJECT TITLE AND LOCATION: FOLSOM DAM RAISE PROJECT, DIKES 7 AND 8 AND MORMON ISLAND AUXILIARY DAM (MIAD). THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERFORMANCE PERIOD. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.