Federal contract award
W9123823C0014
THE SACRAMENTO WEIR WIDENING WILL REDUCE WATER SURFACE ELEVATION IN SACRAMENTO RIVER AND ALLOW WATER TO FLOW INTO THE YOLO BYPASS SYSTEM. PROJECT CONSISTS OF CONSTRUCTION OF A PASSIVE WEIR, LEVEE SETBACK, FISH PASSAGE CONTROL AMONG OTHERS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST SACRAMENTO |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Y1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $203.6M |
| Current contract value | $206.3M |
| Potential contract value / ceiling | $206.3M |
| Start date | Jun 1, 2023 |
| Current end date | Dec 2, 2026 |
| Potential end date | Dec 2, 2026 |
| Latest award activity | Jun 12, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 42 of 42 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 12, 2026 | P00011 | $7.0M | ARCF SAC BYPASS WEIR WIDENING CLIN 1047/ MOD R00047/CD054-1 (PT 1 WEIR STRUCTURAL BACKFILL)(100% NONFED) (P2 NO. 456852) |
| May 27, 2026 | PZ0010 | $187.2K | ARCF SAC BYPASS WEIR WIDENING DEFINITIZE CHANGE ORDER CD 49 - ADDITIONAL INSTRUMENTATION |
| Apr 27, 2026 | A00030 | $58.6K | ARCF SAC BYPASS WEIR WIDENING RAZOR WIRE AND AGG SURFACING |
| Apr 23, 2026 | A00029 | $15.6K | ARCF SAC BYPASS WEIR WIDENING REA FOR DIFFERING SITE CONDITIONS ENCOUNTERED DURING EXCAVATION OF A FIBER OPTIC TRENCH |
| Apr 17, 2026 | P00009 | $3.5M | UNDEFINITIZED CONTRACT ACTION TO CONSTRUCT NORTH ABUTMENT PER THE REVISED DRAWINGS AND SPECIFICATIONS PROVIDED. |
| Mar 12, 2026 | A00028 | $150.9K | IN-PROGRESS QUANTITY INCREASE OF 26,263.29 CUBIC YARD FOR SOIL TYPE 1 IN-PROGRESS QUANTITY INCREASE OF 1,379.29 CUBIC YARD FOR SOIL TYPE 4 |
| Mar 6, 2026 | P00008 | $1.6M | CD 41 / MOD REFERENCE R00040 REA BASED ON CHANGED VEHICLE BRIDGE PILE TIP ELEVATIONS FOR 51 PILES FROM AB1 THROUGH AB2 |
| Feb 24, 2026 | A00027 | $-223 | CD 45-2 / R00037 THIS MODIFICATION DEFINITIZES PREVIOUSLY EXECUTED MODIFICATION REFERENCE R00031 - PROVIDE ALL NECESSARY ITEMS REQUIRED TO INSTALL/MONITOR TWO ZERO-ANNULUS DIRECT PUSH PIEZOMETERS AT SPECIFIC LOCATIONS. |
| Feb 6, 2026 | P00007 | $4.0M | R00039 CD 40-1 AB 2 DEMOLISH EXISTING AB ABUTMENT 1. CONTRACTOR TO DEMOLISH ABUTMENT 2 TO THE EXTENTS, GRADES, AND LIMITS AS DESCRIBED IN REVISED DRAWING CD-105 AND PROCURE 173 ADDITIONAL PILES FABRICATED OF ASTM A252, GRADE 3, 60 KSI STEEL. |
| Feb 5, 2026 | A00026 | $121.3K | CONTRACT NO. W9123823C0014 ARCF SACRAMENTO BYPASS WEIR WIDENING. R00038 CD050 - UTILITY CONFLICT IN FP (RFI 229). TOTAL CONTRACT PRICE INCREASED BY $121,319.75. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Jan 29, 2026 | A00025 | $9.2K | CD 48 - GIRDER STORAGE COSTS REA STORAGE COSTS INCURRED FOR AN ADDITIONAL SEVEN MONTHS OF STORAGE FOR GIRDERS SUPPORTING SPANS C4 AND C5 |
