Federal contract award

W9123823C0014

THE SACRAMENTO WEIR WIDENING WILL REDUCE WATER SURFACE ELEVATION IN SACRAMENTO RIVER AND ALLOW WATER TO FLOW INTO THE YOLO BYPASS SYSTEM. PROJECT CONSISTS OF CONSTRUCTION OF A PASSIVE WEIR, LEVEE SETBACK, FISH PASSAGE CONTROL AMONG OTHERS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SACRAMENTO
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$203.6M
Current contract value$206.3M
Potential contract value / ceiling$206.3M
Start dateJun 1, 2023
Current end dateDec 2, 2026
Potential end dateDec 2, 2026
Latest award activityJun 12, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 42 of 42 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 12, 2026P00011$7.0MARCF SAC BYPASS WEIR WIDENING CLIN 1047/ MOD R00047/CD054-1 (PT 1 WEIR STRUCTURAL BACKFILL)(100% NONFED) (P2 NO. 456852)
May 27, 2026PZ0010$187.2KARCF SAC BYPASS WEIR WIDENING DEFINITIZE CHANGE ORDER CD 49 - ADDITIONAL INSTRUMENTATION
Apr 27, 2026A00030$58.6KARCF SAC BYPASS WEIR WIDENING RAZOR WIRE AND AGG SURFACING
Apr 23, 2026A00029$15.6KARCF SAC BYPASS WEIR WIDENING REA FOR DIFFERING SITE CONDITIONS ENCOUNTERED DURING EXCAVATION OF A FIBER OPTIC TRENCH
Apr 17, 2026P00009$3.5MUNDEFINITIZED CONTRACT ACTION TO CONSTRUCT NORTH ABUTMENT PER THE REVISED DRAWINGS AND SPECIFICATIONS PROVIDED.
Mar 12, 2026A00028$150.9KIN-PROGRESS QUANTITY INCREASE OF 26,263.29 CUBIC YARD FOR SOIL TYPE 1 IN-PROGRESS QUANTITY INCREASE OF 1,379.29 CUBIC YARD FOR SOIL TYPE 4
Mar 6, 2026P00008$1.6MCD 41 / MOD REFERENCE R00040 REA BASED ON CHANGED VEHICLE BRIDGE PILE TIP ELEVATIONS FOR 51 PILES FROM AB1 THROUGH AB2
Feb 24, 2026A00027$-223CD 45-2 / R00037 THIS MODIFICATION DEFINITIZES PREVIOUSLY EXECUTED MODIFICATION REFERENCE R00031 - PROVIDE ALL NECESSARY ITEMS REQUIRED TO INSTALL/MONITOR TWO ZERO-ANNULUS DIRECT PUSH PIEZOMETERS AT SPECIFIC LOCATIONS.
Feb 6, 2026P00007$4.0MR00039 CD 40-1 AB 2 DEMOLISH EXISTING AB ABUTMENT 1. CONTRACTOR TO DEMOLISH ABUTMENT 2 TO THE EXTENTS, GRADES, AND LIMITS AS DESCRIBED IN REVISED DRAWING CD-105 AND PROCURE 173 ADDITIONAL PILES FABRICATED OF ASTM A252, GRADE 3, 60 KSI STEEL.
Feb 5, 2026A00026$121.3KCONTRACT NO. W9123823C0014 ARCF SACRAMENTO BYPASS WEIR WIDENING. R00038 CD050 - UTILITY CONFLICT IN FP (RFI 229). TOTAL CONTRACT PRICE INCREASED BY $121,319.75. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION.
Jan 29, 2026A00025$9.2KCD 48 - GIRDER STORAGE COSTS REA STORAGE COSTS INCURRED FOR AN ADDITIONAL SEVEN MONTHS OF STORAGE FOR GIRDERS SUPPORTING SPANS C4 AND C5
Nov 25, 2025A00024$299.2KCD 44 - CHANGES TO BULKHEAD GUARDRAIL CONFIGURATION CD 47 - GOV'T DIRECTED WORK TO INVESTIGATE, ADDRESS, AND/OR MONITOR THE SETTLEMENT OF THE NORTHERN WEIR ABUTMENT
Nov 17, 2025A00023$53.7KREA FOR ADDITIONAL COSTS TO OBTAIN NEW PERMIT COVERAGE AND TO MAINTAIN COMPLIANCE WITH THE PERMIT REQUIREMENTS FOR THE REMAINING DURATION OF THE CONTRACT. STATE WATER BOARD REQUIRES PERMIT COVERAGE UNDER THE 2022 CONSTRUCTION GENERAL PERMIT.
Nov 13, 2025A00022$150.0KWINTERIZING EFFORTS TO PREVENT EROSION OVER THE WINTER'S RAINY SEASON WHILE THE GOVERNMENT INVESTIGATES CONCERNS REGARDING THE WEIR STILLING BASIN AND ASSOCIATED SLAB SUBGRADE.
Nov 5, 2025P00006$600.0KADDITIONAL INSTRUMENTATION AND SUBSURFACE INVESTIGATIONS ARE NECESSARY TO PROVIDE ADDITIONAL GEOTECHNICAL INFORMATION ABOUT CURRENT SUBSURFACE CONDITIONS IN ORDER TO HAVE SUFFICIENT INFORMATION FOR A REDESIGN OF THE NORTH ABUTMENT.
Sep 3, 2025A00020$51.5KDELETE FIBER OPTIC VAULT PER GOVERNMENT RESPONSE TO RFI 190
