Federal contract award

W9123823C0009

PHASE 2B MARYSVILLE LEVEE EFFORTS TO STRENGTHEN THE LEVEE BY ADDITION OF THE SEEPAGE CUTOFF WALL AND INCLUDE CONSTRUCTION OF SEEPAGE BERMS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SACRAMENTO
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$17.5M
Current contract value$17.5M
Potential contract value / ceiling$17.6M
Start dateMar 27, 2023
Current end dateMar 30, 2025
Potential end dateMar 30, 2025
Latest award activityMar 31, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 8 of 8 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 31, 2026A00007$125.0KREA FOR DIFFERING SITE CONDITIONS - CONCRETE STRUCTURES DISCOVERED IN THE WEST SIDE BLANKET DRAIN.
Oct 22, 2025A00006$33.8KIMPORT ROCK STONE PROTECTION TO FIX THE RSP TRANSITION IDENTIFIED DURING THE PRE-FINAL INSPECTION, FROM APPROXIMATELY STA 256+65 TO 245+57.
Sep 30, 2025P00006$2.8MCONTRACT FOR MARYSVILLE RING LEVEE PHASE 2B AT MARYSVILLE, CA. REFERENCE NO. R00017/CD015 FINAL QUANTITY VARIATION. TOTAL CONTRACT PRICE IS INCREASED BY $2,795,901.46. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Sep 16, 2025P00005$750.9KCHANGE CD 19 - REA FOR DIFFERING SITE CONDITIONS
Jun 26, 2025A00005$9.3KPHASE 2B MARYSVILLE LEVEE EFFORTS
May 29, 2025A00004$85.0KPHASE 2B MARYSVILLE LEVEE EFFORTS
Apr 23, 2025A00003$236.0KPHASE 2B MARYSVILLE LEVEE EFFORTS
Apr 18, 2025P00004$1.2MPHASE 2B MARYSVILLE LEVEE EFFORTS R0007/CD010 UNSUITABLE GENERAL FILL MATERIAL