| Nov 25, 2025 | A00024 | $299.2K | CD 44 - CHANGES TO BULKHEAD GUARDRAIL CONFIGURATION CD 47 - GOV'T DIRECTED WORK TO INVESTIGATE, ADDRESS, AND/OR MONITOR THE SETTLEMENT OF THE NORTHERN WEIR ABUTMENT |
| Nov 17, 2025 | A00023 | $53.7K | REA FOR ADDITIONAL COSTS TO OBTAIN NEW PERMIT COVERAGE AND TO MAINTAIN COMPLIANCE WITH THE PERMIT REQUIREMENTS FOR THE REMAINING DURATION OF THE CONTRACT. STATE WATER BOARD REQUIRES PERMIT COVERAGE UNDER THE 2022 CONSTRUCTION GENERAL PERMIT. |
| Nov 13, 2025 | A00022 | $150.0K | WINTERIZING EFFORTS TO PREVENT EROSION OVER THE WINTER'S RAINY SEASON WHILE THE GOVERNMENT INVESTIGATES CONCERNS REGARDING THE WEIR STILLING BASIN AND ASSOCIATED SLAB SUBGRADE. |
| Nov 5, 2025 | P00006 | $600.0K | ADDITIONAL INSTRUMENTATION AND SUBSURFACE INVESTIGATIONS ARE NECESSARY TO PROVIDE ADDITIONAL GEOTECHNICAL INFORMATION ABOUT CURRENT SUBSURFACE CONDITIONS IN ORDER TO HAVE SUFFICIENT INFORMATION FOR A REDESIGN OF THE NORTH ABUTMENT. |
| Sep 3, 2025 | A00020 | $51.5K | DELETE FIBER OPTIC VAULT PER GOVERNMENT RESPONSE TO RFI 190 |
| Sep 3, 2025 | A00021 | $51.0K | CD 45-1 INSTALL 2 PUSH-IN PIEZOMETERS DATA FROM THE INSTALLATION OF THESE PUSH-IN PIEZOMETERS WILL SUPPORT AND INFLUENCE A COURSE OF ACTION DIRECTLY RELATED TO THE RESOLUTION OF THE NORTH ABUTMENT WINGWALL SETTLEMENT/REPLACEMENT CHANGE CD 40-1. |
| Aug 19, 2025 | A00019 | $243.6K | CD 34 - DESIGN CHANGES TO SOUTH ABUTMENT APPROACH |
| Aug 12, 2025 | A00018 | $9.8K | CHANGE: CD038 TITLE: VEQ - CLIN 35 INTERIM QTY IN PROGRESS QUANTITIES FOR CLIN 35 CHANGE: CD043 TITLE: NOC 12 - PG&E SPLICE BOX REA REA FOR REDESIGN AND RE-FABRICATION REQUIRED TO COMPLY WITH DIRECTED CHANGES PER THE GOV'T RESPONSE TO RFI 179. |
| Jul 28, 2025 | A00017 | $379.5K | VARIATION IN ESTIMATED QUANTITIES - CLIN 33 SOIL TYPE 1 |
| Jul 24, 2025 | P00005 | $0 | SAC WEIR CONST - NON - FEDERAL FUNDING |
| Jul 8, 2025 | A00016 | $196.6K | ADJUSTMENT TO FINAL ESTIMATED QUANTITIES TO CLIN 79 AND AN REA FOR WORK ON EXISTING STILLING BASIN |
| May 20, 2025 | A00015 | $175.0K | PHASE 2 TOPO SURVEY REA REA FOR MULTIPLE PRE-CONSTRUCTION SURVEY VISITS RFI 158 - LIFT GATE ALIGNMENT CONFLICT IN SELECT DRAWINGS LEBLS ACCESS RD REPAIR REA REA FOR THE REPAIR AND MAINTENANCE OF THE LEBLS CONNECTION ROAD FOR DWR EMERGENCY ACCESS. |
| May 1, 2025 | A00014 | $162.6K | CD 33 - REA FOR GATE STEM/GUIDE DESIGN REVISIONS CD 35 - REA FOR GROUNDBREAKING CEREMONY STANDDOWN |
