Federal contract award
W9123823C0008
DESIGN-BID-BUILD CONSTRUCTION OF SEEPAGE CUTOFF WALL ADJACENT TO LANDWARD SIDE OF EXISTING LEVEE IN THE AMERICAN RIVER COMMON FEATURES (ARCF) NATOMAS BASIN REACH E SEGMENT. CONSTRUCTION INCLUDES OPEN TRENCH CONSTRUCTION.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST SACRAMENTO |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PC — CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $48.0M |
| Current contract value | $48.0M |
| Potential contract value / ceiling | $48.0M |
| Start date | May 1, 2023 |
| Current end date | Apr 5, 2026 |
| Potential end date | Apr 5, 2026 |
| Latest award activity | May 21, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 35 of 35 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 21, 2026 | PZ0013 | $1.2M | NATOMAS BASIN REACH E DEFINITIZING PART 2 FOR CHANGE CD 27-2 PAVING NB LEVEE RD |
| Feb 9, 2026 | P00012 | $5.2M | CD024-2/R00032/P00012 ADDITION OF BROOKFIELD BORROW SITE/REA-002 |
| Nov 25, 2025 | P00011 | $3.1M | CONTRACT NO. W9123823C0008 NATOMAS BASIN REACH E MODIFICATION NO. R00031 - ADDITIONAL BORROW MATERIAL VEQ/REA#007 |
| Nov 12, 2025 | A00021 | $197.8K | REMEDIATION OF CONTAMINATED SPOIL AT WELL #7 |
| Oct 30, 2025 | P00010 | $2.3M | SEEPAGE WALL CONST FEDERAL FUNDING |
| Aug 26, 2025 | P00009 | $549.3K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Aug 7, 2025 | P00008 | $0 | SEEPAGE WALL CONST FEDERAL FUNDING. EO MODIFICATION |
| Aug 6, 2025 | A00020 | $272.4K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Aug 4, 2025 | A00019 | $207.2K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jul 28, 2025 | P00007 | $675.0K | SEEPAGE WALL CONST NON-FEDERAL FUNDING |
| Mar 28, 2025 | A00018 | $-16.1K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Mar 4, 2025 | A00017 | $23.5K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jan 22, 2025 | A00016 | $214.6K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jan 8, 2025 | A00015 | $225.3K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Dec 18, 2024 | A00014 | $471.9K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Nov 26, 2024 | A00013 | $167.7K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Oct 10, 2024 | A00012 | $46.8K | CONTRACT FOR AMERICAN RIVER COMMON FEATURES (ARCF) NATOMAS BASIN REACH E SEEPAGE WALL CONSTRUCTION AT PLEASANT GROVE, CA. REFERENCE NO. R00018/CD023 REMOVE UTILITY POLES SOUTH OF HOWSLEY. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED. |
| Sep 30, 2024 | P00006 | $2.5M | SEEPAGE WALL CONST FEDERAL FUNDING |
| Sep 13, 2024 | A00011 | $250.0K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Sep 12, 2024 | A00010 | $25.0K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Sep 5, 2024 | P00005 | $831.8K | SEEPAGE WALL CONST FEDERAL FUNDING, CULVERT B AND D CONNECTION CHANGE CD003/R00014 |
| Aug 1, 2024 | A00009 | $250.0K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jul 31, 2024 | A00008 | $108.0K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jul 30, 2024 | A00007 | $239.2K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jul 25, 2024 | P00004 | $-1.1M | CONTRACT FOR NATOMAS BASIN E AT PLEASANT GROVE, CA. REFERENCE NO. R00013/CD009 DELETE WELL #3 FROM CONTRACT. |
| Jun 7, 2024 | P00003 | $1.0M | SEEPAGE WALL CONST FEDERAL FUNDING |
| May 17, 2024 | A00006 | $-14.7K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Apr 29, 2024 | A00005 | $247.3K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Apr 22, 2024 | A00004 | $240.9K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Apr 2, 2024 | A00003 | $204.3K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Oct 17, 2023 | A00002 | $200.0K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Aug 28, 2023 | P00002 | $0 | SEEPAGE WALL CONST FEDERAL FUNDING |
| Jul 27, 2023 | A00001 | $69.0K | SEEPAGE WALL CONST FEDERAL FUNDING |
| Apr 27, 2023 | P00001 | $0 | SEEPAGE WALL CONST FEDERAL FUNDING |
| Apr 10, 2023 | 0 | $27.9M | DESIGN-BID-BUILD CONSTRUCTION OF SEEPAGE CUTOFF WALL ADJACENT TO LANDWARD SIDE OF EXISTING LEVEE IN THE AMERICAN RIVER COMMON FEATURES (ARCF) NATOMAS BASIN REACH E SEGMENT. CONSTRUCTION INCLUDES OPEN TRENCH CONSTRUCTION. |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.