Federal contract award

W9123823C0021

HILL AIR FORCE BASE BUILDING 225 AREA D ROOF REPLACEMENT AND OFFICE SPACE RENOVATION.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SACRAMENTO
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2BZ — REPAIR OR ALTERATION OF OTHER AIRFIELD STRUCTURES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$79.2M
Current contract value$79.2M
Potential contract value / ceiling$79.2M
Start dateAug 11, 2023
Current end dateJul 21, 2026
Potential end dateJul 21, 2026
Latest award activityMay 14, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 27 of 27 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 14, 2026A00022$48.3KFLAKING PAINT CONTRACT FOR B225 - ROOF REPLACEMENT AND SEISMIC UPGRADE AREA D AT HILL AIR FORCE BASE, UTREFERENCE NO. R00026
Apr 6, 2026A00021$-23.3KTELECOM OUTLETS IN CORRIDOR CREDIT CONTRACT FOR B225 - ROOF REPLACEMENT AND SEISMIC UPGRADE AREA D AT HILL AIR FORCE BASE, UTREFERENCE NO. R00025
Feb 2, 2026P00005$654.2KB225 - ROOF REPLACEMENT AND SEISMIC UPGRADE AREA D
Jan 14, 2026A00020$11.0KB225 - ROOF REPLACEMENT AND SEISMIC UPGRADE AREA D
Jan 8, 2026A00019$-22.3KR00006 SF30 PG2. A. SCOPE OF WORKVC002 ADDITIONAL MECHANICAL SCOPEITEM 1. PROVIDE MATERIAL, LABOR, AND EQUIPMENT TO REMOVE AND REPLACE THE FIRE SPRINKLER SYSTEM IN 3ADDITIONAL ROOMS (EC106A, EC106B, EC106C).ITEM 2. PROVIDE MATERIAL, LABOR, AND
Nov 18, 2025A00018$50.1KR00006 SF30 PG2. A. SCOPE OF WORKVC002 ADDITIONAL MECHANICAL SCOPEITEM 1. PROVIDE MATERIAL, LABOR, AND EQUIPMENT TO REMOVE AND REPLACE THE FIRE SPRINKLER SYSTEM IN 3ADDITIONAL ROOMS (EC106A, EC106B, EC106C).ITEM 2. PROVIDE MATERIAL, LABOR, AND
Oct 14, 2025A00017$-143.9KBUILDING 225 AREA D - ROOF REPLACEMENT R00020/VC018 LIGHTNING PROTECTION CREDIT FOR A DECREASE COST OF -$143,850.77 AND 0 CALENDAR DAYS TIME EXTENSION.
Sep 29, 2025A00016$10.0KBUILDING 225 AREA D - ROOF REPLACEMENT R00019/VC020 PAINT CHANGE FOR A COST INCREASE OF $10,029.17 AND ZERO (0) CALENDAR DAYS' TIME EXTENSION.
Jun 5, 2025A00015$-20.3KBUILDING 225 AREA D - ROOF REPLACEMENT R00018 VC017 FALL PROTECTION FOR A COST DECREASE OF -$20,311.48 AND 0 CALENDAR DAYS' TIME EXTENSION.
May 13, 2025A00014$67.7KBUILDING 225 AREA D - ROOF REPLACEMENT R00017/VC016 MOVING OF GRIDLINE 9 TEMP WALL.
Apr 3, 2025A00013$86.4KCERCLA CAP CONTRACT FOR B225 - ROOF REPLACEMENT & SEISMIC UPGRADE AREA D AT HILL AFB REFERENCE NO. R00016
Jan 7, 2025A00012$101.5KBUILDING 225 AREA D - ROOF REPLACEMENT R00015 VC013 UNFORESEEN SITE CONDITIONS
Dec 11, 2024A00011$-193.5KBUILDING 225 AREA D - ROOF REPLACEMENT REFERENCE NO. R00014 VC007 SKYLIGHT REMOVAL
Nov 26, 2024P00004$636.2KBUILDING 225 AREA D - ROOF REPLACEMENT REFERENCE NO. R00013 VC012 HOBBY SHOP TO MACHINE SHOP CONVERSION EXTEND THE POP BY 28 DAYS FROM 11 MAR 2026 TO 01 APR 2026. NOTE: SYSTEM OVERSIGHT IN A10 DIDN'T UPDATE 75 DAY POP FROM 26 DEC 2025 TO 11 MAR 2026.
Nov 18, 2024A00009$283.5KBUILDING 225 AREA D - ROOF REPLACEMENT DP3 ADDITIONAL DESIGN LABOR CONTRACT FOR B225 - ROOF REPLACEMENT & SEISMIC UPGRADE AREA D AT HILL AFB. REFERENCE NO. R00011 VC009 DP3 ADDITIONAL DESIGN LABOR
Nov 18, 2024A00010$215.7KBUILDING 225 AREA D - ROOF REPLACEMENT USER VACATING SPACE CONTRACT FOR B225 - ROOF REPLACEMENT & SEISMIC UPGRADE AREA D AT HILL AFB. REFERENCE NO. R00012 VC010 USER VACATING SPACE
Nov 14, 2024P00003$2.8MBUILDING 225 AREA D - ROOF REPLACEMENT R00010/VC006 ADDITIONAL CONSTRUCTION EFFORTS
Sep 9, 2024A00007$430.1KBUILDING 225 AREA D - ROOF REPLACEMENT R00009VC008 COMPRESSED AIR TANKS AND AIR DROPS
Sep 5, 2024A00006$67.2KBUILDING 225 AREA D - ROOF REPLACEMENT R00008/VC011 RELOCATE THE 4160V BEACON ELECTRICAL LINE.
Jul 11, 2024A00005$346.7KBUILDING 225 AREA D - ROOF REPLACEMENT R00007VC004 ADDITIONAL DESIGN FOR STEAM & CONDENSATE
Jun 28, 2024A00004$90.9KBUILDING 225 AREA D - ROOF REPLACEMENT REFERENCE NO. R00006 VC002 ADDITIONAL MECHANICAL SCOPE. TOTAL CONTRACT PRICE IS INCREASED BY $90,865.00 AND 0 CALENDAR DAYS-TIME EXTENSION.
Apr 11, 2024A00003$17.6KBUILDING 225 AREA D - ROOF REPLACEMENT VC003 ELECTRICAL & COMMUNICATION REQUIREMENTS
Apr 9, 2024A00002$69.2KBUILDING 225 AREA D - ROOF REPLACEMENT R00004 VC005 EAST EGRESS TUNNEL
Feb 1, 2024A00001$21.5KBUILDING 225 AREA D - ROOF REPLACEMENT R00003VC001 TEMP WALL
Oct 31, 2023P00002$0BUILDING 225 AREA D - ROOF REPLACEMENT - INCORPORATE CONFORMED SPEC'S INTO THE CONTRACT
Aug 9, 2023P00001$0BUILDING 225 AREA D RENOVATION AT HILL AIR FORCE BASE, UTAH. MODIFICATION P00001 ALIGNS CONTRACT PERIOD OF PERFORMANCE WITH THE DATE THE NOTICE TO PROCEED WAS RECEIVED BY THE CONTRACTOR.
Jul 24, 20230$73.6MHILL AIR FORCE BASE BUILDING 225 AREA D ROOF REPLACEMENT AND OFFICE SPACE RENOVATION.