Federal contract award

W9123824C0012

CONSTRUCT ELB

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SACRAMENTO
NAICS236220 — Commercial and Institutional Building Construction
PSCY1EB — CONSTRUCTION OF MAINTENANCE BUILDINGS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$23.8M
Current contract value$23.8M
Potential contract value / ceiling$23.8M
Start dateMay 15, 2024
Current end dateJan 31, 2026
Potential end dateJan 31, 2026
Latest award activityMay 8, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 17 of 17 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 8, 2026A00013$68.1KA00013/R00014 SEISMIC UPGRADES TO MECHANICAL SEISMIC UPGRADES TO MECHANICALCONTRACT FOR DVA LIVERMORE REALIGNMENT AND CLOSURE PHASE EENGINEERING AND LOGISTICS BUILDING AT FRENCH CAMP, CAREFERENCE NO. R00014
Apr 27, 2026A00012$75.8KA00012/R00013 RECEIVING 1A141 FINISHES CONTRACT FOR DVA LIVERMORE REALIGNMENT AND CLOSURE PHASE EENGINEERING AND LOGISTICS BUILDING AT FRENCH CAMP, CAREFERENCE NO. R00013
Jan 30, 2026A00011$41.0KA00011/R00011 TWO ADDITIONAL EXIT SIGNS IN 1A102 CONTRACT FOR DVA LIVERMORE REALIGNMENT AND CLOSURE PHASE EENGINEERING AND LOGISTICS BUILDING AT FRENCH CAMP, CAREFERENCE NO. R00012
Dec 19, 2025A00010$0A00010/R00010 TIME EXTENSION DUE TO OUTSTANDING RFPS CONTRACT FOR DVA LIVERMORE REALIGNMENT AND CLOSURE PHASE EENGINEERING AND LOGISTICS BUILDING AT FRENCH CAMP, CAREFERENCE NO. R00010
Dec 17, 2025A00009$81.5KA00009/R00009 INSTALL CONCRETE TRENCH DRAINS CONTRACT FOR DVA LIVERMORE REALIGNMENT AND CLOSURE PHASE EENGINEERING AND LOGISTICS BUILDING AT FRENCH CAMP, CAREFERENCE NO. R00009
Sep 9, 2025A00008$243.6KCONSTRUCT ELB
Aug 7, 2025A00007$54.7KCONSTRUCT ELB
Jun 20, 2025A00006$193.8KCONSTRUCT ELB
Jun 12, 2025A00005$261.2KCONSTRUCT ELB
Jun 5, 2025P00003$0CONSTRUCT ELB
Apr 23, 2025A00004$104.8KCONSTRUCT ELB
Apr 1, 2025A00003$87.6KCONSTRUCT ELB
Mar 3, 2025A00002$47.5KCONSTRUCT ELB
Jan 31, 2025A00001$50.0KCONSTRUCT ELB
Aug 29, 2024P00002$0CONSTRUCT ELB
Jun 13, 2024P00001$0CONSTRUCT ELB
May 15, 20240$22.5MCONSTRUCT ELB

Research next steps