Federal contract award

W9127S24F0002

UCIC MCX OFFICE AND SCADA LAB AE DESIGN

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW076 ENDIST LITTLE ROCK
NAICS541330 — Engineering Services
PSCC219 — Other Architect and Engineering Services
Parent award / vehicleW9127S23D6035
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.4M
Current contract value$1.4M
Potential contract value / ceiling$1.5M
Start dateNov 15, 2023
Current end dateJun 23, 2025
Potential end dateJun 23, 2025
Latest award activityMar 26, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 26, 2025P00006$0THE PURPOSE OF THIS MODIFICATION IS TO RAISE THE CONSTRUCTION COST LIMITATION (CCL) FROM $10,000,000 TO $13,500,000.00. AN UPDATED STATEMENT OF WORK (SOW) IS PROVIDED TO HIGHLIGHT THESE CHANGES. THIS IS A NO-COST MODIFICATION.
Dec 5, 2024P00005$145.3KUPDATE SOW, INCREASE CLIN 0001 BY $145,291.34 AND EXTEND DELIVERY DATE TO 23JUN2025
Oct 24, 2024P00004$71.6KFIRE PUMP AND WATER TANK SYSTEM TO SUPPLEMENT CITY WATER. ADD CLIN 0003 $71,561.37.
Aug 29, 2024P00003$0REVISE SCHEDULE AND EXTEND DELIVERY DATE TO 14MAR2025
Jul 25, 2024P00002$56.8KTO INCORPORATE REVISED EXHIBITS VII AND XI TO CHANGE THE DURATION FROM 3 DAYS TO 5 DAYS AND TO INCREASE CLIN0001 BY $56,771.39.
Mar 25, 2024P00001$0UCIC MCX OFFICE AND SCADA LAB AE DESIGN ADMINISTRATIVE MOD TO ADD DFARS CLAUSE 252.204-7000.
Nov 16, 20230$1.2MUCIC MCX OFFICE AND SCADA LAB AE DESIGN