Federal contract award
W9127S21C0006
UNITS 1-2 GENERATOR STATOR REWIND, BEAVER POWERHOUSE. COMPLETION DUE 705 CALENDAR DAYS AFTER NTP.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W076 ENDIST LITTLE ROCK |
| NAICS | 335312 — Motor and Generator Manufacturing |
| PSC | Z2QA — REPAIR OR ALTERATION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE) |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $20.2M |
| Current contract value | $20.2M |
| Potential contract value / ceiling | $21.6M |
| Start date | Oct 1, 2021 |
| Current end date | Jun 12, 2025 |
| Potential end date | Jun 12, 2025 |
| Latest award activity | Jun 12, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 19 of 19 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 12, 2026 | P00006 | $1.3M | REA FOR U2 STATOR FRAME STIFFENING |
| Apr 21, 2026 | A00012 | $210.0K | REA FOR WATER HAMMER EVENT. |
| Oct 8, 2025 | A00011 | $261.8K | A00011 GOV COMMISSIONING PT 2, U1 BRAKES |
| Jun 27, 2025 | P00005 | $1.4M | COMPLETE SET OF STATOR COILS |
| Jun 23, 2025 | P00004 | $810.0K | COMPLETE SET OF STATOR COILS |
| Jun 16, 2025 | A00010 | $234.8K | GOV COMMISSIONING |
| Feb 19, 2025 | A00009 | $304.4K | CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00012 CC014 THRUST TUB MODIFICATION |
| Sep 13, 2024 | P00003 | $1.2M | REQUEST FOR EQUITABLE TO INCREASE CONTRACT BY $1,200,000 AND EXTEND THE CONTRACT BY 132 CALENDAR DAYS. |
| Aug 28, 2024 | A00007 | $128.3K | CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00009 CC008 REA SUSPENSION OF WORK DEWATERING FAILURE |
| Aug 28, 2024 | A00008 | $26.5K | C02 TEMPERATURE SWITCHES R00010 |
| May 24, 2024 | A00006 | $200.0K | CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00008 CC012-1 NTP STATOR FRAME STIFFENING |
| Apr 25, 2024 | A00005 | $220.6K | PAK_FOL_RINGS/ASBE_WIRE/GEN_BRK_REFURB CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00007 CC006 PACKING FOLLOWER RINGS CC009 UNIT 2 ASBESTOS WIRE REMEDIATION CC010 UNIT 2 GENERATOR BRAKE REFURBISHMENT |
| Jan 26, 2024 | A00004 | $115.7K | CONTRACT FOR FY21 BV UNITSL-2 GENERATOR STATOR REWIND. REFERENCE NO. R00006 CC004 RTD AND TGB OIL PRESSURE GAUGE |
| Jan 25, 2024 | A00003 | $288.3K | REA DIFFERING SITE CONDITIONS DELAYS CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00005 CC005 REA DIFFERING SITE CONDITIONS DELAYS |
| Dec 13, 2023 | A00002 | $231.7K | CONTRACT FOR FY21 BV UNITS1-2 GENERATOR STATOR REWIND. REFERENCE NO. R00004 CC003-2 HAZARDOUS MATERIAL CLEAN-UP |
| Jan 18, 2023 | A00001 | $200.0K | A00001 HAZARDOUS MATERIAL CLEAN-UP |
| Jun 21, 2022 | P00002 | $1.0M | UNITS 1-2 GENERATOR STATOR REWIND AT BEAVER POWERHOUSE. COMPLETION DATE 7 NOV 2023. OPTIONS 0025-0031 ARE BEING EXERCISED IN THIS MODIFICATION (P00002). |
| Mar 3, 2022 | P00001 | $424.5K | EO14042 BEAVER POWERHOUSE UNITS 1-2 GENERATOR STATOR REWIND. COMPLETION IS 706 CALENDAR DAYS FROM NOTICE OF NTP. |
| Sep 30, 2021 | 0 | $11.6M | UNITS 1-2 GENERATOR STATOR REWIND, BEAVER POWERHOUSE. COMPLETION DUE 705 CALENDAR DAYS AFTER NTP. |