Federal contract award
W9124724F0181
FZ-20029-17 REPAIR CWWF RETENTION POND
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W6QM MICC FDO FT BRAGG |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Y1PZ — CONSTRUCTION OF OTHER NON-BUILDING FACILITIES |
| Parent award / vehicle | W9124722D9001 |
| Set-aside | HUBZONE SET-ASIDE |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.3M |
| Current contract value | $1.3M |
| Potential contract value / ceiling | $1.3M |
| Start date | Jul 2, 2024 |
| Current end date | Sep 1, 2026 |
| Potential end date | Sep 1, 2026 |
| Latest award activity | May 6, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 6, 2026 | P00006 | $173.2K | THE CONTRACTOR IS DIRECTED TO RESUME ALL WORK OPERATIONS EFFECTIVE MAY 11, 2026. |
| Apr 7, 2026 | P00005 | $0 | THIS TO EXTEND THE STOP WORK UNTIL 25 MAY 2026. |
| Jan 30, 2026 | P00004 | $0 | TO ISSUE STOP WORK EFFECTIVELY IMMEDIATELY 31 OCTOBER 2025. |
| Nov 10, 2025 | P00003 | $0 | TO ISSUE STOP WORK EFFECTIVELY IMMEDIATELY 31 OCTOBER 2025. |
| Aug 5, 2025 | P00002 | $0 | TO ISSUE STOP WORK EFFECTIVELY IMMEDIATELY 31 JULY 2025. |
| Feb 26, 2025 | P00001 | $0 | FZ-20029-17 REPAIR CWWF RETENTION POND |
| Jul 19, 2024 | 0 | $1.1M | FZ-20029-17 REPAIR CWWF RETENTION POND |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.