Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW074 ENDIST MOBILE
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-asideSMALL BUSINESS SET ASIDE - TOTAL
Pricing typeFIRM FIXED PRICE
Obligations$7.7M
Current contract value$7.7M
Potential contract value / ceiling$7.7M
Start dateApr 27, 2023
Current end dateNov 10, 2025
Potential end dateNov 10, 2025
Latest award activityJan 22, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 16 of 16 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jan 22, 2026A00013$0GE016 TITLE: GOVERNMENT SHUTDOWN TIME EXTENSION
Sep 8, 2025A00012$3.3KGE015 TITLE: OUTSIDE AIR
Feb 20, 2025A00011$0GE013 EGLIN BASE CLOSURE III
Oct 10, 2024A00010$0GE012 EGLIN BASE CLOSURE II
Sep 24, 2024P00002$827.2KTHE PURPOSE OF THE MODIFICATION IS TO ADD ADDITIONAL FUNDS AND EXTEND DELIVERY DATE FOR BLDG 73 GE007 MULTIPLE CHANGES-INTERCONNECTION POINTS AT EGLIN AFB, FL.
Sep 13, 2024A00009$7.4KGE011 OVERHEAD COILING DOOR STRUCTURAL SUPPORT
May 31, 2024A00008$5.0KGE010 PEDESTAL PLATES AND INSTALLATION
May 28, 2024A00007$5.8KGE009 OVERHEAD COILING DOORS
Mar 20, 2024A00006$15.5KGE008 DOME BASE SUPPORT INSTALLATION
Feb 12, 2024A00005$0GE006 EGLIN BASE CLOSURE
Jan 30, 2024A00004$7.0KGE005 MULTIPLE CHANGES 3 - AIR DAMPER, ANTENNA
Jan 11, 2024A00003$40.8KGE004 MULTIPLE CHANGES 2 - DOMES, SINK, POWER
Jan 5, 2024A00002$215.4KGE003 CRAC & CRCU PROCUREMENT
Oct 25, 2023A00001$35.7KGE001 MULTIPLE CHANGES - ELECTRICAL, TERRACOTA
Jun 21, 2023P00001$0PR&C CLIN 0001
Apr 27, 20230$6.5MBUILDING 73 LAB EXPANSION EGLIN AFB FL

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.