Federal contract award

W9124C25FA081

BASE AND OPTIONS -THE CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, MATERIAL, AND COORDINATION REQUIRED TO MILL AND OVERLAY PARKING LOTS, INCLUDING FULL DEPTH PATCH AS NOTED AND COMPLETE CRACK SEALING AND RE-STRIPING AT MULTIPLE LOCATIONS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW6QM MICC-FT JACKSON
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2QA — REPAIR OR ALTERATION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)
Parent award / vehicleW9124C21D0007
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.7M
Current contract value$1.7M
Potential contract value / ceiling$1.7M
Start dateSep 22, 2025
Current end dateJun 2, 2026
Potential end dateJun 2, 2026
Latest award activityMar 10, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 10, 2026P00002$41.6KTHE CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, MATERIAL, AND COORDINATION REQUIRED TO MILL AND OVERLAY THE PARKING LOT, INCLUDING FULL DEPTH PATCH AS NOTED, AT BUILDING 4712, 4713 (MINI MALL).
Jan 16, 2026P00001$0BASE AND OPTIONS -THE CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, MATERIAL, AND COORDINATION REQUIRED TO MILL AND OVERLAY PARKING LOTS, INCLUDING FULL DEPTH PATCH AS NOTED AND COMPLETE CRACK SEALING AND RE-STRIPING AT MULTIPLE LOCATIONS.
Sep 18, 20250$1.7MBASE AND OPTIONS -THE CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, SUPPLIES, MATERIAL, AND COORDINATION REQUIRED TO MILL AND OVERLAY PARKING LOTS, INCLUDING FULL DEPTH PATCH AS NOTED AND COMPLETE CRACK SEALING AND RE-STRIPING AT MULTIPLE LOCATIONS.