Federal contract award
W9126G19C0001
PROVIDE FOR A 1,248 PERSON AIRMEN TRAINING COMPLEX, DORMITORY AND A DINING/CLASSROOM FACILITY WITH SUPPORTING FACILITIES TO INCLUDE A FREE STANDING EQUIPMENT BUILDING TO HOUSE THE MECHANICAL EQUIPMENT, WEAPONS CLEANING PAVILION, RUNNING TRACK, EXERCISE PADS, PARKING LOTS, AT/FP LOW SECURITY WALL WITH INTEGRATED STREET LIGHTS AND LANDSCAPING/IRRIGATION.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W076 ENDIST FT WORTH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1FC — CONSTRUCTION OF TROOP HOUSING FACILITIES |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $150.0M |
| Current contract value | $150.0M |
| Potential contract value / ceiling | $150.0M |
| Start date | Mar 20, 2019 |
| Current end date | Apr 23, 2023 |
| Potential end date | Apr 23, 2023 |
| Latest award activity | Apr 17, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 72 of 72 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 11, 2026 | P00020 | $0 | ATC RECRUIT DORM #5 AND DCF #3 MJ102-2 UNFORESEEN AC PIPE OVER STORM LINE G |
| Apr 17, 2026 | A00051 | $22.1K | ATC RECRUIT DORM #5 AND DCF #3 R00070 MJ102-1 UNFORESEEN AC PIPE OVER STORM LINE G |
| Mar 18, 2026 | P00019 | $7.9K | ATC RECRUIT DORM #5 AND DCF #3 MJ102-1 UNFORESEEN AC PIPE OVER STORM LINE G |
| Sep 29, 2025 | A00050 | $-76.1K | MJ095 DESCOPE CIVIL WORK BY EISA POND, MJ096 DESCOPE EAGLE ROCK, MJ097 DESCOPE OF DCF 3 HAUL ROAD |
| Aug 25, 2025 | P00018 | $9.0K | CONSTRUCT ATC DORMITORY #5 COMPLEX MJ092 REVISED STORM G LINE, STORM F DESCOPE |
| Apr 25, 2025 | A00049 | $44.4K | MJ090 INSTALLATION OF VERTICAL DRAINS MJ091 ELEVATOR PIT LIGHTING MJ093 DCF3 DOORS 100C & 100D HARDWARE |
| Aug 29, 2024 | P00017 | $0 | MJ069 ATC5 LIGHT FIXTURES, MJ075 DCF3 ACCESS CONTROL DOOR HARDWARE, MJ084 LUKE BLVD ELEVATION CHANGE, MJ088 MODIFY COOLING TOWERS |
| Mar 22, 2024 | A00048 | $0 | MJ085 FEMOYER STREET WATER TIE IN |
| Dec 1, 2023 | A00047 | $148.0K | MJ076 COOLING TOWER CHEMICAL TREATMENT MJ078 RAISE EXISTING MANHOLE BY PED BRIDGE MJ081 LOADING DOCK RESTRAINT SYSTEM |
| Nov 29, 2023 | P00016 | $649.7K | MJ079 REA 13 AND REA 33 SOIL HAUL OFF TO COVEL GARDENS |
| Sep 15, 2023 | A00046 | $10.6K | MJ077 EB TR HARD CEILING |
| Aug 25, 2023 | A00045 | $11.3K | MJ071 REFRIGERANT LEAK DETECTOR |
| Aug 15, 2023 | A00044 | $15.3K | MJ072 DCF3 CHILLED WATER SUPPLY |
| Aug 3, 2023 | A00043 | $19.8K | MJ070 DCF3 ELEV EMERGENCY BATTERY, MJ074 ROOF LIFE SAFETY CABLE |
| Jul 11, 2023 | A00042 | $12.2K | MJ068 ADDITIONAL SPRAY FOAM DCF3 MECH ROOM 215 |
| Apr 28, 2023 | A00041 | $65.6K | MJ073 ADDITIONAL SOIL HAUL OFF TO COVEL GARDEN |
| Dec 12, 2022 | A00040 | $140.0K | MJ056 ATC 5 LEVEL 5 FIRE DAMPERS ADDITION |
| Dec 7, 2022 | A00039 | $60.3K | MJ060 PRESSURE REDUCING VALVE |
| Nov 14, 2022 | A00038 | $9.2K | MJ063 MISSING INTERDUCT |
