Federal contract award
W9127S20C0008
REHABILITATE TAINTER GATES 1-4, 6, AND 7
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W076 ENDIST LITTLE ROCK |
| NAICS | 237990 — Other Heavy and Civil Engineering Construction |
| PSC | Z2KA — REPAIR OR ALTERATION OF DAMS |
| Parent award / vehicle | Not reported |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $18.2M |
| Current contract value | $18.2M |
| Potential contract value / ceiling | $18.2M |
| Start date | Nov 12, 2020 |
| Current end date | Aug 9, 2026 |
| Potential end date | Aug 9, 2026 |
| Latest award activity | Dec 9, 2025 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Dec 9, 2025 | A00012 | $0 | A. SCOPE OF WORK CLIN0014 (REPLACE SIDE SEAL ASSEMBLY) WAS NOT ADJUSTED TO ACCOUNT FOR THE INSTALLATION OF SIDE-SEALS ON GATES #9 AND #10. |
| Oct 20, 2025 | A00011 | $0 | CONTRACT FOR TAINTER GATE PAINTING, WILBER D. MILLS DAM, POOL 2, MKARNS, ARKANSAS COUNTY, ARKANSAS REFERENCE NO. R00015 CHANGE: 00010 TITLE: TIME EXTENSION |
| Sep 24, 2025 | A00010 | $-127 | MOD A00010 REVISE QUANTITIES FOR GATE 9 |
| Apr 29, 2025 | A00009 | $16.8K | 53.243CONTRACT FOR TAINTER GATE PAINTING, WILBER D. MILLS DAM, POOL 2, MKARNS, ARKANSAS COUNTY, ARKANSAS REFERENCE NO. R00013 00008 : ADDITIONAL SKIN PLATE |
| Apr 29, 2025 | P00005 | $0 | MILLS TAINTER GATE PAINTING. MODIFICATION FOR CLAUSE REVISIONS FOR CLASS DEVIATIONS 2025-O0003 AND O0004 |
| Mar 10, 2025 | A00008 | $0 | CONTRACT FOR TAINTER GATE PAINTING, WILBER D. MILLS DAM, POOL 2, MKARNS, ARKANSAS COUNTY, ARKANSAS REFERENCE NO. R00012 00007 TIME EXTENSION FOR ADDITIONAL REPAIRS |
Research next steps
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.