SWL MINOR CONSTRUCTION SATOC #60 GATE #2 HOIST SYSTEM REPLACEMENT AT CLEARWATER LAKE DAM. WORK SHALL BE COMPLETED WITHIN 730 CALENDAR DAYS OF THE NOTICE TO PROCEED. DATES ON CAR ARE ESTIMATED.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW076 ENDIST LITTLE ROCK
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1QA — CONSTRUCTION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)
Parent award / vehicleW9127S20D0022
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$2.3M
Current contract value$2.3M
Potential contract value / ceiling$2.3M
Start dateMar 28, 2025
Current end dateJun 30, 2026
Potential end dateJun 30, 2026
Latest award activityMay 29, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 29, 2026P00002$184.8KGATE #2 HOIST ASSEMBLY REPLACEMENT, CLEARWATER DAM. TASK ORDER #60. MODIFICATION TO ADD CLIN 0008 AND INCREASE THE DELIVERY DATE BY NINETY (90) CALENDAR DAYS.
Jul 17, 2025P00001$0GATE #2 HOIST SYSTEM REPLACEMENT, CLEARWATER LOCK AND DAM - MODIFICATION TO ADD END DATE TO REFLECT ISSUANCE OF NOTICE TO PROCEED (NTP)
Mar 4, 20250$2.1MSWL MINOR CONSTRUCTION SATOC #60 GATE #2 HOIST SYSTEM REPLACEMENT AT CLEARWATER LAKE DAM. WORK SHALL BE COMPLETED WITHIN 730 CALENDAR DAYS OF THE NOTICE TO PROCEED. DATES ON CAR ARE ESTIMATED.