| Oct 7, 2022 | A00037 | $9.6K | MJ055 DCF 3 NORTH FACADE LOUVER MJ058 DISCREPANCY DCF 3 MISSING LOUVER/OPENING |
| Sep 27, 2022 | A00036 | $0 | MJ061 DCF ELEVATION CHANGES AND ATC CHAIR RAIL HEIGHT |
| Sep 7, 2022 | P00015 | $296.8K | MJ045-2 REA FOR SOIL HAUL OFF TO COVEL GARDENS |
| Aug 4, 2022 | A00035 | $0 | MJ057 ROOF DRAIN ELEVATION CHANGES AT ATC MJ059 DCF 3 PAINT FINISH CORRECTIONS |
| Jul 5, 2022 | A00034 | $30.6K | MJ054 ATC 5 ADDED CMU AT CHASE WALLS |
| May 24, 2022 | A00033 | $54.1K | MJ052 ATC5 PIPE BRACING CONNECTIONS |
| May 3, 2022 | A00032 | $47.8K | MJ049 WALL AND FURRING-OUT OF I-BEAM CHANGE, MJ051 SECTOR CABINET MANHOLE E-7-2 |
| May 2, 2022 | P00014 | $66.8K | MJ044-2 EB ELECTRICAL COORDINATION |
| Mar 17, 2022 | A00031 | $59.0K | MJ048 ATC FIXTURE CHANGE FOR WATER FOUNTAIN |
| Mar 11, 2022 | A00030 | $6.8K | MJ050 FEEDER CHANGE ATC 5 |
| Mar 1, 2022 | A00029 | $13.0K | MJ047 UNFORESEEN SITE CONDITION AT SUBSTATION |
| Feb 16, 2022 | A00028 | $0 | MJ046 DCF LEVEL 2 AND 3 CMU WALL TYPES |
| Jan 5, 2022 | P00013 | $149.3K | MJ040 PIPE INSULATION GROUND FLOOR ATC 5 MJ043 AMBULATORY STALL TOILET ADJUSTMENT |
| Dec 22, 2021 | P00012 | $130.2K | MJ044-1 EB ELECTRICAL COORDINATION |
| Dec 16, 2021 | P00011 | $1.4M | MJ045-1 SPOIL HAUL OFF |
| Oct 29, 2021 | A00027 | $59.0K | MJ039 COMM DUCT AND STORM DRAIN CONFLICT |
| Oct 18, 2021 | P00010 | $566.9K | MJ041 DCF 3 PLENUM CLARIFICATION |
| Aug 13, 2021 | A00026 | $183.4K | MJ032 TRANSMISSION YARD UNFORESEEN DUCT BANK |
| Jul 23, 2021 | A00025 | $8.5K | MJ034 ATC 5 UTILIDOR TERMINATION VAULT |
| Jul 9, 2021 | A00024 | $0 | MJ036 MJ037 WEATHER TIME EXTENSION MAR 21 - JUN 21 |
| May 14, 2021 | A00023 | $1.4K | MJ035 PUMPING OF SLS |
| May 10, 2021 | A00022 | $-32.0K | MJ021 PRP PIPING VARIANCE CREDIT |
| Apr 30, 2021 | A00021 | $65.2K | MJ021 COMPLETE PIT TESTING AND EVALUATION |
| Apr 27, 2021 | A00020 | $0 | MJ031 COVID-19 IMPACTS TIME EXTENSION |
| Apr 23, 2021 | A00019 | $0 | MJ029 WEATHER TIME EXTENSION JUL 20 - FEB 21 |
| Apr 21, 2021 | A00018 | $67.7K | MJ028 DCF 3 ROOF ANCHOR SUPPORTS |
| Mar 29, 2021 | P00009 | $210.8K | MJ001-3 HAUL ROAD EXTENSION |
| Mar 22, 2021 | A00017 | $55.5K | MJ015 EB1 DOMESTIC WATER ENTRY DETAIL |
| Mar 18, 2021 | P00008 | $0 | SEC 889 CLAUSE ADDITION |
| Mar 9, 2021 | A00016 | $258 | MJ013 LAVATORY SENSOR PWR AND MOVING DISCONNECT MJ019 UTILITY PRIVATIZATION CONNECTION (ELEC) MJ024 SUMP PUMP PIPING |
| Feb 4, 2021 | A00015 | $38.6K | MJ014 PLUMBING FIXTURE CHANGE AND MJ027 ADDITIONAL WELDING AT DCF 3 CONNECTIONS |
| Feb 3, 2021 | A00014 | $59.1K | MJ025 FRENCH DRAIN REMOVAL |
| Feb 2, 2021 | P00007 | $511.8K | MJ007 CYBER, LOCKS, LED, TRASH ENC USR REQ CH |
| Nov 16, 2020 | A00013 | $44.0K | MJ003 WORK ZONE FENCE RELOCATION CARSWELL AVE |
| Nov 2, 2020 | P00006 | $66.1K | MJ020 UTILITY PRIVITIZATION CONNECT (GAS) |