Sep 3, 2025A00021$51.0KCD 45-1 INSTALL 2 PUSH-IN PIEZOMETERS DATA FROM THE INSTALLATION OF THESE PUSH-IN PIEZOMETERS WILL SUPPORT AND INFLUENCE A COURSE OF ACTION DIRECTLY RELATED TO THE RESOLUTION OF THE NORTH ABUTMENT WINGWALL SETTLEMENT/REPLACEMENT CHANGE CD 40-1.
Aug 19, 2025A00019$243.6KCD 34 - DESIGN CHANGES TO SOUTH ABUTMENT APPROACH
Aug 12, 2025A00018$9.8KCHANGE: CD038 TITLE: VEQ - CLIN 35 INTERIM QTY IN PROGRESS QUANTITIES FOR CLIN 35 CHANGE: CD043 TITLE: NOC 12 - PG&E SPLICE BOX REA REA FOR REDESIGN AND RE-FABRICATION REQUIRED TO COMPLY WITH DIRECTED CHANGES PER THE GOV'T RESPONSE TO RFI 179.
Jul 28, 2025A00017$379.5KVARIATION IN ESTIMATED QUANTITIES - CLIN 33 SOIL TYPE 1
Jul 24, 2025P00005$0SAC WEIR CONST - NON - FEDERAL FUNDING
Jul 8, 2025A00016$196.6KADJUSTMENT TO FINAL ESTIMATED QUANTITIES TO CLIN 79 AND AN REA FOR WORK ON EXISTING STILLING BASIN
May 20, 2025A00015$175.0KPHASE 2 TOPO SURVEY REA REA FOR MULTIPLE PRE-CONSTRUCTION SURVEY VISITS RFI 158 - LIFT GATE ALIGNMENT CONFLICT IN SELECT DRAWINGS LEBLS ACCESS RD REPAIR REA REA FOR THE REPAIR AND MAINTENANCE OF THE LEBLS CONNECTION ROAD FOR DWR EMERGENCY ACCESS.
May 1, 2025A00014$162.6KCD 33 - REA FOR GATE STEM/GUIDE DESIGN REVISIONS CD 35 - REA FOR GROUNDBREAKING CEREMONY STANDDOWN
Apr 15, 2025A00013$243.6KCD 17 - REA FOR 86 DAYS OF PILE DRIVING EQUIPMENT STANDBY COSTS. CD 25 - REA FOR THE REMOVAL AND DISPOSAL COSTS OF UNKNOWN SUB-SURFACE CONCRETE OBSTRUCTIONS.
Apr 1, 2025A00012$262.6KREA FOR DIFFERING SITE CONDITIONS BASED ON EARTHWORK AND AGGREGATE BASE DISCREPANCIES OF THE CENTRAL EMBANKMENT RAMP.
Mar 28, 2025A00011$33.2KMODIFICATION FOR THE FISH LADDER TOP OF WALL THICKNESS ENGINEERING CHANGE AND SWAINSON'S HAWK BIOLOGICAL MONITORING REA
Feb 26, 2025A00010$40.5KA10 | R17 - VEHICLE BRIDGE PILE HORIZONTAL TOLERANCE CHANGE
Feb 18, 2025A00009$370.1KSAC WEIR CONST - NON - FEDERAL FUNDING A09/R14 - REA FOR RAILROAD EMBANKMENT & OLD RIVER RD EXCAVATION
Jan 21, 2025A00008$213.3KCD 08 - DOWEL BAR MATERIAL SPECIFICATIONS CD 14 - N. ABUTMENT WING WALL REDESIGN
Dec 20, 2024A00007$292.0KCD013 REA FOR VEH BRIDGE PIER REBAR CHANGES
Dec 18, 2024P00004$583.0KSAC WEIR CONST - NON - FEDERAL FUNDING FISH PASSAGE PILE TIP ELEVATION CHANGE CD0010
Nov 21, 2024A00006$53.3KMOD R9/A6 BAFFLE CHANGES CREDIT, REA FOR UNKNOWN UTILITIES, REA FOR WEIR ABUTMENT FOUNDATION PREP
Oct 24, 2024A00005$0SAC WEIR CONST - NON - FEDERAL FUNDING
Sep 16, 2024P00003$800.0KSAC WEIR CONST - NON - FEDERAL FUNDING CD012-1 PILE DRIVING SPEC REVISION R00007/P00003
May 30, 2024A00004$49.1KSAC WEIR CONST - NON - FEDERAL FUNDING
May 14, 2024A00003$202.6KSAC WEIR CONST - NON - FEDERAL FUNDING
May 1, 2024A00002$43.3KSAC WEIR CONST - NON - FEDERAL FUNDING R00004/CD004 CLIMATE CONTROLLED STORAGE
Apr 4, 2024A00001$59.2KSAC WEIR CONST - NON - FEDERAL FUNDING
Aug 9, 2023P00002$0SAC WEIR CONST - NON - FEDERAL FUNDING
Jun 8, 2023P00001$0SAC WEIR CONST - NON - FEDERAL FUNDING
May 3, 20230$172.9MTHE SACRAMENTO WEIR WIDENING WILL REDUCE WATER SURFACE ELEVATION IN SACRAMENTO RIVER AND ALLOW WATER TO FLOW INTO THE YOLO BYPASS SYSTEM. PROJECT CONSISTS OF CONSTRUCTION OF A PASSIVE WEIR, LEVEE SETBACK, FISH PASSAGE CONTROL AMONG OTHERS.

Estimated positioning window

Oct 25, 2026 – Jan 23, 2027

Recompete signal:
80/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 80/100. Available recorded signals: 75 points.

Contract end 2026-12-02 (38 days from calculation)
+35 points
4 historical awards in this buyer and category group
+15 points
42 recorded award transactions
+10 points
Latest award action: 2026-06-12
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.