| Apr 15, 2025 | A00013 | $243.6K | CD 17 - REA FOR 86 DAYS OF PILE DRIVING EQUIPMENT STANDBY COSTS. CD 25 - REA FOR THE REMOVAL AND DISPOSAL COSTS OF UNKNOWN SUB-SURFACE CONCRETE OBSTRUCTIONS. |
| Apr 1, 2025 | A00012 | $262.6K | REA FOR DIFFERING SITE CONDITIONS BASED ON EARTHWORK AND AGGREGATE BASE DISCREPANCIES OF THE CENTRAL EMBANKMENT RAMP. |
| Mar 28, 2025 | A00011 | $33.2K | MODIFICATION FOR THE FISH LADDER TOP OF WALL THICKNESS ENGINEERING CHANGE AND SWAINSON'S HAWK BIOLOGICAL MONITORING REA |
| Feb 26, 2025 | A00010 | $40.5K | A10 | R17 - VEHICLE BRIDGE PILE HORIZONTAL TOLERANCE CHANGE |
| Feb 18, 2025 | A00009 | $370.1K | SAC WEIR CONST - NON - FEDERAL FUNDING A09/R14 - REA FOR RAILROAD EMBANKMENT & OLD RIVER RD EXCAVATION |
| Jan 21, 2025 | A00008 | $213.3K | CD 08 - DOWEL BAR MATERIAL SPECIFICATIONS CD 14 - N. ABUTMENT WING WALL REDESIGN |
| Dec 20, 2024 | A00007 | $292.0K | CD013 REA FOR VEH BRIDGE PIER REBAR CHANGES |
| Dec 18, 2024 | P00004 | $583.0K | SAC WEIR CONST - NON - FEDERAL FUNDING FISH PASSAGE PILE TIP ELEVATION CHANGE CD0010 |
| Nov 21, 2024 | A00006 | $53.3K | MOD R9/A6 BAFFLE CHANGES CREDIT, REA FOR UNKNOWN UTILITIES, REA FOR WEIR ABUTMENT FOUNDATION PREP |
| Oct 24, 2024 | A00005 | $0 | SAC WEIR CONST - NON - FEDERAL FUNDING |
| Sep 16, 2024 | P00003 | $800.0K | SAC WEIR CONST - NON - FEDERAL FUNDING CD012-1 PILE DRIVING SPEC REVISION R00007/P00003 |
| May 30, 2024 | A00004 | $49.1K | SAC WEIR CONST - NON - FEDERAL FUNDING |
| May 14, 2024 | A00003 | $202.6K | SAC WEIR CONST - NON - FEDERAL FUNDING |
| May 1, 2024 | A00002 | $43.3K | SAC WEIR CONST - NON - FEDERAL FUNDING R00004/CD004 CLIMATE CONTROLLED STORAGE |
| Apr 4, 2024 | A00001 | $59.2K | SAC WEIR CONST - NON - FEDERAL FUNDING |
| Aug 9, 2023 | P00002 | $0 | SAC WEIR CONST - NON - FEDERAL FUNDING |
| Jun 8, 2023 | P00001 | $0 | SAC WEIR CONST - NON - FEDERAL FUNDING |
| May 3, 2023 | 0 | $172.9M | THE SACRAMENTO WEIR WIDENING WILL REDUCE WATER SURFACE ELEVATION IN SACRAMENTO RIVER AND ALLOW WATER TO FLOW INTO THE YOLO BYPASS SYSTEM. PROJECT CONSISTS OF CONSTRUCTION OF A PASSIVE WEIR, LEVEE SETBACK, FISH PASSAGE CONTROL AMONG OTHERS. |
Estimated positioning window
Oct 25, 2026 – Jan 23, 2027
80/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 80/100. Available recorded signals: 75 points.
- Contract end 2026-12-02 (38 days from calculation)
- +35 points
- 4 historical awards in this buyer and category group
- +15 points
- 42 recorded award transactions
- +10 points
- Latest award action: 2026-06-12
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.