Federal contract award
W9123823F0079
BULKHEAD GATE SURFACE PREPARATION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W075 ENDIST SACRAMENTO |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Z1KA — MAINTENANCE OF DAMS |
| Parent award / vehicle | W9123823D0012 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.2M |
| Current contract value | $1.7M |
| Potential contract value / ceiling | $1.7M |
| Start date | Oct 2, 2023 |
| Current end date | Apr 14, 2026 |
| Potential end date | Apr 14, 2026 |
| Latest award activity | Apr 23, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 23, 2026 | A00006 | $50.6K | MODIFICATION NO. R00008 - CD008 BULKHEAD LIFTING EYE INSTALLATION. CONTRACT NO. W9123823D0012 W9123823F0079 ISABELLA BULKHEAD GATE RECOATING. |
| Mar 17, 2026 | A00005 | $54.7K | W9123823D0012 W9123823F0079 ISABELLA BULKHEAD GATE RECOATING. R00007 CD007 - SUSPENSION OF WORK. TOTAL CONTRACT PRICE INCREASED BY $54,746.00.THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 31 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| Mar 13, 2026 | A00004 | $19.1K | W9123823D0012 W9123823F0079 ISABELLA BULKHEAD GATE RECOATING. R00006 - CD006 DESIGN FOR LIFTING EYES AND REINFORCEMENT. TOTAL CONTRACT PRICE INCREASED BY $19,106.00. THE CONTRACT COMPLETION DATE SHALL REMAIN UNCHANGED BY THIS MODIFICATION. |
| Sep 15, 2025 | A00003 | $0 | W9123823D0012 W9123823F0079 ISABELLA BULKHEAD GATE RECOATING. R00005 CD005 - 92-DAY CONTRACT EXTENSION. TOTAL CONTRACT PRICE REMAINS UNCHANGED. THE CONTRACT COMPLETION DATE SHALL BE EXTENDED BY 92 CALENDAR DAYS BY REASON OF THIS MODIFICATION. |
| May 16, 2025 | A00002 | $0 | R00004/CD004 6-MONTH AND 10 DAY CONTRACT TIME EXTENSION. THE CONTRACT PROJECT COMPLETION DATE IS APRIL 21, 2025. THE NEW COMPLETION DATE IS OCTOBER 31, 2025. TOTAL CONTRACT PRICE REMAINS UNCHANGED, AND COMPLETION DATE SHALL BE EXTENDED BY 193 CD. |
| Feb 20, 2025 | P00002 | $493.8K | CONTRACT NO. W9123823D0012 W9123823F0079 ISABELLA BULKHEAD GATE RECOATING. MOD NO.R00003 - CD002 BULKHEAD GATE MARINE PLANT COSTS. TOTAL CONTRACT PRICE IS INCREASED BY $493,815.56. |
| Nov 21, 2024 | A00001 | $0 | ISABELLA BULKHEAD GATE RECOATING. CONTRACT # W91238-23-D-0012, DELIVERY ORDER # W91238-23-F-0079.R00002 CD003 6 MONTH CONTRACT TIME EXTENSION. TOTAL CHANGE IN CONTRACT TIME IN INCREASED BY 182 DAYS AND COMPLETION DATE SHALL CHANGE TO APRIL 21, 2025. |
| Oct 27, 2023 | P00001 | $0 | BULKHEAD GATE SURFACE PREPARATION |
| Sep 22, 2023 | 0 | $1.0M | BULKHEAD GATE SURFACE PREPARATION |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.