| Oct 23, 2020 | A00012 | $79.1K | MJ011 DOUBLE BALL JOINT FIT AND MSRY WALL-DCF3 |
| Oct 9, 2020 | A00011 | $82.5K | MJ006 DOUBLE BALL JOINT FITTING ATC5 |
| Aug 20, 2020 | A00009 | $3.0K | MJ017 REIMBURSEMENT OF PARTNERING MEETING |
| Aug 20, 2020 | A00010 | $8.6K | MJ010 RELOCATION OF GUY WIRE |
| Jul 23, 2020 | A00008 | $0 | MJ023 WEATHER TIME EXTENSION JUN 20 THROUGH JUN 20 |
| Jul 10, 2020 | A00007 | $0 | MJ022 WEATHER TIME EXTENSION MAY 20 |
| May 15, 2020 | A00006 | $0 | MJ018 WEATHER TIME EXTENSION FEB20 THROUGH APR20 |
| Apr 2, 2020 | A00005 | $-4.8K | MJ004 UV LIGHT/ELECTROSTATIC FILTER CH |
| Mar 24, 2020 | A00004 | $2.1K | MJ002 LIGHT FIXTURE CHANGES |
| Feb 27, 2020 | P00005 | $0 | MJ012 WEATHER TIME EXTENSION NOV19 THRU JAN20 |
| Feb 11, 2020 | A00003 | $114.3K | MJ008 CHROMIUM CMU AND ASBESTOS ABATEMENT |
| Dec 19, 2019 | A00002 | $0 | WEATHER TIME EXTENSION |
| Sep 18, 2019 | A00001 | $0 | WEATHER TIME EXTENSION MAR 2019 THRU JUN 2019 |
| Aug 26, 2019 | P00004 | $458.1K | I. THIS MODIFICATION IS ISSUED TO DEFINITIZE TIME AND PRICING ADJUSTMENTS FOR CONTRACT MODIFICATION W9126G19C0001, MJ001-1, P00003 DATED JULY 2, 2019. THIS IS A UNILATERAL MODIFICATION ISSUED AS AN EQUITABLE ADJUSTMENT IN TIME AND PRICE FOR THE FOLLOWING DESCRIBED WORK. THIS ACTION HAS BEEN TAKEN BY THE CONTRACTING OFFICER DUE TO FAILURE TO REACH AGREEMENT THROUGH NEGOTIATIONS. YOU ARE HEREBY NOTIFIED OF YOUR RIGHTS PURSUANT TO CONTRACT CLAUSE "DISPUTES", TO FILE A CLAIM WITH THE CONTRACTING OFFICER. II. DESCRIPTION OF CHANGE: PURSUANT TO THE CLAUSE OF THIS CONTRACT ENTITLED, "CHANGES", THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR AND MATERIAL, AND PERFORM ALL WORK NECESSARY TO ACCOMPLISH THE FOLLOWING DESCRIBED WORK. YOU ARE HEREBY NOTIFIED OF YOUR RIGHTS PURSUANT TO CONTRACT CLAUSE "DISPUTES", TO FILE A CLAIM WITH THE CONTRACTING OFFICER. |
| Jul 2, 2019 | P00003 | $458.0K | MJ001 PART 1 UCO HAUL ROAD EXTENSION |
| Apr 11, 2019 | P00002 | $0 | CONSTRUCT ATC DORMITORY #5 COMPLEX THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE PERIOD OF PERFORMANCE END DATE ON P00001 FROM 06 SEPT 2021 TO 04 SEPT 2021.ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| Mar 25, 2019 | P00001 | $0 | CONSTRUCT ATC DORMITORY #5 COMPLEX THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE PERIOD OF PERFORMANCE AS A RESULT OF THE CONTRACTOR ACKNOWLEDGMENT OF THE NTP. THE POP IS 20 MARCH 2019 THRU 06 SEPTEMBER 2021. |
| Jan 16, 2019 | 0 | $143.5M | PROVIDE FOR A 1,248 PERSON AIRMEN TRAINING COMPLEX, DORMITORY AND A DINING/CLASSROOM FACILITY WITH SUPPORTING FACILITIES TO INCLUDE A FREE STANDING EQUIPMENT BUILDING TO HOUSE THE MECHANICAL EQUIPMENT, WEAPONS CLEANING PAVILION, RUNNING TRACK, EXERCISE PADS, PARKING LOTS, AT/FP LOW SECURITY WALL WITH INTEGRATED STREET LIGHTS AND LANDSCAPING/IRRIGATION. |